Framework for Traffic Management for NGED and NGET
Authority: NATIONAL GRID UK LIMITED (Public body)
What is being bought5 lots · detail below
Published requirement descriptionTo provide full Traffic Management, Traffic Control, and the hire of Traffic Light systems.
The Contractor must adhere to and fully comply with the following:
- New Roads and Street Works Act 1991
- Traffic Management Act 2004
- Traffic Signs Manual Chapter 8
- Safety at Street Works and Road Works Code of Practice (COP) as amended
- Permit schemes (especially conditions relating to traffic management)
- Highway Authority and Utilities Committee (HAUC) Advice Notes as applicable
- ARTSM (Association for Road Traffic Safety and Management) Edition 1.1
The Contractor must be able to support all specified geographical areas of National Grid UK with sufficient resources to provide Plant, Product and Design & Services to enable safe working for all road traffic scenarios.
The Contractor must provide a 24-hour 365-day service, with the ability to respond and be on-site within 2 hours of receipt of notification from NGED / NGET.
- How the procedure runs: Publication of ITT - 18th Sept 2026 Bidder acknowledgment of receipt of ITT through ARIBA - 25th Sept 2026 Last date for submission of Bidder TQs relating to Initial Tenders - 16th October 2026 Final NG responses to Bidder TQs relating to Initial Tenders - 26th October Initial Tender Closing Time - 2nd Nov 2026 Bidder Evaluation / Shortlisting - 10th Nov 2026 Tender negotiations (if required) - Late Nov 2026 Call for Final Tenders (if required) - Early Dec 2026 Last date for submission of Bidder TQs relating to Final Tenders (if required) - Dec 2026 Final NG responses to Bidder TQs relating to Final Tenders (if required) -Dec 2026 Final Tender Closing Time (if required) - Dec 2026 Notification of contract award decision- Dec 2026
CPV: Traffic control services · Traffic monitoring services
How this framework works
From the published notice- Type
- Closed framework
- Call-offs
- call-offs may be awarded directly or by further competition
- Framework period
- 5 yrs · up to 8 yrs from 2 Jan 2027
Published description of the framework
Rates to be fixed and firm and / direct allocation on best for task basis, this via Work Instruction and / or Purchase Order.
Lots and requirements (5)Procurement structure
5 lots · all with a published value · same evaluation weights on every lotEvery one of these 2 lots carries the same published figure, £1,900,000: it is the framework's maximum for the whole notice, not each lot's own budget, and no share per lot is published. The cards below say ceiling above rather than repeat it.
Lot #1/ Area 1 Wales and North West of EnglandRenewalceiling above
Wales and North West of England - Traffic Management Services as described in the Specification.
To provide full Traffic Management, Traffic Control, and the hire of Traffic Light systems.
The Contractor must adhere to and fully comply with the following:
- New Roads and Street Works Act 1991
- Traffic Management Act 2004
- Traffic Signs Manual Chapter 8
- Safety at Street Works and Road Works Code of Practice (COP) as amended
- Permit schemes (especially conditions relating to traffic management)
- Highway Authority and Utilities Committee (HAUC) Advice Notes as applicable
- ARTSM (Association for Road Traffic Safety and Management) Edition 1.1
The Contractor must be able to support all specified geographical areas of National Grid UK with sufficient resources to provide Plant, Product and Design & Services to enable safe working for all road traffic scenarios.
The Contractor must provide a 24-hour 365-day service, with the ability to respond and be on-site within 2 hours of receipt of notification from NGED / NGET.
All Staff should be legally qualified to support Street Works legislation.
The rates are to include complying with the 'Traffic Management Act 2004' and all associated secondary legislation and codes of practice, and are deemed to include for supply, delivery, installation, and collection of all apparatus.
- Condition of participationshortlisting
Technical 60%
Commercial 40% (Price 40% / Terms and Conditions PASS/FAIL)
Lot #2/ Area 2 North East of EnglandRenewalPublished value£400,000
North East of England as described in the Specification.
To provide full Traffic Management, Traffic Control, and the hire of Traffic Light systems.
The Contractor must adhere to and fully comply with the following:
- New Roads and Street Works Act 1991
- Traffic Management Act 2004
- Traffic Signs Manual Chapter 8
- Safety at Street Works and Road Works Code of Practice (COP) as amended
- Permit schemes (especially conditions relating to traffic management)
- Highway Authority and Utilities Committee (HAUC) Advice Notes as applicable
- ARTSM (Association for Road Traffic Safety and Management) Edition 1.1
The Contractor must be able to support all specified geographical areas of National Grid UK with sufficient resources to provide Plant, Product and Design & Services to enable safe working for all road traffic scenarios.
The Contractor must provide a 24-hour 365-day service, with the ability to respond and be on-site within 2 hours of receipt of notification from NGED / NGET.
All Staff should be legally qualified to support Street Works legislation.
The rates are to include complying with the 'Traffic Management Act 2004' and all associated secondary legislation and codes of practice, and are deemed to include for supply, delivery, installation, and collection of all apparatus.
- Condition of participationshortlisting
60% Technical
40% Commercial (Price 40% / Terms and Conditions PASS/FAIL)
Lot #3/ Area 3 South West of EnglandRenewalceiling above
South West of England as described in the Specification.
To provide full Traffic Management, Traffic Control, and the hire of Traffic Light systems.
The Contractor must adhere to and fully comply with the following:
- New Roads and Street Works Act 1991
- Traffic Management Act 2004
- Traffic Signs Manual Chapter 8
- Safety at Street Works and Road Works Code of Practice (COP) as amended
- Permit schemes (especially conditions relating to traffic management)
- Highway Authority and Utilities Committee (HAUC) Advice Notes as applicable
- ARTSM (Association for Road Traffic Safety and Management) Edition 1.1
The Contractor must be able to support all specified geographical areas of National Grid UK with sufficient resources to provide Plant, Product and Design & Services to enable safe working for all road traffic scenarios.
The Contractor must provide a 24-hour 365-day service, with the ability to respond and be on-site within 2 hours of receipt of notification from NGED / NGET.
All Staff should be legally qualified to support Street Works legislation.
The rates are to include complying with the 'Traffic Management Act 2004' and all associated secondary legislation and codes of practice, and are deemed to include for supply, delivery, installation, and collection of all apparatus.
- Condition of participationshortlisting
Technical 60%
Commercial (Price 40% / Terms and Conditions)
Lot #4/ Area 4 South East of EnglandRenewalPublished value£800,000
South East of England as per Specification.
To provide full Traffic Management, Traffic Control, and the hire of Traffic Light systems.
The Contractor must adhere to and fully comply with the following:
- New Roads and Street Works Act 1991
- Traffic Management Act 2004
- Traffic Signs Manual Chapter 8
- Safety at Street Works and Road Works Code of Practice (COP) as amended
- Permit schemes (especially conditions relating to traffic management)
- Highway Authority and Utilities Committee (HAUC) Advice Notes as applicable
- ARTSM (Association for Road Traffic Safety and Management) Edition 1.1
The Contractor must be able to support all specified geographical areas of National Grid UK with sufficient resources to provide Plant, Product and Design & Services to enable safe working for all road traffic scenarios.
The Contractor must provide a 24-hour 365-day service, with the ability to respond and be on-site within 2 hours of receipt of notification from NGED / NGET.
All Staff should be legally qualified to support Street Works legislation.
The rates are to include complying with the 'Traffic Management Act 2004' and all associated secondary legislation and codes of practice, and are deemed to include for supply, delivery, installation, and collection of all apparatus.
- Condition of participationshortlisting
Technical 60%
Commercial 40% (Price 40% / Term and Conditions PASS / FAIL)
Lot #5/ Area 5 West and East Midlands of EnglandRenewalPublished value£3,400,000
West and East Midlands of England as described in the Specification.
To provide full Traffic Management, Traffic Control, and the hire of Traffic Light systems.
The Contractor must adhere to and fully comply with the following:
- New Roads and Street Works Act 1991
- Traffic Management Act 2004
- Traffic Signs Manual Chapter 8
- Safety at Street Works and Road Works Code of Practice (COP) as amended
- Permit schemes (especially conditions relating to traffic management)
- Highway Authority and Utilities Committee (HAUC) Advice Notes as applicable
- ARTSM (Association for Road Traffic Safety and Management) Edition 1.1
The Contractor must be able to support all specified geographical areas of National Grid UK with sufficient resources to provide Plant, Product and Design & Services to enable safe working for all road traffic scenarios.
The Contractor must provide a 24-hour 365-day service, with the ability to respond and be on-site within 2 hours of receipt of notification from NGED / NGET.
All Staff should be legally qualified to support Street Works legislation.
The rates are to include complying with the 'Traffic Management Act 2004' and all associated secondary legislation and codes of practice, and are deemed to include for supply, delivery, installation, and collection of all apparatus.
- Condition of participationshortlisting
Technical 60%
Commercial 40% (Price 40% / Term and Conditions PASS / FAIL)
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (2)
- Technical: 60%
- Commercial: 40%
Published award criteria (2)
- Technical: Technical evaluations of Bids shall be undertaken which shall encompass levels of applicable expertise, quality of systems and capability in terms of operational service levels
- Commercial: Price score to be calculated by use of a mathematical formula which ensures that the lowest bid (pricewise) shall receive the highest score
- Price carries 40 of 100 points: a 10% discount moves about 4 points. The method statement decides this lot, not the discount.
- “Framework for Traffic Management for NGED and NGET” is a framework: the contest is a place on its panel, not a single contract: call-offs may be direct or by further competition.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Competitive flexible procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Services
- Notice status
- Closed
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Utilities
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 10 Aug 2026, 17:43 BST
- Last source update
- 4 Sept 2026, 10:48 BST
- Award evaluation window
- Submission end – 10 Dec 2026
- Authority reference
WS1245025457- FTS notice number
2026/S 000-083799- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-06e0a9Find a Tender
- How it runs
Publication of ITT - 18th Sept 2026
Bidder acknowledgment of receipt of ITT through ARIBA - 25th Sept 2026
Last date for submission of Bidder TQs relating to Initial Tenders - 16th October 2026
Final NG responses to Bidder TQs relating to Initial Tenders - 26th October
Initial Tender Closing Time - 2nd Nov 2026
Bidder Evaluation / Shortlisting - 10th Nov 2026
Tender negotiations (if required) - Late Nov 2026
Call for Final Tenders (if required) - Early Dec 2026
Last date for submission of Bidder TQs relating to Final Tenders (if required) - Dec 2026
Final NG responses to Bidder TQs relating to Final Tenders (if required) -Dec 2026
Final Tender Closing Time (if required) - Dec 2026
Notification of contract award decision- Dec 2026
How it was run
Official notice- Requests to participate (first stage)
- 7 Sept 2026, 23:59 BST
- Appointment period ends
- 7 Sept 2026, 23:59 BST
- Clarification deadline
- 7 Sept 2026, 23:59 BST
- Electronic submission
- Allowed
- Accepted languages
- en
Timeline
10 Aug 2026 → 2 Jan 2027 · 7 dates- Planning notice published72 days ago10 Aug 2026, 17:43 BST
- Next notice expected65 days ago17 Aug 2026, 23:59 BST
- Tender notice published47 days ago4 Sept 2026, 10:48 BST
- Clarification questions by44 days ago7 Sept 2026, 23:59 BST
- Admission / appointment period ends44 days ago · period end, not a bid countdown7 Sept 2026, 23:59 BST
- Today21 Oct 2026
- Award decision expected byin 51 days10 Dec 2026, 23:59 GMT
- Contract startsin 73 days2 Jan 2027
Notice history
4 events · 2 releases on Find a Tender · since 10 Aug 2026- Planned procurement notice published10 Aug 2026, 17:43 BSTUK3
- Tender notice published4 Sept 2026, 10:48 BSTUK4
- Published value published: £8,400,0004 Sept 2026, 10:48 BST
- Status changed to active4 Sept 2026, 10:48 BST
Contracting authority & participating public bodies
Official documents & specifications (5)
Official links; attachments are not copiedTender pack and attachments
- Bidding documents and specifications Onboarding to Ariba and Mandatory Questions
- Technical specifications
- Bidding documents and specifications
Notices published for this procedure
- Tender notice Tender notice on Find a Tender
- Planned procurement notice Planned procurement notice on Find a Tender