Find a Tender
planning
Official procurement procedure
Vyrnwy Frankton IEOI PQQ
Electricity distribution and related services
Electricity power lines
Engineering works and construction works
+8 more
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: GREEN GENERATION ENERGY NETWORKS CYMRU LIMITED: "Vyrnwy Frankton IEOI PQQ". Published status: planning. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | GREEN GENERATION ENERGY NETWORKS CYMRU LIMITED | Scope & Categories | Not published | Submission Window | planning No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: GREEN GENERATION ENERGY NETWORKS CYMRU LIMITED
Market Analytics
Derived from OCDS awards & bid statistics
Published history for GREEN GENERATION ENERGY NETWORKS CYMRU LIMITED. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
Not availableNo published reports
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 0 active published awards; 0 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityGREEN GENERATION ENERGY NETWORKS CYMRU LIMITED | Procedure methodNot published | Procurement categoryNot published |
Statusplanning | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published15 Dec 2025, 11:36 GMT | Last source update15 Dec 2025, 11:36 GMT | Recurring procurementNot published |
ClassificationElectricity distribution and related services, Electricity power lines, Engineering works and construction works, Poles for carrying overhead lines, Pylons, Pylons, poles and pickets, Substation equipment, Towers, lattice masts, derricks and pylons | ||
Delivery area | ||
OCIDocds-h6vhtk-05f589 | ||
What is being bought
This Invitation for Expressions of Interest (IEOI) is issued by Green GEN Cymru Limited to seek expressions of interest for the provision of the Packages 1 - 4 for the Vyrnwy Frankton Project.
Th purpose of this document is to:
a) Inform the market of:
(i) The scope of services; and
(ii) An outline of the procurement process and timeline;
b) Invite parties to express their interest in participating in the Invitation to Tender (ITT) stage for each Package; and
c) Seek preliminary responses to a Pre-Qualification Questionnaire (PQQ) to derive a shortlist of Tenderers to be invited to participate in the ITT for each Package.
1.2 Project Background
The Green GEN Cymru portfolio, Vyrnwy Frankton, is to be serviced by a 132kV high-capacity double circuit connecting into National Grid Electricity Transmission (NGET) Network. The main line comprises overhead steel lattice tower. The Green GEN Cymru contracted generation connections will be made via a network of 132kV wood pole circuits, underground cables, switching and substations.
FEED contract is in place to provide the initial design detail and is being delivered by Stantec. The consultant is undertaking the Principal Designer role during the FEED contract phase; the Principal Design role will be transferred to the Detailed Designer.
1.3 Scope
1.3.1 Package 1 - Substations
The Vyrnwy Frankton electrical network comprises 7 distinct sites, which include:
• Switching Stations
• Collector Stations
• Transformer Substations
Several sites will incorporate:
• Reactive Power Compensation Systems
• Harmonic Filtering Equipment
The Contractor is expected to design, install, construct, and commission the following but not limited to:
Civil Works
• Site platforms and foundations
• Control buildings and auxiliary structures
• Internal / External Access roads
• Transformer Bund
• Cable troughs
• Surface / Foul / Oily water drainage (as required)
• Site Security
• Water Supply
• Fire Fighting Supply
• Flood Resilience (as required)
• Landscaping / screening (as required)
• Construction Compound
Primary Works
• High-voltage switchgear
• Power transformers
• Instrument transformers
• Busbars, disconnectors, and circuit breakers
• Reactive compensation units (e.g., capacitor banks, STATCOMs)
• Harmonic filtering equipment
Secondary Works
• Protection systems (relays, merging units)
• Control systems (SCADA, RTUs, PLCs, GPS clock)
• Building Management System (HVAC, lighting, security)
• Communication infrastructure
• Metering and monitoring systems
The switching/substation sites proposed for are indicated as follows:
Site Name
Lower Frankton Switching Station
Cors y Gareg Collector Station
Llyn Lort I Energy Park Switching Station
Rhiwlas Substation
Banc Du Energy Park Switching Station
Esgair Galed Energy Park Switching Station
Waun Hesgog Energy Park Switching Station
The Contractor is expected to establish temporary working areas to include construction compounds, laydown areas, parking and welfare facilities. The Contractor is expected to provide as-built records once construction is complete.
Package 2 - Tower line
The double circuits from the NGET points of connection into mid Wales are predominantly overhead, with steel lattice towers of the L7(c) design carrying twin ACCC (Aluminium Conductor Composite Core) "Hamburg" conductors and an OPGW earth wire.
The successful contractor will be responsible for the full detailed design and construction works associated with Vyrnwy Frankton tower line needs.
The total route length of the tower line for Vyrnwy Frankton is approximately 45km.
The intent is that the following long-time items will be procured by GGC and novated to the contractor:
• Tower steel work
• ACCC phase Conductor system
Design Works:
Full tower loading and strength assessment for the initial alignments produced by the FEED contractors, to include the detailed design of any tower strengthening requirements where necessary.
The design of all tower foundations.
Full electrical clearance assessment to include conductor profiling and tower wire clearance assessments, including production of route profiles and wire clearance diagrams.
Selection of insulators and fittings to Green Gen Cymru specifications, including production of component and string drawings.
Production of sag/tension book for conductor erection.
Construction Works:
Establishment of temporary working areas and accesses to include construction compounds, laydown areas, parking, welfare facilities, offsite road improvements, haul roads, drainages (pre and post construction as required) and soil management.
Procurement of all materials and components not free-issued by Green GEN Cymru (currently anticipated to be tower steelwork, ACCC phase conductor, and ACCC phase conductor fittings).
Installation of foundations, erection of towers, conductors, earth wire, insulators and fittings.
Design and construction of any required crossing protections e.g. scaffolds for road / rail crossings.
Provision of as-built records once construction complete.
Package 3 - Underground Cable
The Vyrnwy Frankton electrical network comprises 132kV and 33kV underground cable circuits and may require section of undergrounding in some of the overhead line circuits.
The successful contractor will be responsible for the full detailed design and construction works associated with Vyrnwy Frankton underground cable needs.
There are 3.5km of 132kV cable circuit (~180MVA capacity) and 3.5km of 33kV cable circuit (~50MVA capacity) associated with the Vyrnwy Frankton portfolio. Additional undergrounding section may be required through detailed design of the overhead circuits with different capacity requirements.
Design Works:
Full cable system design from the initial assessments produced by the FEED contractor.
The electrical design to include but not limited to:
• Load and short circuit studies
• Cable sizing and selection
• Earthing/bonding design
• The civil design to include but not limited to:
• Trench and duct design
• Joint bay/link box design
• Termination structures
Construction Works:
Establishment of temporary working areas and accesses to include construction compounds, laydown areas, parking, welfare facilities, offsite road improvements, haul roads, drainages (pre and post construction as required) and soil management.
Procurement of all materials and components.
Installation of ducted cable system including trenchless methods where necessary.
Design and construction of any crossing protections/methodologies.
Provision of as-built records once construction is complete.
Package 4 - Wood Pole
The wood pole lines for Vyrnwy Frankton network will be to the ENATS 43-50 "Trident" design and strung with either the "Upas" AAAC alloy conductor or "Oslo" ACCC high-temperature low sag conductor. An additional underslung fibre-optic cable will also be used.
The successful contractor will be responsible for the full detailed design and construction works associated with Vyrnwy Frankton wood pole requirements.
There are 3 wood pole circuits associated with Vyrnwy Frankton cover a total route length of approximately 100km.
Design Works:
Full pole and steelwork loading and strength assessment for the initial alignments produced by the FEED contractors, to include the detailed design of any strengthening requirements where necessary.
The design of all foundations.
Full electrical clearance assessment to include conductor profiling and wire clearance assessments, including production of route profiles and wire clearance diagrams.
Selection of insulators and fittings to Green GEN Cymru specifications, including production of component and string drawings.
Production of sag/tension book for conductor erection.
Construction Works:
Establishment of temporary working areas and accesses to include construction compounds, laydown areas, parking, welfare facilities, offsite road improvements, haul roads, drainages (pre and post construction as required) and soil management.
Procurement of all materials and components noting that in the case of Oslo ACCC the conductor and conductor fittings are anticipated to be free-issued by Green GEN Cymru.
Installation of foundations, erection of poles, conductors, fibre cable, insulators and fittings.
Design and construction of any required crossing protections e.g. scaffolds for road / rail crossings.
Provision of as-built records once construction complete.
1.4 Key Considerations - All Packages
All Equipment specified will be compliant with relevant national/international standards (e.g. IEC and BS EN) for a tower lines, wood pole lines, underground cable and substation environments.
What changed
From the official release history
- Status changed to planning
15 Dec 2025, 11:36 GMT - Official notice release published
15 Dec 2025, 11:36 GMT - Buyer information updated
15 Dec 2025, 11:36 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedplanningPublished valueNot publishedThe source published no individual title or description for this lot.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Pipeline notice
15 Dec 2025, 11:36 GMT - Procedure published
15 Dec 2025, 11:36 GMT - engagement
25 Jan 2026, 23:59 GMT · scheduledScope of engagement is via a Invitation for Expressions of Interest (IEOI) and Pre-Qualification Questionnaire (PQQ). IEOI and PQQ response closing date is the 25th January 2026. Interested parties must complete an return an Non-disclosure Agreement before the IEOI/PQQ can be provided. Request for NDA should be submitted to - supplychain@greengencymru.com The EOI Process represents the first stage in the selection of the Preferred Tenderer and is primarily focused on company / organisational capability. A number of mandatory requirements are outlined as Mandatory Criteria' Respondents will be assessed on these on a pass / fail basis. EOI Responses will be assessed against the Evaluation Criteria outlined in Section 3.5 to select a short-list of Respondents who will be invited to participate in the ITT Stage. Respondents may be given the opportunity, at Green Gen Cymru's discretion, to give a presentation to the Evaluation Panel and advisers on their EOI Response. Green GEN Cymru present intention is to short-list a number of Respondents such that there are three, up to a maximum of four, Tenderers for each package. This number may be varied at Green GEN Cymru's sole discretion. The short-list will be informed by the responses to this EOI. Respondents will only be eligible for short-listing if they have submitted a sufficiently comprehensive EOI Response, including all of the information listed in the Documentation Checklist in Appendix A of this IEOI / PQQ.
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
GREEN GENERATION ENERGY NETWORKS CYMRU LIMITED
Contracting authority GB-COH-13060815Documents (1)
Official links; attachments are not copied
- 15 Dec 2025, 11:36 GMT
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleNot published |