Find a TenderClosedTender notice
Published 27 May 2026, 11:51 BST

Official UK procurement notice

Supply of Materials · UK public procurement notice

Official notice

Authority: Greensquareaccord (Central government)

4 lotsGoodsCompetitive flexible procedureAbove thresholdSME suitable
Final published estimate£83,200,000initial estimate £8,320,000 · 2 value updates
Submissions closed 30 Sept 2026
Lots 4see the lot list below
Contract term 5 yrsends 13 May 2032 · up to 13 May 2037 with extensions · starts 14 May 2027

What is being bought4 lots · detail below

Published requirement description

Tender for manged solution for materials supply for the in-house DLO team and wider Departments.

  • The authority expects to re-tender this requirement around 1 Apr 2032, 23:59 BST.
  • How the procedure runs: Stage 1: Invitation to Submit a Tender 1. Stage 1 commenced with the issuing of a Tender Notice and the publication of this document(s). 2. Tenders must be submitted in accordance with the Procurement Timetable and instructions set out in this document and any additional information provided. 3. A Procurement Specific Questionnaire (PSQ) has been included on Intend, all Suppliers are required to complete and return in accordance with the Procurement Timetable and instructions within this document. 4. Following the deadline for submission of initial tenders, The Authority will also undertake a review of the completed PSQ with reference to any information held on the Central Digital Platform (CDP). Responses to any Conditions of Participation will be assessed in accordance with the selection process and any selection criteria as set out in the Tender Notice, PSQ and described in this document. Following the assessment of these responses any issues identified will be communicated to the relevant suppliers. 5. Suppliers should note that the Authority reserves the right to re-assess any response to the PSQ, in light of any new relevant information that comes to the Authority's attention. Please refer to the 'Supplier eligibility' provisions in Appendix A: Procurement Terms and Conditions. 6. After the deadline for submission of initial tenders, the Authority will consider, in respect of each Supplier that submitted a tender, whether the Supplier or any related persons within its corporate group, associated persons relied on to meet the Conditions of Participation, or proposed sub-contractors, are excluded or excludable Suppliers and will consider whether to disregard the tender submitted in accordance with its obligations under the Act. If the Supplier is an excluded or excludable Supplier only by virtue of an associated person or proposed sub-contractor, the Authority will notify the Supplier of its intention to disregard its tender and provide the Supplier with reasonable opportunity to replace the associated person or sub-contractor. If as a consequence of this process the Authority disregards a tender from an excluded or excludable Supplier or is aware of an associated person or sub-contractor having been replaced, it will give notice of this fact within 30 days of its decision to the Procurement Review Unit (PRU). 7. The Authority will conduct an assessment of all tenders in order to identify the Supplier which has submitted the most advantageous tender (MAT) in accordance with the assessment methodology and Award Criteria set out in the Tender Notice and described in this document. In carrying out this assessment, the Authority will disregard any tender from a Supplier that does not satisfy the Conditions of Participation. The Authority may also disregard a tender: a. from a Supplier that is not a United Kingdom Supplier or a treaty state Supplier or that intends to sub-contract the performance of all or part of the Contract to a Supplier that is not a United Kingdom Supplier or a treaty state Supplier; or b. if the tender breaches a procedural requirement set out in the Tender Notice or associated tender documents; or c. if the tender offers a price that the Authority considers to be abnormally low for the performance of the Contract. Where the Authority considers that a price offered by a Supplier in its tender is abnormally low, the Authority will notify the Supplier and give the Supplier reasonable opportunity to demonstrate that it will be able to perform the contract for the price offered. The Authority will only disregard the tender if the Supplier cannot satisfactorily demonstrate that it will be able to perform the Contract for the price offered. 8. The Authority will assess tenders submission in accordance with the assessment process and Award Criteria set out in the Tender Notice and described in this document. The assessment process will identify which Suppliers are to be selected to participate in the Presentation stage as set out in Stage 2. 9. Once the assessment of initial tenders has concluded, Suppliers will be notified in writing whether they have successfully been invited to Stage 2. The Authority intends to shortlist a maximum of 3 Suppliers per lot to participate in the Presentation stage (dependent on % scores received). Any Suppliers not invited to participate in Stage 2 will be provided with reasons in writing to explain why they have not been successful. Stage 2: Invitation to Presentation 1. Stage 2 will commence with the issuing of a letter inviting Suppliers that have successfully passed Stage 1, and based on the criteria outlined in Appendix B, to attend one (1) or more Presentation meetings. 2. The letter will also provide details of any new information made available to Suppliers at this stage in the Procurement. 3. The letter will also describe how the Presentation will be conducted, including the location and dates for the relevant meetings, as well as the attendee arrangements. 4. Stage 2 will conclude with the issuing of letters to all participating Suppliers confirming the closure of Presentation. 5. Once the assessment has concluded, the Authority will provide an assessment summary to all Suppliers that submitted final tenders to: a. inform them whether they have been successful in being awarded the Contract. b. provide an explanation of the assessment of the Supplier's tender against the relevant Award Criteria, in accordance with the requirements of the Act. c. where different to the Supplier concerned, provide information in respect of the most advantageous tender submitted, including details of the assessment of this tender against the relevant Award Criteria and the Supplier's name. 6. Once the assessment summaries have been provided to the Suppliers that submitted final tenders, the Authority will also publish a Contract Award Notice on the CDP to commence the mandatory standstill period. 7. Subject to completion of the mandatory standstill period, Stage 2 will end with the Authority entering into the Contract with the preferred Supplier and publication of a Contract Details Notice on the CDP (within 30 days of the date on which the Contract is entered into). Where appropriate, a copy of the Contract may also be published on the CDP.

CPV: Boilers · Building fittings · Building internal fittings · Electrical supplies and accessories · Heating materials · Machine tools · Power tools

Lots and requirements (4)Procurement structure

4 lots · all with a published value (£83,200,000 together) · same evaluation weights on every lot
Lot #1Responsive Repairs Van Stock and SpecialsRenewal 5 yrsSMEPublished value£45,000,000

For the supply of Responsive Van Stocks, Core Range Items and Special Materials across all regions.

Contract period: 14 May 2027 – 13 May 2032 (5 yrs) · up to 13 May 2037 with extensionsValue: £45,000,000 exc. VAT · £54,000,000 inc. VAT
Delivery: East Midlands, West Midlands, South East, South WestEligibility: SME eligible
Extensions: Two possible extension available: - First extension for 3 years, - Second extension for 2 years.
Lot #2Electrical, Heating and BoilersRenewal 5 yrsPublished value£19,000,000

For the supply of Electrical, Heating and Gas Van Stocks, Special Materials and Boilers

Contract period: 14 May 2027 – 13 May 2032 (5 yrs) · up to 13 May 2037 with extensionsValue: £19,000,000 exc. VAT · £22,800,000 inc. VAT
Extensions: Two possible extension available: - First extension for 3 years, - Second extension for 2 years.
Lot #3Hire and ToolsRenewal 5 yrsPublished value£2,200,000

For the supply of Hire Items and DLO Power Tools

Contract period: 14 May 2027 – 13 May 2032 (5 yrs) · up to 13 May 2037 with extensionsValue: £2,200,000 exc. VAT · £2,640,000 inc. VAT
Extensions: Two possible extension available: - First extension for 3 years, - Second extension for 2 years.
Lot #4Planned and VoidsRenewal 5 yrsPublished value£17,000,000

For the supply of Kitchen and Bathroom Materials and Voids Core Range

Contract period: 14 May 2027 – 13 May 2032 (5 yrs) · up to 13 May 2037 with extensionsValue: £17,000,000 exc. VAT · £20,400,000 inc. VAT
Extensions: Two possible extension available: - First extension for 3 years, - Second extension for 2 years.

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
How bids were scored · same split on all 4 lots
Quality: 60%Price: 40%
Published award criteria (2)
  • Quality: Quality Questions as per ITT
  • Price: Price as per the Pricing Schedules
What this means for your bid
  • Price carries 40 of 100 points: a 10% discount moves about 4 points. The method statement decides this lot, not the discount.

Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.

Procedure terms & legal framework

From the official record
Procedure method
Competitive flexible procedure
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Procurement category
Goods
Notice status
Closed
Procurement threshold
Above threshold (FTS publication)
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
Yes · next expected 1 Apr 2032
First published
27 May 2026, 11:51 BST
Last source update
19 Aug 2026, 16:02 BST
Award evaluation window
Submission end – 15 Dec 2026
Authority reference
ITT541
FTS notice number
2026/S 000-079136
Latest notice
Tender notice (UK4)
Classification (CPV)
BoilersBuilding fittingsBuilding internal fittingsElectrical supplies and accessoriesHeating materialsMachine toolsPower tools
Delivery area
East Midlands (UKF)West Midlands (UKG)South East (UKJ)South West (UKK)
Official registry OCID
ocds-h6vhtk-06a5e9 Find a Tender
How it runs

Stage 1: Invitation to Submit a Tender

  1. Stage 1 commenced with the issuing of a Tender Notice and the publication of this document(s).
  2. Tenders must be submitted in accordance with the Procurement Timetable and instructions set out in this document and any additional information provided.
  3. A Procurement Specific Questionnaire (PSQ) has been included on Intend, all Suppliers are required to complete and return in accordance with the Procurement Timetable and instructions within this document.
  4. Following the deadline for submission of initial tenders, The Authority will also undertake a review of the completed PSQ with reference to any information held on the Central Digital Platform (CDP). Responses to any Conditions of Participation will be assessed in accordance with the selection process and any selection criteria as set out in the Tender Notice, PSQ and described in this document. Following the assessment of these responses any issues identified will be communicated to the relevant suppliers.
  5. Suppliers should note that the Authority reserves the right to re-assess any response to the PSQ, in light of any new relevant information that comes to the Authority's attention. Please refer to the 'Supplier eligibility' provisions in Appendix A: Procurement Terms and Conditions.
  6. After the deadline for submission of initial tenders, the Authority will consider, in respect of each Supplier that submitted a tender, whether the Supplier or any related persons within its corporate group, associated persons relied on to meet the Conditions of Participation, or proposed sub-contractors, are excluded or excludable Suppliers and will consider whether to disregard the tender submitted in accordance with its obligations under the Act. If the Supplier is an excluded or excludable Supplier only by virtue of an associated person or proposed sub-contractor, the Authority will notify the Supplier of its intention to disregard its tender and provide the Supplier with reasonable opportunity to replace the associated person or sub-contractor. If as a consequence of this process the Authority disregards a tender from an excluded or excludable Supplier or is aware of an associated person or sub-contractor having been replaced, it will give notice of this fact within 30 days of its decision to the Procurement Review Unit (PRU).
  7. The Authority will conduct an assessment of all tenders in order to identify the Supplier which has submitted the most advantageous tender (MAT) in accordance with the assessment methodology and Award Criteria set out in the Tender Notice and described in this document. In carrying out this assessment, the Authority will disregard any tender from a Supplier that does not satisfy the Conditions of Participation. The Authority may also disregard a tender:

a. from a Supplier that is not a United Kingdom Supplier or a treaty state Supplier or that intends to sub-contract the performance of all or part of the Contract to a Supplier that is not a United Kingdom Supplier or a treaty state Supplier; or

b. if the tender breaches a procedural requirement set out in the Tender Notice or associated tender documents; or

c. if the tender offers a price that the Authority considers to be abnormally low for the performance of the Contract. Where the Authority considers that a price offered by a Supplier in its tender is abnormally low, the Authority will notify the Supplier and give the Supplier reasonable opportunity to demonstrate that it will be able to perform the contract for the price offered. The Authority will only disregard the tender if the Supplier cannot satisfactorily demonstrate that it will be able to perform the Contract for the price offered.

  1. The Authority will assess tenders submission in accordance with the assessment process and Award Criteria set out in the Tender Notice and described in this document. The assessment process will identify which Suppliers are to be selected to participate in the Presentation stage as set out in Stage 2.
  2. Once the assessment of initial tenders has concluded, Suppliers will be notified in writing whether they have successfully been invited to Stage 2. The Authority intends to shortlist a maximum of 3 Suppliers per lot to participate in the Presentation stage (dependent on % scores received). Any Suppliers not invited to participate in Stage 2 will be provided with reasons in writing to explain why they have not been successful.

Stage 2: Invitation to Presentation

  1. Stage 2 will commence with the issuing of a letter inviting Suppliers that have successfully passed Stage 1, and based on the criteria outlined in Appendix B, to attend one (1) or more Presentation meetings.
  2. The letter will also provide details of any new information made available to Suppliers at this stage in the Procurement.
  3. The letter will also describe how the Presentation will be conducted, including the location and dates for the relevant meetings, as well as the attendee arrangements.
  4. Stage 2 will conclude with the issuing of letters to all participating Suppliers confirming the closure of Presentation.
  5. Once the assessment has concluded, the Authority will provide an assessment summary to all Suppliers that submitted final tenders to:

a. inform them whether they have been successful in being awarded the Contract.

b. provide an explanation of the assessment of the Supplier's tender against the relevant Award Criteria, in accordance with the requirements of the Act.

c. where different to the Supplier concerned, provide information in respect of the most advantageous tender submitted, including details of the assessment of this tender against the relevant Award Criteria and the Supplier's name.

  1. Once the assessment summaries have been provided to the Suppliers that submitted final tenders, the Authority will also publish a Contract Award Notice on the CDP to commence the mandatory standstill period.
  2. Subject to completion of the mandatory standstill period, Stage 2 will end with the Authority entering into the Contract with the preferred Supplier and publication of a Contract Details Notice on the CDP (within 30 days of the date on which the Contract is entered into). Where appropriate, a copy of the Contract may also be published on the CDP.

How it was run

Official notice
Run through: In-tend · Who buys & how to bid on In-tend
Supplier login requiredElectronic submission allowedLanguage: EN
Access & registration note: Free · one account per buying organisation's portal · reCAPTCHA on signup
Submission deadline
30 Sept 2026, 12:00 BST
Clarification deadline
18 Sept 2026, 17:00 BST
Submission channel
Official e-sourcing portal
Electronic submission
Allowed
Accepted languages
en
Detailed submission instructions & authority contactsFrom official release

All submissions to be received through our InTend Portal - in-tendhost.co.uk/greensquare ↗

Timeline

27 May 2026 → 14 May 2027 · 8 dates
  1. Planning notice published152 days ago
    27 May 2026, 11:51 BST
  2. Market engagement137 days ago
    10 Jun 2026, 23:59 BST

    GSA is keen to listen to the views of the UK supply chain and interested suppliers, on suggestions and recommendations to help frame our approach. We aim to invite interested suppliers to a circa 90 minute online meeting (facilitate via MS Teams) as follows:

    • Introductions
    • GSA Brief on proposals and current position
    • How to engage with GSA on this opportunity
    • Open Q&A Forum

    The MS Teams session is planned for 10am on the 11th June and interested parties are requested to indicate their availability to attend this single opportunity session and provide email addresses of attendees to [email protected] by the deadline of 12pm (noon) on 10th June to be included.

    Questionnaire/Survey

    To support interaction and allow potential bidders to provide their views on approach to market and also innovative ideas for mutual benefit, a questionnaire is attached to help guide discussion, but we ask please do not be constrained by the questions asked, as we really wish to use this opportunity to hear from those with significant experience in the sector. Please provide response of the questionnaire to the above email address by the above deadline.

  3. Tender notice published67 days ago
    19 Aug 2026, 15:51 BST
  4. Next notice expected54 days ago
    1 Sept 2026, 23:59 BST
  5. Clarification questions by37 days ago
    18 Sept 2026, 17:00 BST
  6. Submission deadline26 days ago
    30 Sept 2026, 12:00 BST
  7. Today
    26 Oct 2026
  8. Award decision expected byin 51 days
    15 Dec 2026, 23:59 GMT
  9. Contract startsin 200 days
    14 May 2027, 00:00 BST

Notice history

8 events · 3 releases on Find a Tender · since 27 May 2026
  1. Preliminary market engagement notice published
    27 May 2026, 11:51 BST
    UK2
  2. Tender notice published
    19 Aug 2026, 15:51 BST
    UK4
  3. Published value updated to £8,320,000
    19 Aug 2026, 15:51 BST
    was £76,425,861
  4. Status changed to active
    19 Aug 2026, 15:51 BST
  5. Procurement method changed
    19 Aug 2026, 15:51 BST
  6. Deadline published: 30 Sept 2026, 12:00 BST
    19 Aug 2026, 15:51 BST
  7. Tender notice published
    19 Aug 2026, 16:02 BST
    UK4
  8. Published value updated to £83,200,000
    19 Aug 2026, 16:02 BST
    was £8,320,000
Published amendments (1)

Error in publishing Contract values and lot values, only one year was included. Now updated to include 10 years.

Contracting authority & participating public bodies

GREENSQUAREACCORD LIMITED

Contracting authorityPublic authority - sub-central government GB-COH: RS027052 · GB-PPON: PPDT-5615-BGVM Second Floor, 10 Brindleyplace, Birmingham, West Midlands, B1 2JBContact email

Official documents & specifications (4)

Official links; attachments are not copied

Tender pack and attachments

Notices published for this procedure

  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Preliminary market engagement notice planningPreliminary market engagement noticeUK2Preliminary market engagement notice on Find a Tender