US_22103 Replacement IT Network Infrastructure - Internal Campus Enabling Works

Construction consultancy services
Construction management services
Construction supervision services
+6 more
Published value
Not published
Submission deadline Not published
Lots published3
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: University of Sussex: "US_22103 Replacement IT Network Infrastructure - Internal Campus Enabling Works". Published status: complete. Published value: Value not published. 3 published lots. Submission deadline not published. See the official notice for participation instructions.
Contracting AuthorityUniversity of SussexScope & CategoriesNot publishedSubmission Window
complete
No deadline published
Submission GatewayDirect notice routeLegal Basis & RegimeStandard procurementEstimated Value (exc. VAT)Not published
Bidder Intelligence · Authority Profile: University of Sussex
Market Analytics
View Authority Profile →
Derived from OCDS awards & bid statistics
Published history for University of Sussex. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Requires at least 5 comparable procedures
Competition Density
14Bids / Report
0% of reports have one bid
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate available
Payment Terms
Check noticePublished terms
Payment obligations depend on the applicable regime and contract. Consult the official documents.
Coverage: 3 active published awards; 3 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityUniversity of Sussex
Procedure methodNot published
Procurement categoryNot published
Statuscomplete
Framework / DPSNot published
CompetitionNot published
Above thresholdNot published
Legal basisNot published
Tender period startsNot published
Clarification deadlineNot published
Electronic submissionNot published
Submission languagesNot published
Published14 Oct 2024, 10:34 BST
Last source update14 Oct 2024, 10:34 BST
Recurring procurementNot published
ClassificationConstruction consultancy services, Construction management services, Construction supervision services, Construction work, Installation of cable infrastructure, Installation of cable laying, Installation of computer cabling, Mechanical installations, Other building completion work
Delivery area
OCIDocds-h6vhtk-0346f0
What is being bought
This notice of tender is for the delivery of the internal enabling works for the replacement of the University’s IT Network Infrastructure. This is a highly visible flagship programme for the provision of a modern, secure, high speed wired and wireless campus data network for the entire UoS Falmer Campus. The upgrade of the network infrastructure is instrumental to the University of Sussex achieving its strategic objectives, and central to the delivery of strategic developments in the ITS and Estates roadmap. The project driver being in direct response to negative feedback from the National Student Survey. This works package will therefore deliver the following scope of works: • Design and delivery of independent power supplies for each ITS network equipment room (195 No.) • Design and delivery of cooling systems for critical ITS network equipment room (81 No.) • Fibre data cabling install, internal and external cable runs (Whole Campus) • Fabric building changes for associated fibre and power cabling install (Whole Campus)
What changed
From the official release history
  1. Status changed to complete
    14 Oct 2024, 10:34 BST
  2. Official notice release published
    14 Oct 2024, 10:34 BST
  3. Submission deadline changed to published date
    14 Oct 2024, 10:34 BST
  4. Buyer information updated
    14 Oct 2024, 10:34 BST
  5. Status changed to active
    15 Jun 2022, 16:10 BST
  6. Official notice release published
    15 Jun 2022, 16:10 BST
  7. Submission deadline changed to 18 Jul 2022, 12:00 BST
    15 Jun 2022, 16:10 BST
  8. Buyer information updated
    15 Jun 2022, 16:10 BST
Lots and requirements (3)
Published by the contracting authority
  • Lot 1 · #1
    Principal Contractor, site management
    cancelled
    Published valueNot published
    Principal Contractor, Site management
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
  • Lot 2 · #3
    Individual lot title not published
    cancelled
    Published valueNot published
    Data cabling install (Internal & External to the buildings)
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
  • Lot 3 · #4
    Individual lot title not published
    cancelled
    Published valueNot published
    Building fabric alterations and enabling works for data cabling
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
Timeline
  1. Procedure published
    14 Oct 2024, 10:34 BST
  2. Award active
    Not published · Not published
  3. Contract active
    Signed 9 Oct 2024, 00:00 BST · £6,231,688
Commercial outcome and competition
Awards
Capita Business Services Ltd
Not published · Not published · active
Contracts
Contract
£6,231,688 · signed 9 Oct 2024, 00:00 BST · active
Bid statistics
bids: 5
electronicBids: 5
Buyer and organisations in this procedure

University of Sussex

Contracting authority GB-FTS-75584
View buyer profile
  • University of Sussex
    buyer
    reviewBody

    Brighton, UKJ21, BN1 9RH
  • Capita Business Services Ltd
    supplier

    London, UKI
Documents (0)
Official links; attachments are not copied
No data
No linked documents are published
Related procedures (0)
No data
No related procedures published