Find a TenderAwarded
Published 11 Apr 2022, 11:20 BST

Official UK procurement notice

Covid 19 Impact report · UK public procurement notice

Official notice

Authority: NORTHERN GAS NETWORKS LIMITED (Public body)

ServicesNegotiated procedure with prior call for competition
Awarded value£70,529published contract · exc. VAT
Submissions closed 19 Apr 2022awarded 24 May 2022
Awarded to Economic Insight Limited

What is being bought

Published requirement description

Impact of Covid 19 reporting - Award

The purpose of this contract is to source a supplier to support and document the impact of the Covid -19 Pandemic on NGN to ensure impacts are documented now and retained in corporate memory prior to RIIO2 Close out.

Key requirements are:

  • To document the impact of covid-19 on NGN
  • To develop a framework for quantifying costs of Covid 19 and subsequent workload impact on NGN
  • To prepare a proposal based on cost and workload which supports the NGN GD2 Close Out Covid-19 submission (recover costs)

The output of the work should be a professional services report capturing short and long term impacts i.e. GD1 then GD2 to future and identify:

  • Risks faced
  • How we responded
  • Rational for decisions
  • Opportunity cost of decisions
  • Timelines
  • Costs
  • Workloads
  • Impact on customer
  • Impact on / through the regulatory framework - compared to baseline

CPV: Research and development services and related consultancy services

The lotProcurement structure

single lot · no lot value published
Lot #1The specification of requirements:Awarded

The specification of requirements:

In the final year of RIIO-GD-1 (2020/21) and cross over to Year 1 of RIIO-GD 2 (2021/22) the global Covid-19 Pandemic caused disruption to business-as-usual operations and back-office functions at Northern Gas Networks (NGN).

NGN applied a stringent safety-first approach throughout this time in strict accordance with the latest government guidance as the pandemic evolved.

As a frontline service, NGN was able to maintain some operational workforce during the pandemic, however, there were many instances where planned Capex, Repex or Operational activity was delayed or deferred to manage the workforce and service outputs in response to the evolving situation. In addition, decision making took account of the evolving situation which may have resulted in short term decisions right for that moment in time but not necessarily consistent with NGN's long-term strategy.

Ofgem have confirmed that the impact of the Covid Pandemic will be assessed during the close out process for RIIO-GD2 which will take place in 2026-27. Due to the time gap between the pandemic ending and NGN returning to business-as-usual activity and the RIIO2 close out process NGN requires support to document the impact of the impact of the Covid -19 Pandemic on NGN to ensure impacts are documented and retained in corporate memory prior to RIIO2 close out.

The scope of this project will target all business areas and key requirements include:

  • To document the impact of covid-19 on NGN, specifically Repex Programme, Capital Programme, Operational Activity, Delivery of Outputs and compliance with the regulatory contract.
  • To develop a framework which quantifies the costs of Covid 19 and subsequent workload impact on NGN in relation to decisions made as the pandemic evolved.
  • To prepare a report focussed on cost and workload which supports the NGN GD2 Close Out Covid-19 submission (recover costs).
  • The output of the work will be a professional services report capturing short- and long-term impacts of NGN's Response i.e., GD1 then GD2 to future and identify:
  • Risks faced
  • How NGN responded
  • Rational for decisions
  • Opportunity cost of decisions
  • Timelines
  • Costs
  • Workloads
  • Impact on customer
  • Impact on / through the regulatory framework - compared to baseline

It is expected that the project will be completed via a suite of onsite interviews/workshops with key senior managers and their teams to facilitate data collection and working with the Regulation and strategy teams to develop a framework for assessment and subsequent completion of a report.

It is anticipated that the contract will be completed in a period of 6-10 weeks

Variant bids: not allowed

Procedure terms & legal framework

From the official record
Procedure method
Negotiated procedure with prior call for competition
Legal basis
CELEX · 32014L0025 Utilities Contracts Regulations 2016 (Directive 2014/25/EU)
Procurement category
Services
Notice status
Awarded
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
No (one-off requirement)
First published
11 Apr 2022, 11:20 BST
Last source update
24 May 2022, 08:41 BST
FTS notice number
2022/S 000-014153
Classification (CPV)
Research and development services and related consultancy services
Delivery area
North East (UKC)North West (UKD)Yorkshire & Humber (UKE)East Midlands (UKF)West Midlands (UKG)
Official registry OCID
ocds-h6vhtk-032c12 Find a Tender

How it was run

Official notice
Submission deadline
19 Apr 2022, 12:00 BST
Submission channel
{"written"}
Accepted languages
en

Timeline

19 Apr 2022 → 24 May 2022 · 2 dates
  1. Submission deadline
    19 Apr 2022, 12:00 BST
  2. Notice published
    24 May 2022, 08:41 BST

Notice history

1 event · 2 releases on Find a Tender
  1. Status changed to complete
    24 May 2022, 08:41 BST

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £70,5291 contract exc. VAT
Contracts signed 1latest 24 May 2022
Awarded toValueDateStatus
Economic Insight LimitedSME£70,529 †—Awarded

Contracts

Contracting authority & participating public bodies

NORTHERN GAS NETWORKS LIMITED

Contracting authorityPublic bodyProduction, transport and distribution of gas and heat 1100 Century Way Thorpe Park, LEEDS, Yorkshire & Humber, LS158TUContact name, email, phone Published organisation website ↗

Dispute resolution & review bodies

  • Northern Gas NetworksReview body LeedsContact email

Bidders & participating suppliers

1 commercial party on the notice

Official documents & specifications

Official links; attachments are not copied

No document links were published on the notice.