Official UK procurement notice
Wessex P-Way Track Minor Works (Maintenance)
Authority: NETWORK RAIL INFRASTRUCTURE LIMITED (Central government)
What is being bought2 lots · detail below
Published requirement descriptionProvision of Works to support Wessex Delivery Units in all required maintenance activity on the Permanant Way.
CPV: Track construction works
How this framework works
From the published notice- Bids received
- 7 bids on the busiest of 2 lots · 2 suppliers appointed
Lots and requirements (2)Procurement structure
2 lots · no lot values published · same evaluation weights on every lotLot #1Inner DUAwarded
Provision of the Services for the Inner Delivery Unit.
Lot #2Outer DUAwarded
Provision of the Works to the Outer Delivery Unit.
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (5)
- Technical and Construction Methodology: 25%
- Programme: 10%
- Supplier Resource Competency: 10%
- price: 50%
- Sustainability: 5%
Published award criteria (5)
- Technical and Construction Methodology: 25%
- Programme: 10%
- Sustainability: 5%
- Supplier Resource Competency: 10%
- Price: 50%
- Price carries 50 of 100 points: a 10% discount moves about 5 points. This one is won on the number: sharpen the price before polishing the prose.
- “Wessex P-Way Track Minor Works (Maintenance)” is a framework: the contest is a place on its panel, not a single contract.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Negotiated procedure with prior call for competition
- Legal basis
- CELEX · 32014L0025 Utilities Contracts Regulations 2016 (Directive 2014/25/EU)
- Procurement category
- Works
- Notice status
- Awarded
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 25 Jan 2022, 22:44 GMT
- Last source update
- 25 Jan 2022, 22:44 GMT
- FTS notice number
2022/S 000-002243- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-030f5cFind a Tender
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast2 suppliers are admitted to this framework without individual award values or dates, see the supplier list below.
Contracts
Wessex P-Way Track Minor Works (Maintenance) - Lot 1 Inner DU
- Signed
- 29 Dec 2021
- Value
- —
- Status
- active
Wessex P-Way Track Minor Works (Maintenance) - Lot 2 Outer DU
- Signed
- 8 Dec 2021
- Value
- —
- Status
- active
Bid statistics published by the authority
| Lot | Bids | SME | VCSE | Valid bid range |
|---|---|---|---|---|
| 1 · Inner DU | 7bids | — | — | — |
| 2 · Outer DU | 7bids | — | — | — |
Contracting authority & participating public bodies
Dispute resolution & review bodies
- High Court (England and Wales)Review body
Framework contractors & participating bidders
2 commercial parties on the notice- Balfour Beatty Rail LtdFramework contractor
- Sonic Rail ServicesFramework contractor
Official documents & specifications