What is being bought
Published requirement descriptionIntroduction
Network Rail (NR) is a public-sector organisation which owns, operates and maintains the rail infrastructure in the United Kingdom. Network Rail owns and operates 20,000 miles of track, 30,000 bridges, tunnels and viaducts and thousands of signals, level crossings and stations, as well as offices and depots across the country. We manage 20 of the UK's largest stations while all the others, over 2,500, are currently managed by the country’s Train Operating Companies (TOC’s). Although this may change with the nationalisation of the Train Operating Companies and the creation of Great British Railways (GBR).
Background
Network Rail, including TOC’s, use approximately 4.5TWh of electricity a year, about 0.5TWh is used by NR to power our stations, offices, depots, signals etc. (non-traction power) with the other 4TWh used to power the trains (Traction power).
NR has a well-established Transition to Renewables (T2R) programme which includes both on-site renewables, via capital investment and supplier funded, and Corporate Power Purchase Agreements (CPPA’s). NR has a target to transition all non-traction consumption to renewables by 2030.
Overview
Network Rail intends to establish a framework of five capable and experienced suppliers to support the delivery of on-site or near site supplier funded renewable energy solutions delivered through Power Purchase Agreements (PPA).
The framework will support a variety of renewable energy deployment types, including:
- Rooftops installations
- Car park solar canopies
- Ground-mount systems
- High energy consuming sites with potential to secure nearby land option.
The framework will be technology agnostic, allowing for Solar PV, on-site wind turbines, and future emerging technologies, with the option to include energy storage solutions where appropriate.
The framework will be awarded to five suppliers and be valid for 8 years. It will be available for use across Network Rail, as well as covering the nationalised ToC’s and GBR, including any affiliates. Call-offs will be run as mini competitions through the framework for individual sites or a portfolio of sites. Each resulting call-off contract will be for a term of up to 25 years depending on the technology and project requirements. At the end of the contract there may be an option to:
- Purchase the renewable assets, or
- Extend the contract at a reduced price, or
- Require the removal of the asset and reinstatement of the site.
An initial award of up to five sites will be made to the highest scoring supplier, subject to feasibility and affordability. Further information is included in the procurement documents.
- How the procedure runs: As detailed in the procurement documents
CPV: Batteries · Electricity · Solar energy · Wind-energy generators
How this framework works
From the published notice- Type
- Open framework
- Call-offs
- every call-off is a further competition among the appointed suppliers
- Places
- up to 5 suppliers
- Framework period
- 8 yrs from 1 Feb 2027
Who may buy through it
This framework will be available to Network Rail, Great British Railways, Department For Transport Operator Limited (DFTO), and their subsidiaries, successor organisations and affiliates.”
Published description of the framework
Deatils are included in the procurement documents
The lotProcurement structure
single lot · value publishedLot #1Published value£220,000,000
- Economic & financial standing
As detailed in the procurement documents
- Technical & professional ability
As detailed in the procurement documents
- Condition of participationshortlisting
As deatiled in the procurement documents
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (2)
- Technical: 50%
- Commercial: 50%
Published award criteria (2)
- Commercial: As detailed in the procurment documents
- Technical: As detailed in the procurment documents
- Economic & financial standing
As detailed in the procurement documents
- Technical & professional ability
As detailed in the procurement documents
- Condition of participationshortlisting
As deatiled in the procurement documents
- Price carries 50 of 100 points: a 10% discount moves about 5 points. This one is won on the number: sharpen the price before polishing the prose.
- “DPPA framework (Supplier funded On-site renewables)” is a framework: the contest is a place on its panel, up to 5 suppliers, not a single contract: each call-off is a further competition, so the pricing contest starts after appointment.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Competitive flexible procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Goods
- Notice status
- Closed
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Utilities
- Commercial structure
- Framework agreement
- Who may use this agreement
- This framework will be available to Network Rail, Great British Railways, Department For Transport Operator Limited (DFTO), and their subsidiaries, successor organisations and affiliates.”
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA, CPTPP)
- Recurring procurement
- Unspecified in notice
- First published
- 16 Jul 2025, 15:15 BST
- Last source update
- 1 Apr 2026, 14:59 BST
- Award evaluation window
- Submission end – 12 Jan 2027
- FTS notice number
2026/S 000-030444- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-056076Find a Tender
- How it runs
As detailed in the procurement documents
How it was run
Official notice- Requests to participate (first stage)
- 6 May 2026, 11:00 BST
- Appointment period ends
- 6 May 2026, 11:00 BST
- Clarification deadline
- 15 Apr 2026, 16:00 BST
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
- Accepted languages
- en
Register at networkrail.bravosolution.co.uk ↗ navigate to PQQ's open to all suppliers and express an interest in pqq_3885 DPPA framework (Supplier funded On-site renewables)
Timeline
16 Jul 2025 → 1 Feb 2027 · 8 dates- Planning notice published16 Jul 2025, 15:15 BST
- Market engagement31 Jul 2025, 23:59 BST
Network Rail is seeking to engage with interested suppliers as part of a Pre-Market Engagement exercise to ensure adequate market interest and to help shape the design of the framework and form of contract.
We welcome expressions of interest from suppliers with relevant experience in delivering supplier-funded renewable energy projects (PPA’s).
Capable suppliers should express an interest by the deadlne and a questionaire will be sent out. Follow up meetings may be held with suppliers.
To express an interest in taking part in the Market Engagement - please email [email protected]. With the subject heading “EOI - PPA Framework for Onsite renewables”.
Please also register on our Procurement portal at networkrail.bravosolution.co.uk ↗
- Next notice expected329 days ago1 Dec 2025, 23:59 GMT
- Tender notice published209 days ago1 Apr 2026, 14:59 BST
- Clarification questions by195 days ago15 Apr 2026, 16:00 BST
- Admission / appointment period ends174 days ago · period end, not a bid countdown6 May 2026, 11:00 BST
- Today27 Oct 2026
- Award decision expected byin 77 days12 Jan 2027, 23:59 GMT
- Contract startsin 96 days1 Feb 2027
Notice history
7 events · 4 releases on Find a Tender · since 16 Jul 2025- Preliminary market engagement notice published16 Jul 2025, 15:15 BSTUK2
- Preliminary market engagement notice published17 Jul 2025, 09:36 BSTUK2
- Preliminary market engagement notice published17 Jul 2025, 09:37 BSTUK2
- Tender notice published1 Apr 2026, 14:59 BSTUK4
- Published value updated to £220,000,0001 Apr 2026, 14:59 BSTwas £240,000,000
- Status changed to active1 Apr 2026, 14:59 BST
- Procurement method changed1 Apr 2026, 14:59 BST
Routine re-releases (4)
- 2025-07: 1 release · 16 Jul 2025
Contracting authority & participating public bodies
Official documents & specifications (5)
Official links; attachments are not copiedTender pack and attachments
- Bidding documents and specificationsAccess: Site information for the intial five Route Services sites to be awarded will be provided to those shortlisted to tender. The sites are in GB mainland. Any new documents and updates will be published via Bravo throughout the event. Where a stage is in progress, a message shall be sent to all participants within the stage to inform them.
Notices published for this procedure
- Tender notice Tender notice on Find a Tender
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender