Official UK procurement notice
Notting Dale Heat Network Project O&M
Authority: capitalEsourcing
What is being bought
Published requirement descriptionThe Notting Dale Heat Network (the “Heat Network” / “Project”) is to be delivered and operated by a SPV wholly owned by the Council. It is the Council’s ambition that it will be the most reliable and proactively maintained heat network in the UK. The initial phase of the Project is to serve the Lancaster West Estate (LWE) for which the intended heat users include around 800 residential units (currently subject to a major refurbishment programme being led by the Council), a school, a large Council-owned leisure centre and business units for SMEs (Baseline Studios). The Project is anticipated to expand through future phases, which are currently being assessed.
In respect to the initial phase, sources of necessary funding have been identified including award of a £1.116m HNIP capital grant. The scheme is currently at Commercialisation Stage and is intended to reach Final Investment Decision (FID) in December 2022, when firm prices for the D&B works will need to have been procured. Construction is due to start at the end of March 2023, with heat supply commencing in mid-2024, and the last heat network connections being made at the end of 2029.
In summary, the O&M services for the initial phase will comprise:
- Operation of a smart control system, dashboard and helpdesk facility under a comprehensive payment mechanism, use of remote sensors and smart error reporting to ensure resilience and performance against KPIs.
- Provision of operations & maintenance services to include: a central ASHP/s, electric boilers, thermal store and associated equipment; together with associated energy centre and plant room/s; approximately a 1,200m primary network; and around 20 connection points (substations / HIUs) serving the residential blocks, the school, leisure centre and Baseline Studios; together with their associated secondary networks (but excluding any tertiary networks). In so doing, minimising the need for call-outs through use of the smart control system to monitor plant performance, identify issues and make adaptions
- Provision of metering & billing services. In respect to the social housing, this is currently intended to be on a bulk supply basis to the Council, which in turn will use its existing resource to manage the individual billing to each resident, but in the future a variation may be required for the O&M services provider to meter & bill these residents directly.
- It is currently intended that the O&M contract last for 5 years with an option to extend by a further 5 years.
CPV: District heating
The lotProcurement structure
single lot · no lot value publishedLot #1Supplier Engagement: Kensington & Chelsea Council intends to undertake a market…Planned
Supplier Engagement: Kensington & Chelsea Council intends to undertake a market engagement event with organisations interesting in tendering for and delivering these works. Please note this is purely an opportunity to potentially shape the requirements and participation in this consultation. Registration of interest will not give any advantage in this procurement opportunity. We will consult with interested suppliers to obtain views and comments on the planned route to market. Your responses will help to inform the procurement although we cannot guarantee that all views expressed will be taken into account.
The market engagement event is expected to take place on 3rd March 2022. If you wish to participate, please contact [email protected] as soon as possible but by no later than 21 February 2022.
It is intended to issue a F02 Contract Notice on the UK Find a Tender Service by 15 March 2022, and suppliers are advised to monitor regularly to see the opportunity when it is published. Once the Contract Notice has been published, suppliers will be required to express interest in this opportunity on Capital Esourcing. If not already registered on Capital Esourcing, please register at the following link: www.capitalesourcing.com/web/login.shtml ↗. Suppliers will then be granted access to the tender documentation once it is published.
Please note that registering on Capital Esourcing and expressing interest does not mean that you have bid for the tender - once the above steps are complete you will be required to complete and submit the tender documentation.
Procedure terms & legal framework
From the official record- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Goods
- Notice status
- Past planning notice
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Unspecified in notice
- First published
- 11 Feb 2022, 22:45 GMT
- Last source update
- 11 Feb 2022, 22:45 GMT
- Authority reference
KCCND5- FTS notice number
2022/S 000-004079- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-03168aFind a Tender
How it was run
Official notice- Submission deadline
- —
Timeline
11 Feb 2022 → 11 Feb 2022 · 2 dates- Tender notice expected11 Feb 2022
- Notice published11 Feb 2022, 22:45 GMT
Commercial outcome & contract awards
Pipeline notice- Awards (0)
- No award published
- Contracts (0)
- No contract published
- Bid statistics
- No aggregate bid statistics published
Contracting authority & participating public bodies
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.