NCC1164 Framework for The Provision of Repairs and Maintenance Works to Highways Bridges
Authority: Northumberland County Council (Local council)
What is being bought9 lots · detail below
Published requirement descriptionThe Contracting Authority intends to establish a Framework for the provision of various bridge repair and maintenance works across the county of Northumberland.
The Framework will be divided into the following nine Lots:
Lot 1 - Concrete Repair and Hydrodemolition
Lot 2 - Stone Masonry
Lot 3 - Waterproofing
Lot 4 - Scaffolding
Lot 5 - Steel Repair and Fabrication
Lot 6 - Steel Painting
Lot 7 - Driven Piling
Lot 8 - Cast-in-Place Piling
Lot 9 - Soil Nailing
Tender documents are available to download from the OPEN e-procurement portal: www.open-uk.org ↗. Please refer to project reference OPEN20261800.
- The authority expects to re-tender this requirement around 2 Dec 2030, 23:59 GMT.
CPV: Construction work for bridges
How this framework works
From the published notice- Type
- Closed framework
- Call-offs
- call-offs may be awarded directly or by further competition
- Framework period
- 4 yrs from 1 Dec 2026
Published description of the framework
Lots 1 to 5
Suppliers appointed to the Framework will be ranked according to their combined price and quality score (Most Advantageous Tender). A maximum of three suppliers achieving the highest combined quality and price scores will be awarded a place on the relevant Framework Lot.
Lot 6 to 9
Suppliers appointed to the Framework will be ranked according to their total quality score (Most Advantageous Tender). A maximum of three suppliers achieving the highest quality scores will be awarded a place on the relevant Framework Lot.
All Lots
The Contractor with the highest overall score will be ranked first, the Contractor with the second highest score will be ranked second, and so on.
The successful suppliers will enter into a Framework Agreement in a form which is set out in Schedule 8. The Framework will commence in November 2026 and will be for 4 years.
The Framework does not include any guarantee of any minimum volume of works or any minimum expenditure. Furthermore, appointment under the Framework does not constitute a commitment by the Contracting Authority to the exclusive use of the Framework or an individual supplier for such requirements.
Call-off contracts under this Framework will be awarded either by direct award (also referred to as an award without competition) to the highest-ranked Contractor for the relevant Lot, or through a job-specific further competition. Details of the processes for both direct awards and further competitions are set out below.
Award Without Competition (Ranked)
Under section 45(4)(b) of PA34 a Contracting Authority may award a call-off contract without competition where there is an objective mechanism for supplier selection e.g. "a 'taxi-rank' system where call-off contracts are awarded on a 'highest ranking' system with a limitation on the number or value of call-off contracts to be awarded to any one supplier.
Direct awards under this Framework will be made based on the project value thresholds set out below for each individual Lot.
- Lot 1 Concrete Repair and Hydrodemolition: Project value of up to £50,000
- Lot 2 Stone Masonry: Project value of up to £50,000
- Lot 3 Waterproofing: Project value of up to £50,000
- Lot 4 Scaffolding: Project value of up to £100,000
- Lot 5 Steel Repair and Fabrication: Project value of up to £5,000
- There is no direct award provision for Lots 6,7,8 & 9.
The Client will contact the highest-ranked Contractor for the relevant Lot to confirm their availability for the required project date, time, and duration. If the highest-ranked Contractor is unable to fulfil the Client's requirements, the Client will approach the second highest-ranked Contractor.
This process will continue with each subsequent ranked Contractor, as necessary, until a Contractor is appointed. Upon confirmation that the selected Contractor can fulfil the project requirements, a call-off contract will be entered into.
When an award without competition is made the price will be based on the Supplier's tendered rates. The Supplier can improve on their tendered rates but must not exceed them.
Further details of the Contracting Authority's requirements are set out in Schedule 2 - Specification of the ITT documents.
Further Competition
A further competition will be undertaken for projects under Lots 1 to 5 where the project value exceeds the thresholds stated above, and for all projects under Lots 6 to 9.
A Project Specification will be issued by the Client to all Contractors appointed to the relevant Lot under the Framework. All Contractors within that Lot will be invited to submit a Further Competition response against the job-specific specification.
Further competitions will be carried out in accordance with the following process:
Framework Contractors will be required to complete and submit:
- a Further Competition Award Questionnaire; and/or
- a Further Competition Pricing Schedule.
Evaluation of submissions will be carried out in accordance with the 'Award Methodology and Scoring' section set out in this Instructions to Tenderers (ITT) document, and as further specified by the Client.
In the case of further competitions involving multiple projects, Contractors will be required to confirm that they have the capacity to deliver all projects they are bidding for within the required timescales, as outlined in the specification issued at further competition stage.
The Client reserves the right to award projects to the next ranked bidder following the conclusion of the further competition where the highest-ranked Contractor confirms that they are unable to meet the required timescales.
Following evaluation, all bidders will be notified of the outcome in writing by the Client, and a call-off contract will be entered into with the successful Contractor.
Biennial Re-ranking of Lots 1 to 5
Suppliers appointed to Lots 1 to 5 of the Framework will be re-ranked every two years through a Further Competition, as follows:
Tendered rates will be fixed initially for a period of 24 months from commencement of the Framework.
Three (3) months prior to the expiry of the initial fixed 24 months all providers for Lots 1 to 5 on the Framework will be invited to resubmit their framework rates.
Framework suppliers will be re-ranked, and the revised pricing will be implemented for the remainder of the Framework duration.
The re-ranking further competition will be issued via the OPEN system (www.open.org ↗) and Tenders must be submitted electronically via the OPEN system.
Lots and requirements (9)Procurement structure
9 lots · all with a published value · win at most 2 of them · evaluation weights differ by lotEvery one of these 9 lots carries the same published figure, £333,333: it is the framework's maximum for the whole notice, not each lot's own budget, and no share per lot is published. The cards below say ceiling above rather than repeat it.
Lot #1Concrete Repair and Hydrodemolitionceiling above
Concrete Repair and Hydrodemolition Works
Lot #2Stonemasonryceiling above
Stonemasonry Works
Lot #3Waterproofingceiling above
Waterproofing Works
Lot #4Scaffoldingceiling above
Scaffolding Works
Lot #5Steel Repair and Fabricationceiling above
Steel Repair and Fabrication Works
Lot #6Steel Paintingceiling above
Steel Painting Works
Lot #7Piling - Drivenceiling above
Piling - Driven Works
Lot #8Piling - Cast in Placeceiling above
Piling - Cast in Place Works
Lot #9Soil Nailsceiling above
Soil Nails Works
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Lots publish different evaluation splits; there is no single procedure weighting.
| Lot | Quality | Price | Split |
|---|---|---|---|
| 1 · Concrete Repair and Hydrodemolition | 60% | 40% | |
| 2 · Stonemasonry | 50% | 50% | |
| 3 · Waterproofing | 50% | 50% | |
| 4 · Scaffolding | 60% | 40% | |
| 5 · Steel Repair and Fabrication | 80% | 20% | |
| 6 · Steel Painting | 100% | — | |
| 7 · Piling - Driven | 100% | — | |
| 8 · Piling - Cast in Place | 100% | — | |
| 9 · Soil Nails | 100% | — |
- Price carries 20–50 points depending on the lot. Read the split per lot below.
- “NCC1164 Framework for The Provision of Repairs and Maintenance Works…” is a framework: the contest is a place on its panel, not a single contract: call-offs may be direct or by further competition.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Open procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Closed
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Yes · next expected 2 Dec 2030
- First published
- 23 May 2025, 17:09 BST
- Last source update
- 21 Aug 2026, 09:21 BST
- Award evaluation window
- Submission end – 11 Nov 2026
- Authority reference
NCC1164- FTS notice number
2026/S 000-079746- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-0524cfFind a Tender
How it was run
Official notice- Appointment period ends
- 28 Sept 2026, 12:00 BST
- Clarification deadline
- 15 Sept 2026, 12:00 BST
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
- Accepted languages
- en
Timeline
23 May 2025 → 1 Dec 2026 · 7 dates- Planning notice published23 May 2025, 17:09 BST
- Next notice expected82 days ago30 Jul 2026, 23:59 BST
- Tender notice published61 days ago21 Aug 2026, 09:21 BST
- Clarification questions by36 days ago15 Sept 2026, 12:00 BST
- Admission / appointment period ends23 days ago · period end, not a bid countdown28 Sept 2026, 12:00 BST
- Today21 Oct 2026
- Award decision expected byin 22 days11 Nov 2026, 23:59 GMT
- Contract startsin 41 days1 Dec 2026
Notice history
7 events · 3 releases on Find a Tender · since 23 May 2025- Pipeline notice published23 May 2025, 17:09 BSTUK1
- Pipeline notice published22 Jun 2026, 16:21 BSTUK1
- Tender notice published21 Aug 2026, 09:21 BSTUK4
- Published value published: £3,000,00021 Aug 2026, 09:21 BST
- Status changed to active21 Aug 2026, 09:21 BST
- Procurement method changed21 Aug 2026, 09:21 BST
- Deadline published: 28 Sept 2026, 12:00 BST21 Aug 2026, 09:21 BST
Contracting authority & participating public bodies
Official documents & specifications (5)
Official links; attachments are not copiedTender pack and attachments
Notices published for this procedure
- Tender notice Tender notice on Find a Tender
- Pipeline notice Pipeline notice on Find a Tender
- Pipeline notice Pipeline notice on Find a Tender