Find a TenderAwardedContract performance notice
Published 2 Jul 2025, 16:48 BST

Official UK procurement notice

National Underground Asset Register (NUAR) Data Transformation and Ingestion Service

Official notice

Authority: ORDNANCE SURVEY LIMITED (Public body)

ServicesCompetitive flexible procedureAbove thresholdSME suitable
Published estimate£5,000,000≈ £2.1m / year · £6,000,000 inc. VAT
Submissions closed 26 Sept 2025awarded 17 Nov 2025
Awarded to 1Spatial Group Ltd
Contract term 2 yrs 4 moends 31 Mar 2028 · up to 31 Mar 2031 with extensions · starts 8 Dec 2025

What is being bought

Published requirement description

Ordnance Survey Ltd (OS) is Great Britain’s mapping agency and is responsible for the surveying, production, maintenance and marketing of a wide range of geographic information, relied on by government, business and individuals. Further information can be found on our website www.os.uk ↗.

OS is a private limited company (company registration number 09121572), and the entire share capital is owned by the Department for Science, Innovation and Technology.

OS is appointing an organisation “the Supplier” to deliver the Data Transformation and Ingestion (DT&I) Service component of the National Underground Asset Register (NUAR) Data Lifecycle. The NUAR Programme is a Government Digital Service (GDS) initiative to build a digital map of underground pipes and cables that will revolutionise the way the different sectors of the economy install, maintain, operate, and repair Great Britain’s buried infrastructure. Once operational, NUAR is envisaged to deliver £490 million per year of economic growth through increased efficiency, reduced asset strikes (when underground pipes and cables are accidentally damaged) and reduced disruptions for the public and businesses.

The NUAR Programme delivers underground asset data to thousands of utility users through the Safe-Dig User Interface. This improves the efficiency and safety of underground works by providing secure access to privately and publicly owned location data about the pipes and cables beneath our feet. The digital map, available through the Safe-Dig Interface, gives planners and excavators standardised access to the data they need, when they need it, to carry out their work effectively and safely. It also includes features to keep data secure and improve its quality over time.

Data processed, stored and published under NUAR represents assets critical to the functioning of the nation and therefore security is critical to the delivery of the NUAR Programme. The programme takes a security first approach to every aspect of delivery. This is particularly important for organisation handling the data as the successful DT&I Supplier will be responsible for providing an access point through the Data Supply Portal for the Asset Owner (AO) and then transforming the data to the NHDM. The NPSA and NPSC are key partners and NUAR has been identified by the former as an exemplar of how to implement security into a major programme of national significance.

The DT&I Service is the interface for all Asset Owner (AO) data entering NUAR. The service receives AO data, transforms it into the NHDM and makes it available for ingestion into the NUAR Holding DB. The Authority will then pull the data to the NUAR Holding DB.

OS is appointing a Supplier to deliver the Data Transformation and Ingestion (DT&I) Services which forms part of the NUAR Data Lifecycle. The Supplier will be required to transition all AOs (with a scheduled refresh date before 30 June 2026) by 1 April 2026. The Supplier will develop a plan, in consultation with the Authority, for transitioning the remaining AOs prior to their next scheduled refresh date. The Supplier will be provided with a DIS and a Transformation Pack for each AO to enable the transition.

The services carried out by the Supplier must be delivered from within the UK. This includes any transfer or access of data and systems.

It is anticipated that this contract shall commence on 8 December 2025 (the Commencement Date) which shall be the commencement of the Service Implementation and which shall complete on 31 March 2026. Following the Service Implementation, the remaining Services shall commence on 1 April 2026 and without prejudice to the early termination rights set out in the Conditions, shall continue for an initial period of two (2) years (the Term)

The initial term of the contract will be for two years with the option for the Authority to extend the contract annually for a further three years meaning the contract would run until at least 31 March 2028, but potentially up to 31 March 2031 if all extensions were taken. Therefore, if all extensions are taken, the total length of the contract will be for five years (2+1+1+1).

  • How the procedure runs: This procurement will be conducted in accordance with the competitive flexible procedure as set out in the Procurement Act 2023. The process will comprise two stages. Stage One will openly invite interested suppliers to submit Bids to deliver the required services. All submissions will be evaluated against the criteria detailed in the procurement documentation. The evaluation will be conducted to identify the Bid that offers the most advantageous tender. The supplier whose Bid is assessed as the most advantageous tender will be designated as the preferred supplier. Stage Two will be a preferred bidder and post-tender negotiation stage. The preferred supplier will enter into a post-tender negotiation phase. The purpose of this stage is to; Confirm the commitments made in the Bid submission; Ensure the final contract terms and conditions accurately reflect those commitments; Address any necessary clarifications or refinements to ensure mutual understanding of the contract deliverables; Address any cost elements submitted by the preferred Bidder as part of the tender response with the objective of ensuring value for money and alignment with the Authority’s budget constraints and commercial objectives; and Review and consider any proposed amendments from the Bidder to the contractual terms and conditions issued with the procurement documentation.

CPV: Customer services · Data capture services · Data collection and collation services · Data conversion services · Data entry services · Data management services · Data preparation services · Data services · Data storage services · Data supply services · Data-processing services · Database and operating software development services · +8 more

The lotProcurement structure

single lot · value published
Lot #1AwardedRenewal 2 yrs 4 moPublished value£5,000,000
Contract period: 8 Dec 2025 – 31 Mar 2028 (2 yrs 4 mo) · up to 31 Mar 2031 with extensionsValue: £5,000,000 exc. VAT · £6,000,000 inc. VAT
Delivery: South East
Extensions: It is anticipated that this contract shall commence on 8 December 2025 (the Commencement Date) which shall be the commencement of the Service Implementation and which shall complete on 31 March 2026. Following the Service Implementation, the remaining Services shall commence on 1 April 2026 and without prejudice to the early termination rights set out in the Conditions, shall continue for an initial period of two (2) years (the Term) The initial term of the contract will be for two years with the option for the Authority to extend the contract annually for a further three years meaning the contract would run until at least 31 March 2028, but potentially up to 31 March 2031 if all extensions were taken. Therefore, if all extensions are taken, the total length of the contract will be for five years (2+1+1+1).

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
How bids were scored
Quality: 70%Price: 20%Social value: 10%
Published sub-criteria (3)
  • Quality Criteria: 70%
  • Price: 20%
  • Social Value Criteria: 10%
Published award criteria (3)
  • Quality Criteria
  • Social Value Criteria
  • Price
What this means for your bid
  • Price carries 20 of 100 points: a 10% discount moves about 2 points. The method statement decides this lot, not the discount.

Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.

Procedure terms & legal framework

From the official record
Procedure method
Competitive flexible procedure
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Procurement category
Services
Notice status
Awarded
Procurement threshold
Above threshold (FTS publication)
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Yes (GPA)
Recurring procurement
Unspecified in notice
First published
2 Jul 2025, 16:48 BST
Last source update
13 Oct 2026, 14:39 BST
Award evaluation window
Submission end – 10 Nov 2025
Authority reference
BS.0756
FTS notice number
2025/S 000-050767
Latest notice
Contract performance notice (UK9)
Classification (CPV)
Customer servicesData capture servicesData collection and collation servicesData conversion servicesData entry servicesData management servicesData preparation servicesData servicesData storage servicesData supply services
+10 moreData-processing servicesDatabase and operating software development services
Delivery area
South East (UKJ32)
Official registry OCID
ocds-h6vhtk-0557e6 Find a Tender
Contract terms summary

Payment of undisputed sums will be due within 30 calendar days of receipt by Ordnance Survey of a correctly presented and properly submitted invoice.

How it runs

This procurement will be conducted in accordance with the competitive flexible procedure as set out in the Procurement Act 2023. The process will comprise two stages.

Stage One will openly invite interested suppliers to submit Bids to deliver the required services. All submissions will be evaluated against the criteria detailed in the procurement documentation. The evaluation will be conducted to identify the Bid that offers the most advantageous tender. The supplier whose Bid is assessed as the most advantageous tender will be designated as the preferred supplier.

Stage Two will be a preferred bidder and post-tender negotiation stage. The preferred supplier will enter into a post-tender negotiation phase. The purpose of this stage is to; Confirm the commitments made in the Bid submission; Ensure the final contract terms and conditions accurately reflect those commitments; Address any necessary clarifications or refinements to ensure mutual understanding of the contract deliverables; Address any cost elements submitted by the preferred Bidder as part of the tender response with the objective of ensuring value for money and alignment with the Authority’s budget constraints and commercial objectives; and Review and consider any proposed amendments from the Bidder to the contractual terms and conditions issued with the procurement documentation.

Review and risk notes
Risks

Ordnance Survey has identified the below risks that could jeopardise the contracts satisfactory performance:

  1. Legislative or Regulatory Change

There is a known risk that future changes in government legislation, regulation, or statutory guidance may materially alter the requirements for the delivery of the Service under this contract. This includes, but is not limited to, changes in compliance obligations, reporting standards, service scope, operational procedures or Asset Owner onboarding mandated by law.

If such legislative changes occur, they may render the current contract provisions insufficient to ensure satisfactory performance. The Authority may need to modify the contract to align with new legal requirements and ensure the successful performance of the contract.

  1. End-Customer-Initiated Service Changes or Enhancements

There is a known risk that the Customer of the Authority for the National Underground Asset Register (NUAR) may, during the term of the contract, request changes or enhancements to the scope, functionality, or delivery model of the Service. These requests may stem from evolving operational needs, policy developments, or strategic priorities that are not foreseeable at the time of contract award.

Such requests may materially affect the supplier’s ability to deliver the Service as originally specified, potentially requiring adjustments to staffing, technology, delivery timelines, or service outputs. If these changes cannot be accommodated within the existing contract terms, a modification may be required.

  1. Delay in Receipt of Service Transition Documentation from Incumbent Supplier

There is a known risk that the incumbent supplier may not provide the necessary service transition documentation within the required timeframe prior to contract commencement. This documentation is critical to ensuring a smooth and informed transition of service responsibilities to the incoming supplier.

A delay or failure in receiving the transition documentation may hinder the incoming supplier’s ability to mobilise effectively, understand legacy systems or processes, and deliver the service to the expected standard from day one. This could result in operational disruption, reduced service quality, or delays in achieving contractual milestones.

  1. Change in Anticipated Number of Asset Owners Due to Third-Party Dependencies

There is a known risk that the actual number of third-party asset owners to be onboarded during the contract term may differ from initial projections. This variability arises from the Authority’s reliance on external Asset Owners—who are not party to the contract—to engage with and participate in the onboarding process.

Fluctuations in the number of participating Asset Owners may affect the scale, timing, and resource requirements of the service. A lower-than-expected onboarding rate could reduce service volumes, while a higher-than-expected rate may require additional capacity, infrastructure, or support mechanisms not accounted for in the original contract scope.

How it was run

Official notice
Run through: In-tend · Who buys & how to bid on In-tend
Supplier login requiredElectronic submission allowedLanguage: EN
Access & registration note: Free · one account per buying organisation's portal · reCAPTCHA on signup
Submission deadline
26 Sept 2025, 12:00 BST
Submission channel
Official e-sourcing portal
Electronic submission
Allowed
Accepted languages
en
Detailed submission instructions & authority contactsFrom official release

in-tendhost.co.uk/os ↗

Each Bidder has access to a dedicated area on In-Tend to allow them to upload their Bid. It is the Bidder’s sole responsibility to ensure that its Bid is correctly and properly loaded onto In-Tend by the closing date and time stipulated on the system

Timeline

2 Jul 2025 → 13 Oct 2026 · 9 dates
  1. Planning notice published
    2 Jul 2025, 16:48 BST
  2. Next notice expected
    12 Aug 2025, 00:59 BST
  3. Tender notice published
    22 Aug 2025, 10:40 BST
  4. Submission deadline389 days ago
    26 Sept 2025, 12:00 BST
  5. Award decision expected by343 days ago
    10 Nov 2025, 23:59 GMT
  6. Assessment summaries sent337 days ago
    17 Nov 2025
  7. Standstill ends327 days ago
    26 Nov 2025, 23:59 GMT
  8. Contract starts316 days ago
    8 Dec 2025
  9. Latest notice published7 days ago
    13 Oct 2026, 14:39 BST

Notice history

13 events · 6 releases on Find a Tender · since 2 Jul 2025
  1. Pipeline notice published
    2 Jul 2025, 16:48 BST
    UK1
  2. Tender notice published
    22 Aug 2025, 10:40 BST
    UK4
  3. Status changed to active
    22 Aug 2025, 10:40 BST
  4. Procurement method changed
    22 Aug 2025, 10:40 BST
  5. Deadline published: 25 Sept 2025, 12:00 BST
    22 Aug 2025, 10:40 BST
  6. Tender notice published
    12 Sept 2025, 14:43 BST
    UK4
  7. Deadline moved to 26 Sept 2025, 12:00 BST
    12 Sept 2025, 14:43 BST
    +1 days · was 25 Sept 2025, 12:00 BST
  8. Contract award notice published
    17 Nov 2025, 11:41 GMT
    UK6
  9. Status changed to complete
    17 Nov 2025, 11:41 GMT
  10. Procurement method changed
    17 Nov 2025, 11:41 GMT
  11. Contract signature expected
    28 Nov 2025, 23:59 GMT
    scheduled
  12. Contract details notice published
    22 Dec 2025, 17:22 GMT
    UK7
  13. Contract performance notice published
    13 Oct 2026, 14:39 BST
    UK9
Published amendments (1)

The Tender Submission Deadline has been extended from Thursday 25 September 2025 at 12:00 to Friday 26 September 2025 at 12:00. The description for the Competitive Flexible Procedure Description has also been updated to reflect the wording that is within the Instructions for Tendering document of the procurement documentation.

Routine re-releases (6)
  • 2025-09: 1 release · 12 Sept 2025
  • 2025-08: 1 release · 22 Aug 2025
  • 2025-07: 1 release · 2 Jul 2025

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £5,000,0001 award exc. VAT
Bids received 64 from SMEs
Named bidders 6published on the award notice
Contracts signed 1latest 4 Dec 2025
Awarded toValueDateStatus
1Spatial Group LtdSME8 Dec 2025 – 31 Mar 2028 · up to 31 Mar 2031Extensions: It is anticipated that this contract shall commence on 8 December 2025 (the Commencement Date) which shall be the commencement of the Service Implementation and which shall complete on 31 March 2026. Following the Service Implementation, the remaining Services shall commence on 1 April 2026 and without prejudice to the early termination rights set out in the Conditions, shall continue for an initial period of two (2) years (the Term) The initial term of the contract will be for two years with the option for the Authority to extend the contract annually for a further three years meaning the contract would run until at least 31 March 2028, but potentially up to 31 March 2031 if all extensions were taken. Therefore, if all extensions are taken, the total length of the contract will be for five years (2+1+1+1). · Options: It is anticipated that this contract shall commence on 8 December 2025 (the Commencement Date) which shall be the commencement of the Service Implementation and which shall complete on 31 March 2026. Following the Service Implementation, the remaining Services shall commence on 1 April 2026 and without prejudice to the early termination rights set out in the Conditions, shall continue for an initial period of two (2) years (the Term) The initial term of the contract will be for two years with the option for the Authority to extend the contract annually for a further three years meaning the contract would run until at least 31 March 2028, but potentially up to 31 March 2031 if all extensions were taken. Therefore, if all extensions are taken, the total length of the contract will be for five years (2+1+1+1).£5,000,00017 Nov 2025Awarded

Contracts

  • National Underground Asset Register (NUAR) Data Transformation and Ingestion Service · 1Spatial Group LtdSME

    Signed
    4 Dec 2025
    Value
    £5,000,000
    Period
    8 Dec 2025 – 31 Mar 2028 · up to 31 Mar 2031 with extensions
    Status
    active
    Extensions
    It is anticipated that this contract shall commence on 8 December 2025 (the Commencement Date) which shall be the commencement of the Service Implementation and which shall complete on 31 March 2026. Following the Service Implementation, the remaining Services shall commence on 1 April 2026 and without prejudice to the early termination rights set out in the Conditions, shall continue for an initial period of two (2) years (the Term) The initial term of the contract will be for two years with the option for the Authority to extend the contract annually for a further three years meaning the contract would run until at least 31 March 2028, but potentially up to 31 March 2031 if all extensions were taken. Therefore, if all extensions are taken, the total length of the contract will be for five years (2+1+1+1).
    Options
    It is anticipated that this contract shall commence on 8 December 2025 (the Commencement Date) which shall be the commencement of the Service Implementation and which shall complete on 31 March 2026. Following the Service Implementation, the remaining Services shall commence on 1 April 2026 and without prejudice to the early termination rights set out in the Conditions, shall continue for an initial period of two (2) years (the Term) The initial term of the contract will be for two years with the option for the Authority to extend the contract annually for a further three years meaning the contract would run until at least 31 March 2028, but potentially up to 31 March 2031 if all extensions were taken. Therefore, if all extensions are taken, the total length of the contract will be for five years (2+1+1+1).
    3 agreed KPIs: KPI 02 - Creation of Data Ingestion Specifications · KPI 10 - Refresh Success · KPI 11 - Data Supply Portal Availability
    • KPI 02 - Creation of Data Ingestion Specifications, The time taken for a Data Ingestion Specification to be created following successful data triage.
    • KPI 10 - Refresh Success, The number of total data refresh submissions that fail due to issues with the DT&I service or other factors within the Supplier’s control.
    • KPI 11 - Data Supply Portal Availability, The number of minutes in a month AOs can log onto the Data Supply Portal and upload or refresh their data, unless prior agreement is made with the Authority.
    • Good - performance is meeting or exceeding the KPI KPI 02 - Creation of Data Ingestion Specifications · to 30 Sept 2026
    • Good - performance is meeting or exceeding the KPI KPI 10 - Refresh Success · to 30 Sept 2026
    • Good - performance is meeting or exceeding the KPI KPI 11 - Data Supply Portal Availability · to 30 Sept 2026

Bid statistics published by the authority

BidsSMEVCSEValid bid range
6final-stage tenders40—

Who bid

Bidders as named on the Procurement Act 2023 award notice. “Won” means the bidder holds an award on this notice.

Contracting authority & participating public bodies

Ordnance Survey Limited

Contracting authorityPublic undertaking GB-COH: 09121572 Explorer House, Adanac Drive, Southampton, South East, SO16 0ASContact name, email

Bidders & participating suppliers

6 commercial parties on the notice · 1 awarded
  • 1Spatial Group LimitedAwarded supplierGB-COH: 04785688 Unit F7, Stirling House Cambridge Innovation Park, Denny End Road, Waterbeach, Cambridge, East of England, CB25 9PBContact email, phone
  • AtkinsRéalis UK LimitedBidder / tendererGB-COH: 00688424 Woodcote Grove, Ashley Road, Epsom, South East, KT18 5BW
  • BlueRose Technologies LimitedBidder / tendererGB-COH: 11024697 85 Brunner Road, London, London, E17 7NW
  • Datalynx LimitedBidder / tendererGB-COH: 04399948 2 Claridge Court, Lower Kings Road, Berkhamsted, East of England, HP4 2AF
  • VAAMG Consulting LimitedBidder / tendererGB-COH: 10087677 The White House Castlethorpe Road, Hanslope, Milton Keynes, South East, MK19 7HQ
  • Ve3 Global LtdBidder / tendererGB-COH: 07343436 Paul Street, 86-90 Paul Street, London, London, EC2A 4NE

Official documents & specifications (8)

Official links; attachments are not copied

Tender pack and attachments

  • Signed contract contractSigned contractPDFNational Underground Asset Register (NUAR) Data Transformation and Ingestion Services Contract - Commercially Redacted Version
  • Bidding documents and specifications tenderBidding documents and specificationsAll procurement documentation is available through the eTendering system used by Ordnance Survey (InTend) using the link above

Notices published for this procedure

  • Contract performance notice contractContract performance noticeUK9Contract performance notice on Find a Tender
  • Contract details notice contractContract details noticeUK7Contract details notice on Find a Tender
  • Contract award notice awardContract award noticeUK6Contract award notice on Find a Tender
  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Pipeline notice planningPipeline noticeUK1Pipeline notice on Find a Tender