What is being bought
Published requirement descriptionThe Provider is expected to design, supply and install the solar PV array and battery system which most efficiency reduce the running costs of Middletons Yard, balancing the solar array and battery sizing to maximise the £46,250 budget.
Request for Quotation for the full scope of works involved in designing, supplying and installing two solar arrays at 83-83a and 87 Bridge Street.
The Contractor will be responsible for developing the entire design of the solar PV array and battery system which will provide the greatest financial return within the £46,250 budget. This will require the following;
- PV array quantity, quality/brand, and orientation
- Inverter specification to match
- Battery sizing optimised for solar array size and consumption.
- Design connection to sites electrical infrastructure
The works to undertake the delivery and installation of solar PV and battery system.
Work includes, but not limited to:
- Initial electrical survey
- G99 electrical application
- Installation of two solar PV arrays
- Installation of battery system
- Full CAD Design for all installs (or similar/equivalent design drawings)
- Testing and certification of all final instalment
- Associated Electrical Works
- Associated Building Works including ensuring the roof is fit for purpose.
All drawings submitted as part of the Design Process or as instructed by the Council's Client Team in accordance with this contract shall be subject to appropriate Planning Permission and approvals. These permissions and approvals are to be sought and managed by The Provider.
The contractor will be responsible for gathering information relating to certain elements of the Project, all as detailed, as well as any other surveys/tests necessary for compliance with all statutory, legislative or any other requirements in relation to the type of works carried out, and to facilitate designs where applicable.
All designs to be CAD or similar/equivalent design drawings.
Costs associated with the above to design, supply and fix shall be priced for within the Price Framework, either as a specific Schedule of Works item or as a Provisional Sum.
It is expected the Solar PV array proposals will be accompanied with adequate designs, drawings and financial calculations to show the expected benefit from installation, which the contractor will be held accountable to.
An initial structural survey has been undertaken and is included in this tender pack as Appendix A for information only. The Council gives no warranty or representation as to the accuracy, completeness or suitability of that survey for the Provider's proposed design. The successful Provider shall be deemed to have satisfied itself as to the structural adequacy of the buildings and shall be solely responsible for all surveys, checks, calculations, assumptions and design work necessary to support its proposal and deliver the works
Exit Strategy / Handover at End of Contract
An onsite inspection to be arranged with BDC prior to handover.
Handover pack from the Provider to include:
- MCS Certificate: Proves the installation is certified for export tariffs (e.g., SEG).
- Electrical & Building Regulations Certificates: Electrical Installation Certificate (EIC) and Building Regulations Part P notification.
- DNO Connection Letter: Confirmation of grid approval from the Distribution Network Operator (G98/G99).
- Warranties: Proof of the manufacturer's equipment warranties (panels 20-25 years, inverters 5-10 years) and Insurance Backed Guarantees (IBGs).
- Manuals & Schematics: Single-line electrical drawings, system schematics, and startup/shutdown procedures
- Confirmation of PV ownership
CPV: Solar panel roof-covering work
The lotProcurement structure
single lot · value publishedLot #1Published value£46,200
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Lot awarding rule: Quality 80% Pricing 20% Total 100% Quality Breakdown: Return on Investment 50% Experience 30% Equipment Details 10% Social Value 10% Total 80% Return on Investment Please complete the ROI spreadsheet in Appendix B and include it with your return. Half-hourly consumption data has been provided to support an accurate forecast. This section will not count towards the word limit. Bassetlaw District Council expects batteries and inverters to be replaced during the lifetime of the PV array. This should be reflected in the annual expenditure column of the ROI spreadsheet. Contractors should also explain how their proposed system design delivers the best return on investment while making full use of the available budget. This must be supported by PV modelling software that confirms the key variables. Your response should include a full breakdown of the system design and a schematic showing the layout of the solar arrays. (Maximum 500 words, 50% Weighting) Answer: Experience Please demonstrate your experience in managing similar projects in scale, complexity and of a decarbonisation nature. Please include reference to what and how timescales were successfully met as well as with specific reference to your experience supporting and delivering solar PV projects on live sites. (Maximum 500 words, 30% Weighting). Answer: Equipment Details Please provide details of the equipment you intend to use to complete the work, explaining how this will meet all requirements and complies with relevant regulations. Please also provide the relevant accreditations and qualifications of all staff who will be on site using the equipment. (Maximum 250 words, 10% Weighting). Answer: Social Value Please provide details of your company's social value outputs (Maximum 250 words, 10% Weighting). Answer:
Procedure terms & legal framework
From the official record- Procedure method
- Below threshold - open competition
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Closed
- Procurement threshold
- Below threshold
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 5 Jun 2026, 08:26 BST
- Last source update
- 5 Jun 2026, 08:26 BST
- FTS notice number
2026/S 000-053107- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-06ae32Find a Tender
- Reserved participation area
- E10000024
How it was run
Official notice- Submission deadline
- 10 Jul 2026, 23:59 BST
- Clarification deadline
- 26 Jun 2026, 23:59 BST
- Electronic submission
- Not allowed
All tenders to be submitted to [email protected]
Site Visits:
Arrangements for site visits: Via the Project Officer, Emma Illingworth
Telephone: 07725 768421
Email: [email protected]
Officer will be on annual leave until 16th June, working days are Tuesday, Wednesday and Thursday.
Timeline
5 Jun 2026 → 10 Aug 2026 · 4 dates- Tender notice published140 days ago5 Jun 2026, 08:26 BST
- Clarification questions by119 days ago26 Jun 2026, 23:59 BST
- Submission deadline105 days ago10 Jul 2026, 23:59 BST
- Contract starts75 days ago10 Aug 2026, 00:00 BST
Notice history
1 event · 1 release on Find a Tender- Tender notice published5 Jun 2026, 08:26 BSTUK4
Contracting authority & participating public bodies
Official documents & specifications (3)
Official links; attachments are not copiedTender pack and attachments
Notices published for this procedure
- Tender notice Tender notice on Find a Tender