Authority: THAMES WATER UTILITIES LIMITED
What is being bought
Published requirement descriptionThames Water Utilities Limited intends to establish the Major Projects Framework following a competitive procurement procedure. The framework is intended to support the development and delivery of major water and wastewater capital projects across Thames Water's operational area during Asset Management Period 8 (AMP8), with provision for use during AMP9 subject to the framework terms and applicable approvals.
The framework will provide a route for the award of project-specific contracts covering pre-construction services, engineering, construction and associated works, goods and services. Individual project contracts will be progressed in accordance with the framework's call-off arrangements and relevant project approvals. This notice concerns the intended framework appointments.
- How the procedure runs: Requests to Participate Stage This Tender Notice invites a request to participate from Applicants. Having reviewed the Tender Notice, all Applicants wishing to participate in the Major Projects Framework competition will need to demonstrate in their submissions that they meet the Conditions of Participation set out in the Procurement Specific Questionnaire Pack (PSQ Pack) and complete a Non-Disclosure/Confidentiality Agreement. Applications will be submitted via the contracting authority's portal as described in the PSQ Pack - Part 1 Instructions to Applicants. The contracting authority will assess the Applicant's submissions and be shortlisted based on several pass/fail questions on financial standing, insurances, health and safety etc along with 4 scored questions. The weighting of the scored questions is listed below; Core Capability 55% Supply Chain 15% Health, Safety & Wellbeing 15% Environmental & Sustainability 15% Scored submissions will be ranked from highest to lowest and, subject to the procedure set out in the PSQ Pack, the contracting authority intends to invite the Applicants of the top ten (10) highest scoring compliant submissions to tender for the Major Projects Framework AMP8/9. Invitation to Negotiate (ITN) Stage The contracting authority will share with the shortlisted Applicants an Invitation to Negotiate (ITN) against which such Applicants will be invited to submit a tender. Tender submissions will be evaluated in accordance with the objective criteria set out in the ITN. Technical Questions will be made available at ITN Stage and will follow the question themes and weightings below: • Pre-Construction and Programme Delivery (35%) • Delivery, Risk and Commercial Management (20%) • Organisation, Collaboration and Behaviours (15%) • Health, Safety, Wellbeing and Sustainability (20%) • Innovation and Continuous Improvement (10%) Negotiation Stage The contracting authority may engage in negotiations with tenderers as set out further in the ITN. Records of any negotiations and agreements reached will be kept by the contracting authority. For the avoidance of doubt, the contracting authority reserves the right to award the framework without any negotiation, on the basis of the most advantageous tenders submitted at the ITN Stage. Following any negotiation stage, the contracting authority also reserves the right to invite tenderers to submit an updated tender, as explained further in the ITN. Following the submission of any BAFO's updated tenders, the contracting authority will complete the tender evaluation process and award places on the Major Project Framework Agreement to up to eight (8) most advantageous tenders in accordance with the objective criteria set out in the ITN.
CPV: Works for complete or part construction and civil engineering work
How this framework works
From the published notice- Type
- Closed framework
- Call-offs
- every call-off is a further competition among the appointed suppliers
- Places
- up to 8 suppliers · 12 appointed (full)
- Framework period
- 4 yrs · up to 9 yrs from 31 Mar 2026
Published description of the framework
As per tender documents
The lotProcurement structure
single lot · value publishedLot #1AwardedRenewalPublished value£4,000,000,000
- Economic & financial standing
As per PSQ documents
- Technical & professional ability
As per PSQ documents
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (2)
- Technical: 60%
- Commercial: 40%
Published award criteria (2)
- Technical: Technical sub-criteria and associated weightings will be developed prior to tender invitation and set out in the ITN.
- Commercial: Commercial sub-criteria and associated weightings will be developed prior to tender invitation and set out in the ITN.
- Economic & financial standing
As per PSQ documents
- Technical & professional ability
As per PSQ documents
- Price carries 40 of 100 points: a 10% discount moves about 4 points. The method statement decides this lot, not the discount.
- “Major Projects Framework AMP8/9” is a framework: the contest is a place on its panel, up to 8 suppliers, not a single contract: each call-off is a further competition, so the pricing contest starts after appointment.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Competitive flexible procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Awarded
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Utilities
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 4 Jul 2025, 14:20 BST
- Last source update
- 23 Oct 2026, 16:59 BST
- Award evaluation window
- Submission end – 17 Mar 2026
- Authority reference
FA2280- FTS notice number
2025/S 000-058213- Latest notice
- Contract award notice (UK6)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-055934Find a Tender
- How it runs
Requests to Participate Stage
This Tender Notice invites a request to participate from Applicants. Having reviewed the Tender Notice, all Applicants wishing to participate in the Major Projects Framework competition will need to demonstrate in their submissions that they meet the Conditions of Participation set out in the Procurement Specific Questionnaire Pack (PSQ Pack) and complete a Non-Disclosure/Confidentiality Agreement.
Applications will be submitted via the contracting authority's portal as described in the PSQ Pack - Part 1 Instructions to Applicants.
The contracting authority will assess the Applicant's submissions and be shortlisted based on several pass/fail questions on financial standing, insurances, health and safety etc along with 4 scored questions. The weighting of the scored questions is listed below;
Core Capability 55%
Supply Chain 15%
Health, Safety & Wellbeing 15%
Environmental & Sustainability 15%
Scored submissions will be ranked from highest to lowest and, subject to the procedure set out in the PSQ Pack, the contracting authority intends to invite the Applicants of the top ten (10) highest scoring compliant submissions to tender for the Major Projects Framework AMP8/9.
Invitation to Negotiate (ITN) Stage
The contracting authority will share with the shortlisted Applicants an Invitation to Negotiate (ITN) against which such Applicants will be invited to submit a tender. Tender submissions will be evaluated in accordance with the objective criteria set out in the ITN.
Technical Questions will be made available at ITN Stage and will follow the question themes and weightings below:
- Pre-Construction and Programme Delivery (35%)
- Delivery, Risk and Commercial Management (20%)
- Organisation, Collaboration and Behaviours (15%)
- Health, Safety, Wellbeing and Sustainability (20%)
- Innovation and Continuous Improvement (10%)
Negotiation Stage
The contracting authority may engage in negotiations with tenderers as set out further in the ITN. Records of any negotiations and agreements reached will be kept by the contracting authority.
For the avoidance of doubt, the contracting authority reserves the right to award the framework without any negotiation, on the basis of the most advantageous tenders submitted at the ITN Stage.
Following any negotiation stage, the contracting authority also reserves the right to invite tenderers to submit an updated tender, as explained further in the ITN.
Following the submission of any BAFO's updated tenders, the contracting authority will complete the tender evaluation process and award places on the Major Project Framework Agreement to up to eight (8) most advantageous tenders in accordance with the objective criteria set out in the ITN.
How it was run
Official notice- Requests to participate (first stage)
- 15 Oct 2025, 10:00 BST
- Appointment period ends
- 15 Oct 2025, 10:00 BST
- Clarification deadline
- 6 Oct 2025, 10:00 BST
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
- Accepted languages
- en
To request access to the PSQ documents, please fill out the details in this form;
Timeline
4 Jul 2025 → 3 Nov 2026 · 11 dates- Planning notice published4 Jul 2025, 14:20 BST
- Market engagement4 Jul 2025, 23:59 BST
We invite interested parties to participate in our preliminary market engagement for the AMP8/9 major projects Framework. We have made a detailed Head of Terms and project list available via our secure data room.
An introductory webinar will be held on 16th July 2025 to explain the programme, guide access to the data room, and address high-level queries. The registration window will remain open from the engagement date of publication until the close of this market engagement period in mid-September 2025. Interested contractors may register and access the data room at any point during this period.
To access the data room, please complete the form by clicking the following link; forms.office.com/e/8tWiii5Lyi ↗. Please contact [email protected] with any queries.
- Tender notice published400 days ago19 Sept 2025, 15:39 BST
- Next notice expected400 days ago19 Sept 2025, 23:59 BST
- Clarification questions by384 days ago6 Oct 2025, 10:00 BST
- Admission / appointment period ends375 days ago · period end, not a bid countdown15 Oct 2025, 10:00 BST
- Award decision expected by221 days ago17 Mar 2026, 23:59 GMT
- Contract starts208 days ago31 Mar 2026, 00:00 BST
- Assessment summaries sent2 days ago23 Oct 2026, 00:00 BST
- Latest notice published1 day ago23 Oct 2026, 16:59 BST
- Today24 Oct 2026
- Standstill endsin 10 days3 Nov 2026, 23:59 GMT
Notice history
10 events · 4 releases on Find a Tender · since 4 Jul 2025- Preliminary market engagement notice published4 Jul 2025, 14:20 BSTUK2
- Planned procurement notice published3 Sept 2025, 09:51 BSTUK3
- Status changed to planned3 Sept 2025, 09:51 BST
- Procurement method changed3 Sept 2025, 09:51 BST
- Tender notice published19 Sept 2025, 15:39 BSTUK4
- Published value updated to £4,000,000,00019 Sept 2025, 15:39 BSTwas £840,000,000
- Status changed to active19 Sept 2025, 15:39 BST
- Contract award notice published23 Oct 2026, 16:59 BSTUK6
- Status changed to complete23 Oct 2026, 16:59 BST
- Contract signature expected4 Nov 2026, 23:59 GMTscheduled
Routine re-releases (4)
- 2025-07: 1 release · 4 Jul 2025
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast£4,000,000,000 is the framework's published maximum, restated by the publisher on 9 award rows. It is one ceiling, not 9 separate sums, and no share per lot is published; those rows read “ceiling above”.
| Awarded to | Value | Date | Status |
|---|---|---|---|
| BAM Nuttall Limited4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| Barhale Ltd4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| Costain Limited4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| Binnies UK Ltd, CADAGUA, S.A., FERROVIAL CONSTRUCTION (UK) LIMITED4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| J Murphy and Sons Limited4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| AMENTUM ENTERPRISE ASSET SOLUTIONS LIMITED, Taylor Woodrow Infrastructure Limited4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| Galliford Try Construction Limited4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| KIER INFRASTRUCTURE AND OVERSEAS LIMITED4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
| Mott MacDonald Bentley Limited4 Nov 2026 – 31 Mar 2030 · up to 31 Mar 2035Extensions: Thames Water Utilities Limited may extend the framework beyond its initial term, in accordance with the extension provisions set out in the Framework Agreement and subject to any applicable approvals, up to a maximum expiry date of 31 March 2035. · Options: The right to extend the term of the framework as set out above. | ceiling above | 23 Oct 2026standstill to 3 Nov 2026 | Standstill |
Contracting authority & participating public bodies
Framework contractors & participating bidders
12 commercial parties on the notice- AMENTUM ENTERPRISE ASSET SOLUTIONS LIMITEDFramework contractor
- BAM NUTTALL LIMITEDFramework contractor
- BINNIES UK LIMITEDFramework contractor
- Barhale LtdFramework contractor
- CADAGUA, S.A.Framework contractor
- COSTAIN LIMITEDFramework contractor
- FERROVIAL CONSTRUCTION (UK) LIMITEDFramework contractor
- GALLIFORD TRY CONSTRUCTION LIMITEDFramework contractor
- J. MURPHY & SONS LIMITEDFramework contractor
- KIER INFRASTRUCTURE AND OVERSEAS LIMITEDFramework contractor
Show 2 more suppliers
- MOTT MACDONALD BENTLEY LTDFramework contractor
- TAYLOR WOODROW INFRASTRUCTURE LIMITEDFramework contractor
Official documents & specifications (12)
Official links; attachments are not copiedNotices published for this procedure
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
Show 4 more notices
- Contract award notice Contract award notice on Find a Tender
- Tender notice Tender notice on Find a Tender
- Planned procurement notice Planned procurement notice on Find a Tender
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender