Large Scale Non-Battery based Electrical Energy Storage Systems
Electrical power systems design services
Engineering design services
Plant engineering design services
UK
Published value
£0
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: UK FUSION ENERGY LTD: "Large Scale Non-Battery based Electrical Energy Storage Systems". Published status: planning. Published value: £0. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | UK FUSION ENERGY LTD | Scope & Categories | Not published | Submission Window | planning No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | £0 |
Bidder Intelligence · Authority Profile: UK FUSION ENERGY LTD
Market Analytics
Derived from OCDS awards & bid statistics
Published history for UK FUSION ENERGY LTD. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Competition Density
5.4Bids / Report
Supplier ConcentrationLow Concentration
NPL Management LtdTop vendor: 18.1% of attributable valuePayment Terms
Check noticePublished terms
Coverage: 40 active published awards; 11 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Historical Awarded Suppliers With This Authority:
| Supplier Name | Historic Awards | Attributable GBP Value |
|---|---|---|
| NPL Management Ltd | 1 win | £192,091 |
| KPMG LLP | 1 win | £175,000 |
| MuWave Limited | 1 win | £168,234 |
| Amentum Clear Energy Limited | 1 win | £100,367 |
| QMC Instruments | 1 win | £99,499 |
Procedure terms
Contracting AuthorityUK FUSION ENERGY LTD | Procedure methodNot published | Procurement categoryNot published |
Statusplanning | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published27 Jan 2026, 14:05 GMT | Last source update27 Jan 2026, 14:05 GMT | Recurring procurementNot published |
ClassificationElectrical power systems design services, Engineering design services, Plant engineering design services | ||
Delivery area UK | ||
OCIDocds-h6vhtk-060fbe | ||
What is being bought
The following summary is not intended as a complete or definitive specification of the requirement. A purpose of this engagement is to seek information from the market to help refine our understanding and aid the development of a future specification.
STEP is currently in its Concept Design phase, which is expected to be completed by 2026.
The electrical infrastructure of STEP will resemble that of large conventional thermal power stations; however, its design presents unique challenges:
Fusion power stations like STEP have exceptionally large parasitic (auxiliary/house) loads required to initiate and sustain fusion reactions—significantly higher than those in conventional power plants.
These parasitic loads must be supplied by external sources during plant start-up, before the power generation cycle begins producing electricity.
The highly dynamic nature of these loads could make compliance with grid code requirements challenging.
For more information, please refer to: Staying positive: producing net power | Philosophical Transactions of the Royal Society A | The Royal Society
UKIFS is seeking experts to support the technology selection of a Central Energy Storage System (CESS) that is part of the STEP Electrical infrastructure. Due to the power dynamics of operating the STEP power plant and the operating parameters set by the National Energy System Operator (NESO), an energy storage system is required to provide a mechanism to ensure that we remain within the NESO operating parameters.
Rather than a continuous output, STEP will operate on a pulsed basis. The power dynamics of the fusion pulses are typically different to a conventional power plant. The CESS has been identified as a critical system to the design as it provides a mechanism to compensate for the changing load dynamics throughout the pulse. This will ensure STEP remains within the NESO defined operating parameters at the point of grid connection.
The scope of the CESS cannot be fully defined due to knowledge gaps in CESS behaviour and limitations. Once these are understood, a technology will be selected, and limitations will be incorporated into the electrical infrastructure design. This PME is looking to address the knowledge gaps.
The proposed technical and operations of the CESS are
•2 operational cycles per day
•Pulse length will be over 1 hour (continuous)
•Power range larger than 300MW
•Energy capacity 100-300MWh
•Response in the millisecond range
•Similar charge and discharge rates.
•Fast response time during power swings (full charge to discharge)
•High round trip efficiency: 80%
In conjunction the CESS will be required to be operated and maintained for the 20-year life of the STEP machine.
Due to the requirements, we are attempting to ascertain if this could be accomplished or partly accomplished by a non-battery-based system (Flywheel, Super-conducting magnetic storage (SMES), Capacitor, Super Capacitor, Fuel Cells or other)
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://www.delta-esourcing.com/tenders/UK-UK-Culham:-Engineering-design-services./W8UFJUNW28
To respond to this opportunity, please click here:
https://www.delta-esourcing.com/respond/W8UFJUNW28
What changed
From the official release history
- tender value changed
27 Jan 2026, 14:05 GMT - Status changed to planning
27 Jan 2026, 14:05 GMT - Official notice release published
27 Jan 2026, 14:05 GMT - Buyer information updated
27 Jan 2026, 14:05 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedplanningPublished valueNot publishedThe source published no individual title or description for this lot.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Pipeline notice
27 Jan 2026, 14:05 GMT - Procedure published
27 Jan 2026, 14:05 GMT - engagement
24 Mar 2026, 23:59 GMT · scheduledTo participate in this exercise, please complete and submit Appendix 1: Questionnaire and return any documents via the Delta portal. We are conscious of your time (and grateful to you for taking the time to complete the questionnaire), therefore we suggest you limit your responses to a maximum of 5 pages. If there are any areas you would like to expand on, please add a note to the relevant section for future discussion. If you experience any difficulties with the portal, please contact the portal helpdesk helpdesk@delta-esourcing.com cc operationalprocurement.step@ukifs.uk Information obtained from responses to Appendix 1: Questionnaire will help UKIFS understand current market capabilities and may shape the scope, direction, and design of the future procurement activities. If you have any questions about this Preliminary Market Engagement, please contact UKIFS through the Delta portal. We are keen to engage with suppliers to assist with the questionnaire if needed, to ensure quality responses enabling us to shape the future requirement and procurement. Following the submission and review of questionnaires, UKIFS intends to run an online conference call meeting/seminar/Q&A. The closing date for the pre-market engagement is Monday 23rd March 2026, 1 pm.
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
UK FUSION ENERGY LTD
Contracting authority GB-PPON-PCRM-7973-DCBLDocuments (1)
Official links; attachments are not copied
- 27 Jan 2026, 14:05 GMT
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |