Find a Tender
planned
Official procurement procedure
J5 Reactive Power Compensation Compound Decommissioning
Demolition work
Demolition
site preparation and clearance work
+15 more
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: United Kingdom Atomic Energy Authority: "J5 Reactive Power Compensation Compound Decommissioning". Published status: planned. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | United Kingdom Atomic Energy Authority | Scope & Categories | Not published | Submission Window | planned No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: United Kingdom Atomic Energy Authority
Market Analytics
Derived from OCDS awards & bid statistics
Published history for United Kingdom Atomic Energy Authority. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
12.5Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 182 active published awards; 175 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityUnited Kingdom Atomic Energy Authority | Procedure methodNot published | Procurement categoryNot published |
Statusplanned | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published10 Jul 2023, 12:24 BST | Last source update10 Jul 2023, 12:24 BST | Recurring procurementNot published |
ClassificationDemolition work, Demolition, site preparation and clearance work, Dismantling equipment, Dismantling works, Earthmoving work, Excavating and earthmoving work, Excavating work, Infill and land-reclamation work, Infill work, Non-hazardous refuse and waste treatment and disposal services, Radioactive-, toxic-, medical- and hazardous waste services, Site preparation and clearance work, Siteworks, Toxic waste disposal services except radioactive waste and contaminated soil, Waste disposal site construction work | ||
Delivery area | ||
OCIDocds-h6vhtk-03e035 | ||
What is being bought
JET Decommissioning and Repurposing
J5 Reactive Power Compensation Compound:
The J5 Reactive Power Compensation (RPC) compound, is a legacy facility located in the northern area of the Culham Science Campus. Operating from early 1990s to 2012 the purpose of the J5 RPC system (external compound and internal network) was to avoid causing disturbances to the 400kV National Grid supply as a result of large power pulses on site.
The RPC compound has been left in a quiescent state since it was disconnected from the Joint European Torus power supplies and mothballed.
The J5 RPC compound contains high voltage, low voltage, and extra low voltage electrical equipment including resistors, capacitors (624 high voltage oil filled capacitors to be exact), inductors, and surge arresters along with cable and busbar systems.
Please refer to attached documents for further details.
What changed
From the official release history
- Status changed to planned
10 Jul 2023, 12:24 BST - Official notice release published
10 Jul 2023, 12:24 BST - Buyer information updated
10 Jul 2023, 12:24 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedplannedPublished valueNot publishedDecommissioning and Repurposing: Under the agreement to host the JET machine, when JET finishes operations, the UK retains responsibility for decommissioning the machine and associated facilities. In 2022 the JET Decommissioning and Repurposing programme within UKAEA was set up to review the JET decommissioning plan and identify whether modern technologies and methodologies can be used to decommission smarter, quicker, cheaper, and safer. It was also decided to review alternative end of life scenarios to repurpose plant, equipment, and facilities thereby promoting sustainability and aiding other research and development programmes both domestically and internationally. J5 Reactive Power Compensation Compound: The J5 Reactive Power Compensation (RPC) compound, shown in Figure 1, is a legacy facility located in the northern area of the Culham Science Campus. Operating from early 1990s to 2012 the purpose of the J5 RPC system (external compound and internal network) was to avoid causing disturbances to the 400kV National Grid supply as a result of large power pulses on site. The RPC compound has been left in a quiescent state since it was disconnected from the Joint European Torus power supplies and mothballed. The J5 RPC compound contains high voltage, low voltage, and extra low voltage electrical equipment including resistors, capacitors (624 high voltage oil filled capacitors to be exact), inductors, and surge arresters along with cable and busbar systems.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
10 Jul 2023, 12:24 BST
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
United Kingdom Atomic Energy Authority
Contracting authority GB-FTS-1212Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published