Official UK procurement notice
Client Support Framework (CSF)
Authority: East West Rail Company Limited (Central government)
What is being bought
Published requirement descriptionThe East West Railway Company (the Authority) is responsible for the delivery of East West Rail (EWR), a Nationally Significant Infrastructure Project providing new and upgraded rail links between Oxford, Milton Keynes, Bedford and Cambridge. EWR Co. is responsible for leading the development, procurement, and commissioning of the railway.
The Authority is undertaking preliminary market engagement in advance of a planned procurement for Client Support Framework (CSF) Partners to support the development and delivery of the EWR programme.
This notice is issued to inform the market of the Authority's current thinking, to seek clarifications and respond to all interested suppliers. This is not a call for competition.
Overview of the Intended Contract
The Authority is considering the establishment of a 3 lot / single appointed supplier per lot framework for the provision of Client Support Services (CSF) for a period of up to twelve (12) years, with performance and scope breakpoints at Years 3, 6 and 9.
Relationship with the ITOAE Partner
The Authority is separately considering the procurement of an Integration, Technical, Operations, Assurance and Environmental (ITOAE) Partner.
The Authority's current position is that the CSF partners will be structurally separated from the ITOAE, such that the appointed CSF Partners will not be eligible to be appointed under the ITOAE for the duration of the CSF contracts. The purpose of this separation is to protect the independence of assurance and advice, to mitigate real or perceived conflicts of interest, and to align with independent review findings on major programme governance (including the Stewart Review, 2025).
The Authority is testing this position through this preliminary market engagement. The final Conditions of Participation will be confirmed in the tender documentation and will be set in accordance with the Authority's obligations under the Procurement Act 2023 and the Procurement Regulations 2024.
Indicative Scope of Services
At this stage, the Authority has defined the high-level scope of services. These are expected to include (but are not limited to), at Lot level
Lot 1 – Reporting and Controls / PMO Support
Programme, portfolio and package level reporting:
- cost, schedule, risk, issue and change dashboards;
- consolidated programme performance reporting
Planning and scheduling support:
- development, maintenance and assurance of master and integrated schedules;
- critical path, float and scenario analysis;
- schedule change control support.
Cost and performance controls:
- cost forecasting and EAC support;
- reconciliation of cost, schedule and scope baselines;
- trend analysis and early warning indicators.
Risk, issue and opportunity management support:
- maintenance of programme and workstream risk registers;
- quantitative risk analysis (QRA) support;
- interface with assurance and gateway preparation.
Management information (MI) production:
- Board, Sponsor and DfT packs;
- standardised reporting templates and data definitions;
- audit ready evidence trails.
Controls systems and data governance:
- toolset configuration and administration (e.g. planning, cost, risk tools);
- data quality checks and consistency rules;
- document and records management interfaces.
Lot 2 – Commercial Management and Contract Administration support
Procurement support:
- pre tender estimation;
- commercial evaluation;
- commercial support during tender processes
Contract administration:
- management of notices, instructions, early warnings and compensation events;
- administration of NEC (or equivalent) processes;
- maintenance of contractual registers and correspondence logs.
Change control and forecasting support:
- cost planning, estimating and cost engineering;
- development and maintenance of cost estimates;
- assessment and logging of change events;
- affordability and cost assurance of options
Payment and cost management support:
- valuation support;
- payment application assessment;
- reconciliation against cost records.
Claims avoidance and dispute support:
- contemporaneous record management;
- support to dispute resolution processes;
- preparation of evidence packs (without advocacy role unless instructed).
Supplier performance and compliance monitoring:
- performance data collation against contractual KPIs;
- payment practice and supply chain compliance checks.
Commercial data and audit support:
- audit responses and evidence collation;
- benchmarking and affordability analyses.
Lot 3 – Project & Construction Management Support
Project and package management support:
- workstream coordination and day to day management support;
- delivery plan development and tracking;
- action management and follow up.
- Interface and dependency management:
- coordination across contractors, designers, third parties and stakeholders;
- management of interface schedules and logs.
Programme governance support:
- preparation of governance boards and working groups;
- action and decision tracking;
- support to stage gate and readiness reviews.
Stakeholder and third party coordination, including:
- support to statutory undertaker, local authority and regulator engagement;
- tracking of commitments and undertakings.
Transition and mobilisation support:
- support to phase transitions (e.g. design to construction);
- readiness planning and handover coordination.
Delivery performance support:
- progress measurement and reporting;
- recovery planning support (without authority to direct suppliers).
Construction Management:
- Clerk of works/Site Inspector
- Construction Supervisor/Compliance Manager
- Quality Assurance
- Health & Safety
- CDM compliance.
- Contract Form – NEC4 Professional Service Contract
- Estimated total value - £230 million -£350 million *
*The indicative value range reflects a twelve (12) year term. The final value will be confirmed in the tender notice and is subject to internal approval and the outcome of this engagement.
CPV: Construction project management services · Consultative engineering and construction services · Engineering services · Health and safety consultancy services · Infrastructure works consultancy services · Project management consultancy services · Railway engineering services · Supervision of project and documentation · Transport systems consultancy services
How this framework works
From the published notice- Framework period
- 3 yrs · up to 12 yrs from 1 May 2028
The lotProcurement structure
single lot · no lot value publishedWhat it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
- “Client Support Framework (CSF)” is a framework: the contest is a place on its panel, not a single contract.
Pipeline intelligence · planning stage: how this market runs before the tender is published
Consultative engineering and construction services (CPV 7131) in South East England, and who usually turns up
East West Rail Company Limited has too little published record in this market to describe on its own. Published market evidence for the same work stands beside whatever it has. This notice is a framework or DPS, so only frameworks and DPS are compared. Whole-market view: Consultative engineering and construction services (CPV 7131) →
How the contest usually goes
Winner shares use published awards; bid and price charts use contested lots.
i
How often small and medium firms win.
Share of awards where the winner’s size is known.
The counts under this question show how many awards have a known supplier size.
No supplier sizes published for this authority.
i
How often local firms win similar work.
Winners with a registered address in the delivery region, out of awards with a known address.
Here, local means registered in South East England.
A local branch does not count if the registered address is elsewhere.
No winner locations published for this authority. Local means a registered address in South East England.
i
How long buyers here take to decide after bids close.
Middle value in days from the deadline to the first award notice, on competitions that published both dates.
Only decided tenders count, so slow ones still waiting are not in.
Half of these awards were announced within 101 days of the bid deadline.
i
How often work is awarded with no recorded rival.
Direct awards and tenders where every published lot count shows one bid.
The market share is a minimum: some awards have no bid count.
Thin markets produce this too; it is not proof of a tailored specification.
Missing bid counts may hide more single-bid awards. This share is a minimum.
How many bids did past lots attract?
i
How many bids past lots received.
Each colour is a bid-count range. Only competed lots with a published count are included.
Past bids do not predict this tender.
1 bid2%
2–39%
4–616%
7+72%
How did awards compare with estimates?
i
Where winning prices landed against estimates.
Each colour shows awards below, close to or above the published estimate, one lot at a time.
On a framework or DPS, prices are agreed when work is called off.
Past prices are a guide, not a bid price.
Not comparable on a framework or DPS. The notice sets up a supplier panel and a ceiling value; what the work actually costs is agreed later, on each call-off or mini-competition, and those publish as contract notices of their own. The award-vs-estimate record of this market therefore sits on the call-offs; this page shows it on the contracts, not on the panel that frames them.
Assess each lot i
What past awards tell you about each lot.
See the forecast, this buyer’s earlier suppliers and firms with relevant wins.
No supplier is confirmed as a bidder.
i
What past awards tell you about each lot.
See the forecast, this buyer’s earlier suppliers and firms with relevant wins.
No supplier is confirmed as a bidder.
Open a lot for its forecast, this buyer’s previous supplier and possible competitors, from published award history, not a bid list
Lot #1CPV 7131Published estimate£350m
i
How many bids this lot may attract.
The forecast uses similar past competitions. The bar shows either that forecast or past bid counts; the line below says which.
Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative. The bar shows 43 past lots.
A forecast, not a list of bidders.
1 bid2%
2–39%
4–616%
7+72%
i
Where the award price may land.
The forecast uses similar awards and the buyer’s estimate. The band covers the middle half of likely prices.
No comparable awards for this lot yet.
A statistical guide from past awards, not a price to bid.
Who has supplied this buyer on similar work? i
Who has done similar work for this buyer.
Past contracts are matched by buyer, title and type of work.
A past supplier may not bid again.
i
Who has done similar work for this buyer.
Past contracts are matched by buyer, title and type of work.
A past supplier may not bid again.
No earlier contract of this buyer matches this lot on the published record.
Who could compete for this lot? i
Who could compete for this lot?
Firms with relevant past wins. On a framework, we show firms on that agreement.
None is confirmed as a bidder.
i
Who could compete for this lot?
Firms with relevant past wins. On a framework, we show firms on that agreement.
None is confirmed as a bidder.
Candidate suppliers for this notice have not been worked out yet, so this is not a verdict that nobody fits.
About this data
- Source. Official UK public procurement notices (Find a Tender), reused under the Open Government Licence v3.0. New notices arrive through the day; the figures are rebuilt nightly.
- Two views, kept apart. The authority’s own track record and the wider market for the same kind of work sit side by side and are never mixed. Where the local picture is too thin, a figure widens to a broader market and says which one it used.
- Forecasts are labelled. The price forecast and its range, possible competitors and the earlier-work matches are our estimates from past awards: not published facts, not win chances and not price advice. Official notices do not say who is bidding.
- Every figure shows what it rests on. Not every notice publishes a bid count, a value or a delivery region, so each figure carries the number of records behind it, and one built on few records is marked as such. The on a figure explains it; the counting rules are in the methodology. Spotted something wrong? Tell us.
Procedure terms & legal framework
From the official record- Procedure method
- Competitive flexible procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Services
- Notice status
- Planned procurement
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Utilities
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 26 May 2026, 16:10 BST
- Last source update
- 16 Oct 2026, 16:35 BST
- Authority reference
CT5466- FTS notice number
2026/S 000-098177- Latest notice
- Preliminary market engagement notice (UK2)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-06a433Find a Tender
How it was run
Official notice- Appointment period ends
- —
Timeline
26 May 2026 → 1 May 2028 · 5 dates- Planning notice published147 days ago26 May 2026, 16:10 BST
- Latest notice published4 days ago16 Oct 2026, 16:35 BST
- Today20 Oct 2026
- Market engagementin 9 days28 Oct 2026, 23:59 GMT
Objectives
This preliminary market engagement under s16 PA23 is being undertaken to:
- Inform the market by way of a market engagement presentation outlining the proposed procurement for a 12-year single supplier per lot / 3 Lot CSF Partner model, including breakpoints at Years 3, 6, and 9.
- To invite interested parties to raise clarification questions by Wednesday 21st October 2026 which will be collated and responses made to all interested parties unless agreed as confidential.
- Confirm if the approach is in line with the market offering and to inform East West Rail in finalising the proposed tender activity.
Key Dates
- Registration Deadline – Tuesday 20th October 2026, 17:00
- Market Clarification Deadline – Thursday 22nd October 2026, 17:00
- EWR Response to Clarification Deadline – Wednesday 28th October 2026, 17:00
To register interest, potential suppliers should:
- Register on the Authority's Jaggaer e-procurement portal, if not already registered East West Rail eastwestrail.ukp.app.jaggaer.com/esop/ogc-host/public… ↗
- Express interest in this preliminary market engagement via the Jaggaer portal by the registration deadline above, review presentation and forward clarifications via the Jaggaer portal.
On confirmation of registration, participants will receive a briefing presentation, setting out the Authority's current programme context, indicative scope of services, and proposed commercial approach. The presentation will provide the information necessary to brief the interested parties about the proposed procurement.
EWR is happy to seek clarifications about the proposed procurement which may include views from the market as to our proposed approach.
Points to Note
Please note the following important points before registering an interest:
- This PME is not a call for competition and is not published with the intention of reducing any time limits for the receipt of tenders.
- EWR Co. reserves the right not to commence any procurement process or award any contracts in respect of the EWR project and to amend the requirements stated in this PME (or as stated in any pre-procurement market engagement documents).
- EWR Co. will provide information on its emerging thinking on scope, commercial structure, and contracting approach via the briefing presentation and within the pre-procurement market engagement documents made available to registered suppliers. EWR Co. reserves the right to further develop and change the procurement strategy and/or other aspects of the proposed procurement and delivery strategy as a result of pre-procurement market engagement or otherwise.
- EWR Co. may undertake further pre-procurement market consultation exercises.
- Publication of this PME is part of the Authority's due diligence process on its options, and the publication of this PME does not indicate that a decision has been made on a particular route for a procurement and/or subsequent contract award, if any.
- Registration does not bind EWR Co. to include any party in the pre-procurement market engagement exercise.
- EWR Co. is not obliged to communicate with any parties that register after the deadline for registration has passed.
- EWR Co. is not obliged to respond to any correspondence on this notice or any matter related to this preliminary market engagement exercise. The decision to accept the registration of any interested party, and subsequent inclusion in any engagement process, shall remain with EWR Co. alone.
- Non-participation in this process will not prevent any party from participating in any procurement process in due course. Participation will not confer any advantage or disadvantage in any future procurement process.
- Given the early stage of the programme and the anticipated impact of the market engagement process and other internal processes, any information provided to the market shall be subject to change. EWR Co. (insofar as it is permitted by law) shall not be liable for any losses incurred by any party as a result of reliance on such information.
- Any values set out in this PME are indicative and subject to revision and to confirmation in any future notices in relation to EWR procurement.
- Tender notice expectedin 11 days30 Oct 2026, 23:59 GMT
- Contract starts1 May 2028, 00:00 BST
Notice history
4 events · 3 releases on Find a Tender · since 26 May 2026- Pipeline notice published26 May 2026, 16:10 BSTUK1
- Preliminary market engagement notice published3 Jun 2026, 16:05 BSTUK2
- Preliminary market engagement notice published16 Oct 2026, 16:35 BSTUK2
- Published value updated to £350,000,00016 Oct 2026, 16:35 BSTwas £300,000,000
Commercial outcome & contract awards
Pipeline notice- Awards (0)
- No award published
- Contracts (0)
- No contract published
- Bid statistics
- No aggregate bid statistics published
Contracting authority & participating public bodies
Official documents & specifications (3)
Official links; attachments are not copiedNotices published for this procedure
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender
- Pipeline notice Pipeline notice on Find a Tender