Find a TenderAwarded without competitionContract award notice
Published 5 Nov 2026, 13:26 GMT

Official UK procurement notice

Engineering Stage 5 (ES5) and Enabling Works for upgrade to Witton and Aston Rail Stations

Official notice

Authority: West Midlands Combined Authority (Local council)

Direct awardUtilities
Awarded value£4,221,520published award · exc. VAT
Award in standstill 30 Oct 2026no call for competition
Award (standstill) to Network Rail Infrastructure
Notice summaryFrom the published notice

The upgrade of Witton and Aston stations was identified as a Mayoral priority in April 2025, with delivery of the interventions to be completed ahead of the UEFA Euro 2028, which nearby Villa Park Stadium is set to host four international football matches. We are now proposing to continue the development phase into Engineering Stage 5 with Network Rail and in parallel commence advanced enabling works activities ahead of a targeted completion ahead of UEFA Euro 2028. To achieve programme and completion in advance of UEFA Euro 2028, enabling works are required in parallel to ES5 (detailed design) development.

What is being bought

Published requirement description

The upgrade of Witton and Aston stations was identified as a Mayoral priority in April 2025, with delivery of the interventions to be completed ahead of the UEFA Euro 2028, which nearby Villa Park Stadium is set to host four international football matches.

We are now proposing to continue the development phase into Engineering Stage 5 with Network Rail and in parallel commence advanced enabling works activities ahead of a targeted completion ahead of UEFA Euro 2028.

Design Development

The project has proceeded through design stages ES3 and ES4 and now needs to progress to detailed design. This is Engineering Stage 5 (ES5) in Network Rail's PACE framework. Additional elements for the next design phase include Overhead Line Equipment (OLE) isolation works to minimise disruption to the network in advance of the enabling works and core construction work phases, preliminary / personnel costs, contingency, and property and planning costs associated with the Waterworks site.

Enabling Works Need

To achieve programme and completion in advance of UEFA Euro 2028, enabling works are required in parallel to ES5 (detailed design) development.

The lotProcurement structure

single lot · no lot value published

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1some still in standstill
Awarded value £4,221,5201 award exc. VAT
Awarded toValueDateStatus
Network Rail InfrastructureEngineering Stage (ES5) and Enabling Works for Witton and Aston Rail Stations17 Nov 2026 – 16 Nov 2027£4,221,52030 Oct 2026standstill to 16 Nov 2026Standstill

Procedure terms & legal framework

From the official record
Procedure method
Direct award
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Utilities
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
5 Nov 2026, 13:26 GMT
Last source update
5 Nov 2026, 14:42 GMT
Authority reference
PRT-RAIL-WPG-2026-0004
FTS notice number
2026/S 000-105286
Latest notice
Contract award notice (UK6)
Delivery area
West Midlands (UKG3)
Official registry OCID
ocds-h6vhtk-07b40a Find a Tender
Why no open competition

Prototypes Development; Single Suppliers Intellectual Property Exclusive Rights; Single Suppliers Technical Reasons; Additional Repeat Extension Partial Replacement

Published justification

Additional or repeat goods, services or works

Previous ES3 and ES4 development work was awarded to Network Rail Infrastructure Limited under Direct Award Reports RFQ-WMRE-WPG-2025-0001 and MOD-RAIL-WPG-2026-0001. This DAR sets out the award to Network Rail for the next stage of work under ES5. ES5 represents the continuation and further development of the engineering design, surveys, technical assurance and project knowledge established through ES3 and ES4, providing continuity between design stages and avoiding unnecessary duplication or rework.

Prototypes and Development

This DAR relates to development of upgrades to existing rail stations at Witton and Aston and the work is reliant on NR to develop, assure and integrate the proposed designs with the existing operational railway, including determining compliance with applicable railway standards, asset requirements, safety processes and operational constraints. Network Rail's involvement is therefore integral to progressing the designs to the level of maturity required for subsequent delivery.

Single Supplier - intellectual property or other exclusive rights and there are no reasonable alternatives

As Network Rail owns the land and railway assets affected by the proposed works, they are best placed to manage the design and enabling solutions required for significant alterations to those assets and to manage the associated engineering, operational and safety risks. The proposed works cannot be developed independently of Network Rail's asset requirements, technical approvals and access arrangements. The owner of the land has a right to determine which supplier can deliver works on that land.

Single Supplier - absence of competition for technical reasons and there are no reasonable alternatives

As NR own the land and assets, they have the required capability to ensure that any works carried out are interoperable with existing assets, manage interfaces with new or altered infrastructure, manage permits and access to the operational railway and secure any required possessions. Use of an alternative supplier would require these matters to remain subject to Network Rail review, assurance and approval, introducing additional technical and organisational interfaces, with associated programme and delivery risk.

How it was run

Official notice
Submission deadline
—

Timeline

5 Nov 2026 → 16 Nov 2026 · 2 dates
  1. Notice published13h ago
    5 Nov 2026, 14:42 GMT
  2. Today
    6 Nov 2026
  3. Standstill endsin 10 days
    16 Nov 2026, 23:59 GMT

Notice history

3 events · 2 releases on Find a Tender · since 5 Nov 2026
  1. Transparency notice published
    5 Nov 2026, 13:26 GMT
    UK5
  2. Contract award notice published
    5 Nov 2026, 14:42 GMT
    UK6
  3. Contract signature expected
    17 Nov 2026, 23:59 GMT
    scheduled

Contracting authority & participating public bodies

West Midlands Combined Authority

Contracting authorityPublic authority - sub-central government GB-PPON: PGMD-1353-PZVX 16 Summer Lane, Birmingham, West Midlands, B19 3SDContact email

Bidders & participating suppliers

1 commercial party on the notice
  • Network Rail InfrastructureAwarded supplierGB-COH: 02904587 Waterloo General Office, London, London, SE1 8SWContact email

Official documents & specifications (2)

Official links; attachments are not copied

Notices published for this procedure

  • Contract award notice awardContract award noticeUK6Contract award notice on Find a Tender
  • Transparency notice awardTransparency noticeUK5Transparency notice on Find a Tender