Official UK procurement notice
DfI Rivers Directorate T-1163 Inspection and Maintenance of Underground Infrastructure Framework
Authority: DfI Transport and Road Asset Management (TRAM) (Central government)
The Department for Infrastructure Inspection and Maintenance of Underground Infrastructure Framework will include the following work activities: A) Desilting of Culverts. Please note: For this procurement, Suppliers submissions are required to be uploaded via the eTendersNI CfT under Lot 1: IMUF 1 (Greater Belfast Area). Published lot titles: IMUF1 - Greater Belfast Area; IMUF3 - Armagh & Lisburn Areas; IMUF2 - Coleraine, Omagh and Fermanagh Areas.
What is being bought3 lots · detail below
Published requirement descriptionThe Department for Infrastructure Inspection and Maintenance of Underground Infrastructure Framework will include the following work activities:
A) Desilting of Culverts
B) CCTV and Fly-through Surveys of Culverts
C) Trenchless / Specialist Repairs of Culverts
D) Traffic Management, Gaining Access to Culverts, Associated Civil Works
E) Small Scale Civil Works
F) Underground Man Entry Repairs
The Framework will comprise of three area Lots (Works Orders valued up to £300k) covering the following areas:
IMUF 1 - Greater Belfast;
IMUF 2 - Coleraine, Omagh and Fermanagh;
IMUF 3 - Armagh and Lisburn.
Please note: For this procurement, Suppliers submissions are required to be uploaded via the eTendersNI CfT under Lot 1: IMUF 1 (Greater Belfast Area). This will serve as the central submission point for all Lots. Suppliers should submit their responses for every Lot they are tendering for within this single location.
- The authority expects to re-tender this requirement around 20 Nov 2030, 23:59 GMT.
- No preliminary market engagement: **Preliminary market engagement notice was published** The Authority has previously conducted a preliminary market engagement online information session on Friday 12 June for this Procurement. Details of this can be found at: https://www.infrastructure-ni.gov.uk/articles/dfi-tram-preliminary-market-engagement IMUF - UK2 Notice https://www.infrastructure-ni.gov.uk/articles/dfi-tram-preliminary-market-engagement Notice identifier: 2026/S 000-051370 Procurement identifier (OCID): ocds-h6vhtk-06a8e2 Published 29 May 2026, 1:19pm
CPV: Construction work for dams, canals, irrigation channels and aqueducts · Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork · Construction work for railways and cable transport systems · Construction work for waterways · Drainage works · Flood-defences maintenance works · River regulation and flood control works · Sewer survey services · Storm-water piping construction work · Works for complete or part construction and civil engineering work
More open work like this
Other notices open now · live search, filters set
How this framework works
From the published notice- Type
- Closed framework
- Call-offs
- every call-off is a further competition among the appointed suppliers
- Framework period
- 4 yrs from 19 Apr 2027
Published description of the framework
Three Measured Term Contracts (MTCs) covering three Contract Areas (Lots 1-3) will be awarded upon execution of the Framework. A Primary Supplier and Reserve Supplier will be appointed for each MTC Lot, as a result of the evaluation of the Framework tender submissions. The Primary Supplier will be required to carry out any such Works instructed by a Works Order, issued under the provisions of the MTC Call-Off Contract. The Call-Off Procedure for MTCs is set out in Volume 2 - Framework Information of the Framework contract documents.
All Suppliers that submit a valid tender for any MTC Lot and meet the minimum assessment requirements will be appointed onto the Framework.
Lots and requirements (3)Procurement structure
3 lots · all with a published value · same conditions of participation on every lotLot #1IMUF1 - Greater Belfast AreaPublished value£3,250,000
ICC Measured Term Contract for works within the Greater Belfast Area (Works Orders valued up to £300k).
The proposed contract relates to works with a cumulative value of £2.6m (ex VAT) over a four year term. If the Contracting Authority is unable, for any reason, to award a new framework or to put in place an alternative regime to replace this Framework on its termination or expiry, any Call-Off Contract established under this Framework may be extended for a further period or periods up to a maximum of 12 additional months. This may increase the value to £3.25m (ex VAT).
- Economic & financial standing
As per Tender documentation – Refer to IFT Part B and TSP-1
- Technical & professional ability
As per Tender Documentation - Refer to TSP-2
Lot #2IMUF3 - Armagh & Lisburn AreasPublished value£1,950,000
ICC Measured Term Contract for works within the Armagh and Lisburn Areas (Works Orders valued up to £300k).
The proposed contract relates to works with a cumulative value of £1.56m (ex VAT) over a four year term. If the Contracting Authority is unable, for any reason, to award a new framework or to put in place an alternative regime to replace this Framework on its termination or expiry, any Call-Off Contract established under this Framework may be extended for a further period or periods up to a maximum of 12 additional months. This may increase the value to £1.95m (ex VAT).
- Economic & financial standing
As per Tender documentation – Refer to IFT Part B and TSP-1
- Technical & professional ability
As per Tender Documentation - Refer to TSP-2
Lot #3IMUF2 - Coleraine, Omagh and Fermanagh AreasPublished value£1,500,000
ICC Measured Term Contract for works within the Coleraine, Omagh and Fermanagh Areas (Works Orders valued up to £300k).
The proposed contract relates to works with a cumulative value of £1.5m (ex VAT) over a four year term. If the Contracting Authority is unable, for any reason, to award a new framework or to put in place an alternative regime to replace this Framework on its termination or expiry, any Call-Off Contract established under this Framework may be extended for a further period or periods up to a maximum of 12 additional months. This may increase the value to £1.5m (ex VAT).
- Economic & financial standing
As per Tender documentation – Refer to IFT Part B and TSP-1
- Technical & professional ability
As per Tender Documentation - Refer to TSP-2
What it takes to wini
Evaluation split and conditions of participation as published; the tender pack may add morei
- Economic & financial standing
As per Tender documentation – Refer to IFT Part B and TSP-1
- Technical & professional ability
As per Tender Documentation - Refer to TSP-2
- “DfI Rivers Directorate T-1163 Inspection and Maintenance of…” is a framework: the contest is a place on its panel, not a single contract: each call-off is a further competition, so the pricing contest starts after appointment.
Competition analysis · published record, not a forecast of who will bid
How DfI Transport and Road Asset Management (TRAM) buys Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork (CPV 4523), and who usually turns up
DfI Transport and Road Asset Management (TRAM)’s published record next to the market for the same work. Compared with other frameworks and DPS only. Whole-market view: Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork (CPV 4523) →
How the contest usually goes
Winner shares use published awards; bid and price charts use contested lots.
i
The counts under this question show how many awards have a known supplier size.
Small firms have won here. Neither number says whether you qualify; it describes who has been winning.
i
Local means the winner is registered in the region where that award was delivered.
Most of this buyer’s recorded winners were registered in the region where that award was delivered.
i
Half of these awards have an award date within 73 days of the bid deadline.
i
Both shares are minimums: some awards have no bid count.
Missing bid counts may hide more single-bid awards. This share is a minimum.
How many bids did past lots attract?
i
1 bid9% / 0%
2–314% / 20%
4–677% / 80%
7+0% / 0%
How did awards compare with estimates?
i
On a framework or DPS, prices are agreed when work is called off.
Not comparable on a framework or DPS: the price is set later, on each call-off.
Assess each lot i
i
Open a lot for its forecast, this buyer’s previous supplier and possible competitors, from published award history, not a bid list
Lot #1IMUF1 - Greater Belfast AreaCPV 4523Published estimate£3.3m
i
Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative. The bar shows 10 past lots.
1 bid0%
2–320%
4–680%
7+0%
i
No comparable awards for this lot yet.
Who has supplied this buyer on similar work? i
i
No earlier contract of this buyer matches this lot on the published record.
Who could compete for this lot? i
i
Candidate suppliers for this notice have not been worked out yet, so this is not a verdict that nobody fits.
Lot #2IMUF3 - Armagh & Lisburn AreasCPV 4523Published estimate£1.9m
i
Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative. The bar shows 10 past lots.
1 bid0%
2–320%
4–680%
7+0%
i
No comparable awards for this lot yet.
Who has supplied this buyer on similar work? i
i
No earlier contract of this buyer matches this lot on the published record.
Who could compete for this lot? i
i
Candidate suppliers for this notice have not been worked out yet, so this is not a verdict that nobody fits.
Lot #3IMUF2 - Coleraine, Omagh and Fermanagh AreasCPV 4523Published estimate£1.5m
i
Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative. The bar shows 10 past lots.
1 bid0%
2–320%
4–680%
7+0%
i
No comparable awards for this lot yet.
Who has supplied this buyer on similar work? i
i
No earlier contract of this buyer matches this lot on the published record.
Who could compete for this lot? i
i
Candidate suppliers for this notice have not been worked out yet, so this is not a verdict that nobody fits.
About this data
- Estimates, labelled. The price range, possible competitors and earlier-work matches are our estimates from past awards, not published facts, win chances or price advice. The buyer’s own record and the wider market are shown apart, never mixed.
- Source. Official UK public procurement notices (Find a Tender and Contracts Finder), reused under the Open Government Licence v3.0, updated through the day and rebuilt nightly. Not every figure uses both feeds, and each one shows how many records it rests on: see the methodology. Spotted something wrong? Tell us.
Procedure terms & legal framework
From the official record- Procedure method
- Open procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Open for tender
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Yes · next expected 20 Nov 2030
- First published
- 20 Nov 2026, 16:50 GMT
- Last source update
- 20 Nov 2026, 16:50 GMT
- Award evaluation window
- Submission end – 17 Feb 2027
- Authority reference
T-1163- FTS notice number
2026/S 000-110338- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-07c0c7Find a Tender- Contract terms summary
For further details on invoicing procedures please see : www.financeni.gov.uk/articles/account-ni-… ↗
- Risks
The Authority has identified the following risks as risks that satisfy the criteria of Schedule 8
sub-paragraph (6 (a) of the Procurement Act 2023 i.e. that the risk/s could jeopardise the
satisfactory performance of the contract but, because of their nature, cannot be addressed in the contract as awarded:
- (a) Extreme Adverse Weather Impacts and Climate Change: Extreme weather events (in particular, high winds, tidal surges and heavy rainfall) may impact service delivery. Increased extreme weather events and storm frequency may require future adaptation of the works carried out under this Framework. Such events may result in significant localised impacts within geographical location, e.g. specific Contract Areas, requiring changes to the scale or emphasis of contracted works.
(b) Regulatory and Policy Changes: The Authority is engaged in developing policy in relation to Net Zero. The introduction of this policy and any potential new obligations in relation to environmental regulations may require adjustments to the scope of works provided under this Framework. The Framework and Call-Offs may be required to align with the Authority's future net zero and sustainability strategies. Changes to national or local carbon reduction targets may require modifications to materials, methods, or delivery schedules.
(c) Changes to legislation, regulation or industry guidance: During the contract period, including revisions or replacements of relevant guidance e.g. Ciria 786. The nature and impact cannot be reasonably determined at this stage.
(d) Uncertainty in Underground Infrastructure asset condition and data accuracy: The extent and condition of underground infrastructure may not be fully known until inspection or excavation activities are undertaken.
AND
- Has concluded that there is a possibility that the contract may have to be modified as a result of a materialisation of the known risk/s at a later date in accordance with Schedule 8 paragraph 5 of the Procurement Act 2023.
How to participate & submission route
Official notice Submit via eTendersNI- Requests to participate (first stage)
- —
- Appointment period ends
- 18 Dec 2026, 23:59 GMT
- Clarification deadline
- 18 Dec 2026, 23:59 GMT
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
- Accepted languages
- en
Tenders must be submitted electronically via the relevant Call for Tender (CfT) opportunity on eTendersNI, website details immediately below.
Paper submissions will not be accepted or considered and will be rejected by the Contracting Authority.
The tender documents are available with unrestricted and full direct access, free of charge, at: ULR etendersni.gov.uk/epps ↗
For this procurement, all Supplier Technical and Financial submissions must be uploaded exclusively via Lot 1 (IMUF1 – Greater Belfast Area) on the eTendersNI platform. Lot 1 will serve as the single, centralised submission point for all Lots within the Framework. Accordingly, Suppliers must select Lot 1 on eTendersNI (in addition to all other Lots they are tendering for) regardless of whether they are submitting a tender for Lot 1 itself.
Timeline
20 Nov 2026 → 19 Apr 2027 · 5 dates- Tender notice published3h ago20 Nov 2026, 16:50 GMT
- Today20 Nov 2026
- Clarification questions byin 28 days18 Dec 2026, 23:59 GMT
- Admission / appointment period endsin 28 days · period end, not a bid countdown18 Dec 2026, 23:59 GMT
- Award decision expected byin 89 days17 Feb 2027, 23:59 GMT
- Contract startsin 149 days19 Apr 2027, 00:00 BST
Notice history
1 event · 1 release on Find a Tender- Tender notice published20 Nov 2026, 16:50 GMTUK4
Commercial outcome & contract awards
Nothing awarded yet- Awards (0)
- No award published
- Contracts (0)
- No contract published
- Bid statistics
- No aggregate bid statistics published
Contracting authority & participating public bodies
Official documents & specifications (1)
Official links; attachments are not copiedNotices published for this procedure
- Tender notice Tender notice on Find a Tender