Official UK procurement notice
“DESIGN & BUILD OF 31 NO UNITS AT HOLM VIEW PHASE 2, BARRY”
Authority: Vale of Glamorgan Council (Central government)
What is being bought
Published requirement description“DESIGN & BUILD OF 31 NO UNITS TOGETHER WITH ALL ASSOCIATED EXTERNAL WORKS, DRAINAGE AND MAINS SERVICE CONNECTIONS AT HOLM VIEW PHASE 2, BARRY”
CPV: Construction work
The lotProcurement structure
single lot · no lot value publishedLot #1
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
- Suitability
Please see tender documents in both notices (1 of 2 and 2 of 2)
Procedure terms & legal framework
From the official record · publisher note attached- Procedure method
- Open procedure
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Works
- Notice status
- Closed
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- No (one-off requirement)
- First published
- 17 Oct 2022, 15:46 BST
- Last source update
- 27 Oct 2022, 12:36 BST
- Award evaluation window
- 12 Dec 2022 – …
- FTS notice number
2022/S 000-030324- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-037666Find a Tender
Publisher note: Please refer to Holm View Phase 2 Design and Build 1 of 2 for the main tender documents. This notice has been raised due to the volume of documents which must be issued for the tender. This notice will only have the ER documents attached. All other tender documents are uploaded onto the notice 1 of 2 All Questions must be raised through Notice 1 of 2 and all tenders must be submitted through 1 of 2. Following formal award of contract, the lead in time is to be considered by the main Contractor but it is estimated that 8 weeks will be necessary to allow for S104 Approval, S38/278 Approval and equivalent pre-commencement conditions. There is a specific stipulation in respect of methodology/type of building and the contractor must state his preference as part of his tender submission. It is estimated that the term of the build contract will be 14-16 months, but the Contractor is requested to confirm this as part of his tender return. Indicative programmes are not required at this time. The Council will require a demonstration of the commitment to Targeted Training and Recruitment and the Value Wales Toolkit and the Contractor is required to fulfil these requirements as part of the contract NOTE: To register your interest in this notice and obtain any additional information please visit the Sell2Wales Web Site at https://www.sell2wales.gov.wales/Search/Search_Switch.aspx?ID=125664. The Contractor shall ensure that all contracts with Subcontractors and Suppliers which the Contractor intends to procure following the Award date, and which the Contractor has not, before the date of this Contract, already planned to award to a particular Subcontractor or Supplier, are advertised through the Sell2Wales portal (www.sell2wales.gov.wales) and awarded following a fair, open, transparent and competitive process proportionate to the nature and value of the contract. Under the terms of this contract the successful supplier(s) will be required to deliver Community Benefits in support of the authority’s economic and social objectives. Accordingly, contract performance conditions may relate in particular to social and environmental considerations. The Community Benefits included in this contract are: Please see tender documents on both 1 of 2 and 2 of 2 (WA Ref:125664)
How it was run
Official noticeTender documents are also served through a separate tool: https://www.sell2wales.gov.wales ↗
- Submission deadline
- 19 Dec 2022, 12:00 GMT
- Submission channel
- {"electronicSubmission"}
- Accepted languages
- en
- Bid validity
- 90 days from the deadline
- Bids opened
- 12 Dec 2022, 12:00 GMT
Timeline
27 Oct 2022 → 19 Dec 2022 · 3 dates- Notice published27 Oct 2022, 12:36 BST
- Bids opened12 Dec 2022, 12:00 GMT
- Submission deadline19 Dec 2022, 12:00 GMT
Notice history
1 event · 2 releases on Find a Tender- Deadline moved to 19 Dec 2022, 12:00 GMT27 Oct 2022, 12:36 BST+7 days · was 12 Dec 2022, 12:00 GMT
Published amendments (1 · 1 deadline change)
| When | What | Before | After | Shift |
|---|---|---|---|---|
| — | DeadlineTime limit · IV.2.2 | 12 Dec 2022 | 19 Dec 2022 | +7 d |
| — | Bid openingConditions for opening of tenders · IV.2.7 | 12 Dec 2022 | 19 Dec 2022 | +7 d |
Deadline request extension agreed by the Council
Contracting authority & participating public bodies
Dispute resolution & review bodies
- High CourtReview body
Official documents & specifications (2)
Official links; attachments are not copiedTender pack and attachments
- Economic and financial selection criteria
- Technical selection criteria