Cambridgeshire County Council Highway Services Contract 2017
Construction work for bridges
Construction work for highways
Construction
+19 more
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Cambridgeshire County Council: "Cambridgeshire County Council Highway Services Contract 2017". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Cambridgeshire County Council | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Cambridgeshire County Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Cambridgeshire County Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
8Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 35 active published awards; 34 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityCambridgeshire County Council | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published24 Feb 2021, 15:00 GMT | Last source update24 Feb 2021, 15:00 GMT | Recurring procurementNot published |
ClassificationConstruction work for bridges, Construction work for highways, Construction, foundation and surface works for highways, roads, Fleet management, repair and maintenance services, Gully cleaning and emptying services, Highway maintenance work, Highways consultancy services, Highways engineering services, Horticultural services, Repair and maintenance services of building installations, Repair, maintenance and associated services related to roads and other equipment, Roadworks, Safety training services, Support services for road transport, Technical testing, analysis and consultancy services, Verge maintenance work, Winter-maintenance vehicles | ||
Delivery area | ||
OCIDocds-h6vhtk-0295de | ||
What is being bought
The contract is for the contractor to develop with the Council a high-performing, comprehensive highways service. The contract encompasses highway maintenance, design, construction, transport planning, consultancy with other services including but not limited to vehicle and grounds maintenance.
- Following publication of an OJEU contract notice 2015/S 208-376868 dated 22 October 2015 and use of the competitive dialogue in 2015-2017, Cambridgeshire County Council established a single contract with Skanska Construction UK Limited (“Skanska”) providing both works and consultancy as a fully integrated highway service commencing on 1.7.2017. The contract period is for 10 years with possible extensions at the Council’s discretion to a maximum of 15 years.
- Skanska has contracted to sell its highways maintenance business to Milestone Infrastructure Limited (“Milestone”). The sale will proceed as an asset sale and will include plant and equipment required to operate the highways maintenance business of Skanska, the transfer of leases or rights to use properties and facilities currently used by the highways maintenance business, and the transfer of approximately 1,487 employees. It will also include the transfer of customer contracts, including this contract with the Council.
- The contract between the Council and Skanska permits novation by Skanska of the contract with the consent of the Council. Skanska has requested consent to novate to Milestone and the Council intends to consent to such novation subject to a decision of the Highways and Transport Committee on 9 March 2021. Entry into such deed of novation to reflect the change in circumstances will not take place earlier than 18 days after the publication of this notice
What changed
From the official release history
- Status changed to complete
24 Feb 2021, 15:00 GMT - Official notice release published
24 Feb 2021, 15:00 GMT - Buyer information updated
24 Feb 2021, 15:00 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedStatus not publishedPublished valueNot publishedCambridgeshire County Council sought to establish a single contract providing both works and consultancy as a fully integrated highways service. It advertised for a business and delivery partner to fulfil these requirements in OJEU contract notice 2015/S 208-376868. The contract notice advertised an opportunity to enter into a single contract and the procurement was carried out using the competitive dialogue. The contract was advertised as being available to be used by other contracting authorities, the details of which were specified in the notice. On 17th July 2017, Cambridgeshire County Council entered into the advertised contract with Skanska Construction UK Limited. This arrangement continued until Skanska Construction UK Limited was acquired by Milestone Infrastructure Limited. Cambridgeshire County Council is proposing to enter into a deed of novation together with Skanska Construction UK Limited and Milestone Infrastructure Limited in order to reflect the change in circumstances. As such, a novation will not be a substantive change and is permitted by Regulation 72(1)(d)(ii) of the Public Contracts Regulations 2015 (Regulations). Cambridgeshire County Council therefore considers that prior publication of a contract notice is not required by Part 2 of the Regulations and have therefore not issued an OJEU contract notice in respect of such novation.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
24 Feb 2021, 15:00 GMT - Award active
Not published · Not published - Contract active
Signed 16 Feb 2021, 00:00 GMT · Not published
Commercial outcome and competition
Awards Milestone Infrastructure Ltd Not published · Not published · active |
Contracts Contract Not published · signed 16 Feb 2021, 00:00 GMT · active |
Bid statistics highestValidBidValue: 900000000 lowestValidBidValue: 600000000 highestValidBidValue: 900000000 (lot 1) lowestValidBidValue: 600000000 (lot 1) |
Buyer and organisations in this procedure
Cambridgeshire County Council
Contracting authority GB-FTS-1059Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleThe Council sought to establish a single contract providing both works and consultancy as a fully integrated highways service. It advertised for a business and delivery partner to fulfil these requirements in OJEU contract notice 2015/S 208-376868. This contract notice advertised an opportunity to enter into a single contract and the procurement was carried out using the competitive dialogue. The contract was advertised as being available to be used by other contracting authorities, the details of which were specified in the notice.
On 17th July 2017, the Council entered into the advertised contract with Skanska. This arrangement continued until Skanska's infrastructure services business was acquired by Milestone. The Council is proposing to enter into a deed of novation together with Skanska and Milestone in order to reflect the change in circumstances subject to a decision of the Highways and Transport Committee on 9 March 2021. As such, a novation will not be a substantive change and is permitted by Regulation 72(1)(d)(ii) of the Public Contracts Regulations 2015 ("Regulations"). The Council therefore considers that prior publication of a contract notice is not required by Part 2 of the Regulations and have therefore not issued an OJEU contract notice in respect of such novation. |