AOC - Continuation of Professional Services for the LUF Programme.
Quantity surveying services for civil engineering works
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Melton Borough Council: "AOC - Continuation of Professional Services for the LUF Programme.". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Melton Borough Council | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Melton Borough Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Melton Borough Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
1.3Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 4 active published awards; 4 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityMelton Borough Council | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published6 Mar 2025, 15:17 GMT | Last source update6 Mar 2025, 15:17 GMT | Recurring procurementNot published |
ClassificationQuantity surveying services for civil engineering works | ||
Delivery area | ||
OCIDocds-h6vhtk-04ea2b | ||
What is being bought
TSA Riley has been supporting the Council to deliver the Stockyard Redevelopment Project, which is funded by the Levelling up Fund, through the design phases up to RIBA Stage 4. Specifically, the services of Quantity Surveying, Contract Administration and Employers Agent providing a wide range of support that can be called upon as and when needed to support the delivery of the programme.
Melton Borough Council sought to utilise a direct award through the ESPO Consultancy Services Framework to procure TSA Riley to continue the services of TSA Riley for RIBA Stage 5, the construction phase and RIBA Stage 6, the defects liability period of the project.
What changed
From the official release history
- Status changed to complete
6 Mar 2025, 15:17 GMT - Official notice release published
6 Mar 2025, 15:17 GMT - Buyer information updated
6 Mar 2025, 15:17 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedTSA Riley has been supporting the Council to deliver the Stockyard Redevelopment Project, which is funded by the Levelling up Fund, through the design phases up to RIBA Stage 4. Specifically, the services of Quantity Surveying, Contract Administration and Employers Agent providing a wide range of support that can be called upon as and when needed to support the delivery of the programme. Melton Borough Council sought to utilise a direct award through the ESPO Consultancy Services Framework to procure TSA Riley to continue the services of TSA Riley for RIBA Stage 5, the construction phase and RIBA Stage 6, the defects liability period of the project.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
6 Mar 2025, 15:17 GMT - Award active
Not published · Not published - Contract active
Signed 15 Jan 2025, 00:00 GMT · £113,959
Commercial outcome and competition
Awards TSA Riley Not published · Not published · active |
Contracts Contract £113,959 · signed 15 Jan 2025, 00:00 GMT · active |
Bid statistics bids: 1 (lot 1) |
Buyer and organisations in this procedure
Melton Borough Council
Contracting authority GB-FTS-140051Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleTSA Riley's contract is due to come to an end at the end of RIBA Stage 4 and it would be detrimental to the programme to lose the knowledge and experience that the existing consultants have developed in relation to the Stockyard project since the start of the programme.
The council does not currently have the existing expertise internally to provide the above services that would enable it to manage this programme effectively and so it is reasoned the most cost-effective way forward is to retain the services of TSA Riley for RIBA Stage 5, the construction phase and RIBA Stage 6, the defects liability period of the project.
The current decision notice CEX409 was approved to the end of RIBA Stage 4 at a cost of £79,092 and has been taken from the Stockyard project management allowance secured from the LUF programme. It is expected that retaining the services of TSA Riley through RIBA Stages 5 and 6 will cost an additional £113,959 and will also be taken from the Stockyard project management allowance secured from the LUF programme.
If approved the Council will be able to continue progressing the project through to the construction phase in spring 2025. |