Published requirement descriptionWe propose to evaluate the possible infrastructure solutions at Allerton TCC for feasibility and option selection assessments as per the outline scope below:
- To evaluate and define optimal solutions for bogie drop, transfer, and storage facilities, as well as jacking systems and a potential shed extension, to support heavy maintenance operations for 3-car and 4-car Class 331 units, with future-proofing considerations.
- 3 car HM cycle is due March 2028 and the 4 car units will commence Jan 2029 this report will determine if there is potential for a phased approach to enable 3 car maintenance to be undertaken with 4 car requirements being constructed at a later stage, and if it should be foreseeable that its possible undertake 3 car maintenance cycle, whilst being able to complete the required construction works for 4 car unit facilities.
- The additional requirements for 4 car units to be maintained would be additional jacking equipment, shed extension to road 4 / 5 shed, foundations/pits and storage for the additional 4-wheel sets (2 old & 2 new)
This feasibility and option selection project will identify the optimum solution to each issue. The solution must be deliverable, operationally efficient, represent value for money and meet NTL strategic objectives.
The Selected option for each proposed scheme will form the work scope for the design phase. Completing this feasibility and option selection will allow the proposed schemes to commence at design stage, improving project delivery efficiency.
CPV: Designs · Feasibility study
The lotProcurement structure
single lot · no lot value publishedPipeline intelligence · planning stage: how this market runs before the tender is published
How Northern Trains Ltd buys Postcards (CPV 2231), and who usually turns up
Northern Trains Ltd’s published record next to the market for the same work. Frameworks and DPS are left out: they draw different bid counts. Whole-market view: Postcards (CPV 2231) →
How the contest usually goes
Winner shares use published awards; bid and price charts use contested lots.
i
How often small and medium firms win.
Share of awards where the winner’s size is known.
The counts under this question show how many awards have a known supplier size.
Small firms have won here. Neither number says whether you qualify; it describes who has been winning.
i
How often local firms win similar work.
Winners with a registered address in the delivery region, out of awards with a known address.
Local means the winner is registered in the region where that award was delivered. The market figure counts awards delivered in North West England.
A local branch does not count if the registered address is elsewhere.
Most of this buyer’s recorded winners were registered outside the region where that award was delivered.
i
How long buyers here take to decide after bids close.
Middle value in days from the bid deadline to the award date, on competitions that published both.
Only decided tenders count, so slow ones still waiting are not in.
Half of these awards have an award date within 42 days of the bid deadline.
i
How often work is awarded with no recorded rival.
Direct awards and tenders where every published lot count shows one bid.
Both shares are minimums: some awards have no bid count.
Thin markets produce this too; it is not proof of a tailored specification.
Direct awards or one recorded bid are common here. Check the route before spending time on a bid.
How many bids did past lots attract?
i
How many bids past lots received.
Each colour is a bid-count range. Only competed lots with a published count are included.
Past bids do not predict this tender.
1 bid0% / 7%
2–320% / 34%
4–640% / 27%
7+40% / 32%
How did awards compare with estimates?
i
Where winning prices landed against estimates.
Each colour shows awards below, close to or above the published estimate, one lot at a time.
Past prices are a guide, not a bid price.
Below estimate50% / 44%
Within ±2%25% / 48%
Above estimate25% / 8%
Assess each lot i
What past awards tell you about each lot.
See the forecast, this buyer’s earlier suppliers and firms with relevant wins.
No supplier is confirmed as a bidder.
i
What past awards tell you about each lot.
See the forecast, this buyer’s earlier suppliers and firms with relevant wins.
No supplier is confirmed as a bidder.
Open a lot for its forecast, this buyer’s previous supplier and possible competitors, from published award history, not a bid list
Lot #1CPV 2231Published estimate£334k
i
How many bids this lot may attract.
The forecast uses similar past competitions. The bar shows either that forecast or past bid counts; the line below says which.
Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative. The bar shows 44 past lots.
A forecast, not a list of bidders.
1 bid7%
2–334%
4–627%
7+32%
i
Where the award price may land.
The forecast uses similar awards and the buyer’s estimate. The band covers the middle half of likely prices.
No comparable awards for this lot yet.
A statistical guide from past awards, not a price to bid.
Who has supplied this buyer on similar work? i
Who has done similar work for this buyer.
Past contracts are matched by buyer, title and type of work.
A past supplier may not bid again.
i
Who has done similar work for this buyer.
Past contracts are matched by buyer, title and type of work.
A past supplier may not bid again.
No earlier contract of this buyer matches this lot on the published record.
Who could compete for this lot? i
Who could compete for this lot?
Firms with relevant past wins. On a framework, we show firms on that agreement.
None is confirmed as a bidder.
i
Who could compete for this lot?
Firms with relevant past wins. On a framework, we show firms on that agreement.
None is confirmed as a bidder.
Candidate suppliers for this notice have not been worked out yet, so this is not a verdict that nobody fits.
About this data
- Source. Official UK public procurement notices (Find a Tender), reused under the Open Government Licence v3.0. New notices arrive through the day; the figures are rebuilt nightly.
- Two views, kept apart. The authority’s own track record and the wider market for the same kind of work sit side by side and are never mixed. Where the local picture is too thin, a figure widens to a broader market and says which one it used.
- Forecasts are labelled. The price forecast and its range, possible competitors and the earlier-work matches are our estimates from past awards: not published facts, not win chances and not price advice. Official notices do not say who is bidding.
- Every figure shows what it rests on. Not every notice publishes a bid count, a value or a delivery region, so each figure carries the number of records behind it, and one built on few records is marked as such. The on a figure explains it; the counting rules are in the methodology. Spotted something wrong? Tell us.
Procedure terms & legal framework
From the official record- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Services
- Notice status
- Planned procurement
- Procurement threshold
- Below threshold
- Regulatory regime
- Utilities
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 26 Jan 2026, 11:30 GMT
- Last source update
- 26 Jan 2026, 11:30 GMT
- FTS notice number
2026/S 000-006548- Latest notice
- Preliminary market engagement notice (UK2)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-060e3dFind a Tender
How it was run
Official notice- Submission deadline
- —
Timeline
26 Jan 2026 → 9 Jun 2026 · 4 dates- Planning notice published270 days ago26 Jan 2026, 11:30 GMT
- Market engagement252 days ago12 Feb 2026, 23:59 GMT
A workshop will take place via teams on 12th February 2026 at 10:30am to engage with suppliers on the upcoming Allerton TCC 331 Heavy maintenance Feasibility scheduled to release on 2nd March 2026.
This workshop will give suppliers a brief overview of the scope, the timelines of the tender, contract and how long the project is expected to run for.
If you would like to attend the session please email the Project Manager and Procurement Manager and the Teams invite will be sent across to you.
Please email: [email protected] & [email protected]
- Tender notice expected234 days ago2 Mar 2026, 23:59 GMT
- Contract starts136 days ago9 Jun 2026, 00:00 BST
Notice history
1 event · 1 release on Find a Tender- Preliminary market engagement notice published26 Jan 2026, 11:30 GMTUK2
Commercial outcome & contract awards
Pipeline notice- Awards (0)
- No award published
- Contracts (0)
- No contract published
- Bid statistics
- No aggregate bid statistics published
Contracting authority & participating public bodies
Official documents & specifications (1)
Official links; attachments are not copiedNotices published for this procedure
- Preliminary market engagement notice Preliminary market engagement notice on Find a Tender