Tylorstown Landslip Remediation Phase 4

Excavating and earthmoving work
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Rhondda Cynon Taf CBC: "Tylorstown Landslip Remediation Phase 4". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
Contracting AuthorityRhondda Cynon Taf CBCScope & CategoriesNot publishedSubmission Window
complete
No deadline published
Submission GatewayDirect notice routeLegal Basis & RegimeStandard procurementEstimated Value (exc. VAT)Not published
Bidder Intelligence · Authority Profile: Rhondda Cynon Taf CBC
Market Analytics
View Authority Profile →
Derived from OCDS awards & bid statistics
Published history for Rhondda Cynon Taf CBC. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Requires at least 5 comparable procedures
Competition Density
4Bids / Report
14.5% of reports have one bid
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate available
Payment Terms
Check noticePublished terms
Payment obligations depend on the applicable regime and contract. Consult the official documents.
Coverage: 55 active published awards; 55 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityRhondda Cynon Taf CBC
Procedure methodNot published
Procurement categoryNot published
Statuscomplete
Framework / DPSNot published
CompetitionNot published
Above thresholdNot published
Legal basisNot published
Tender period startsNot published
Clarification deadlineNot published
Electronic submissionNot published
Submission languagesNot published
Published21 Dec 2022, 12:01 GMT
Last source update21 Dec 2022, 12:01 GMT
Recurring procurementNot published
ClassificationExcavating and earthmoving work
Delivery area
OCIDocds-h6vhtk-039343
What is being bought
On Sunday 16th February 2020, Storm Dennis caused the Llanwonno Upper Tip to fail above the village of Tylorstown. Approximately 60,000m³ of material slipped down the valley, filling the valley bottom and diverting the course of the Afon Rhondda Fach. Emergency works (referred to as Phases 1, 2 and 3 of the Tylorstown Landslip scheme) have been undertaken to remove the slipped material from the river and valley bottom. Rhondda Cynon Taf County Borough Council is now proposing essential stabilisation and remediation works to ensure the colliery material within the Llanwonno Upper Tip is made safe, preventing future landslips such as the one that occurred in February 2020 and demonstrating that the relocated and remaining in-situ material can be regenerated for a beneficial end-use. To achieve this, the majority of the colliery material at Llanwonno Upper Tip will be excavated and transported along a haul road to a new location, referred to as the ‘Receptor Site’, next to Old Smokey.
What changed
From the official release history
  1. Status changed to complete
    21 Dec 2022, 12:01 GMT
  2. Official notice release published
    21 Dec 2022, 12:01 GMT
  3. Buyer information updated
    21 Dec 2022, 12:01 GMT
Lots and requirements (1)
Published by the contracting authority
  • Lot 1 · #1
    Individual lot title not published
    cancelled
    Published valueNot published
    The proposed scheme will involve moving colliery material from the Llanwonno Upper Tip (donor site) to a new receptor site adjacent to Tylorstown Tip, otherwise known as Old Smokey tip. It will also provide for stabilisation and remediation works to the Llanwonno Upper Tip site and remaining material. The overall site area totals circa 31 Ha and the main elements of the application contained within it are as follows: Removal of material remaining within Llanwonno Upper Tip on the top of the hillside, amended drainage arrangements and landscaping of the area following the removal to stabillise the tip; Reprofiling of the upper tip is to be undertaken utilising the in-situ landscape material (i.e. smoothing out the current landslip “bowl” to the proposed levels, with no interim storage of material needed), plus associated drainage and landscaping works; Transportation of the material to be deposited on the nearby receptor site; Profiling, drainage and landscaping of the receptor site.
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
Timeline
  1. Procedure published
    21 Dec 2022, 12:01 GMT
  2. Award active
    Not published · Not published
  3. Contract active
    Signed 18 Oct 2022, 00:00 BST · £5,300,000
Commercial outcome and competition
Awards
TOM PRICHARD HOLDINGS LTD
Not published · Not published · active
Contracts
Contract
£5,300,000 · signed 18 Oct 2022, 00:00 BST · active
Bid statistics
bids: 4 (lot 1)
electronicBids: 4 (lot 1)
foreignBidsFromEU: 4 (lot 1)
foreignBidsFromNonEU: 0 (lot 1)
smeBids: 1 (lot 1)
Buyer and organisations in this procedure

Rhondda Cynon Taf CBC

Contracting authority GB-FTS-1554
View buyer profile
  • Rhondda Cynon Taf CBC
    buyer

    The Pavilions, Clydach Vale, Tonypandy, UKL15, CF40 2XX
    +44 1443
  • High Court
    reviewBody

    Royal Courts of Justice, The Strand, London, WC2A 2LL
    +44 2079477501
  • TOM PRICHARD HOLDINGS LTD
    supplier

    TOM PRICHARD HOLDINGS LTD, Earthmovers House Unit 16 Llantrisant Business Park, PONTYCLUN, UKL, CF728LF
Documents (0)
Official links; attachments are not copied
No data
No linked documents are published
Related procedures (0)
No data
No related procedures published