Find a Tender
active
Official procurement procedure
Strategic Assets Framework Agreement
Technical inspection services of engineering structures
Published value
Not published
Submission deadline 28 Jan 2022, 12:00 GMT
Lots published4
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: West Midlands Combined Authority: "Strategic Assets Framework Agreement". Published status: active. Published value: Value not published. 4 published lots. Recorded submission deadline: 28 Jan 2022, 12:00 GMT. See the official notice for participation instructions.
| Contracting Authority | West Midlands Combined Authority | Scope & Categories | Not published | Submission Window | Closed 28 Jan 2022, 12:00 GMT |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: West Midlands Combined Authority
Market Analytics
Derived from OCDS awards & bid statistics
Published history for West Midlands Combined Authority. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
5.8Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 109 active published awards; 103 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityWest Midlands Combined Authority | Procedure methodNot published | Procurement categoryNot published |
Statusactive | Framework / DPSFramework | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published23 Dec 2021, 22:45 GMT | Last source update23 Dec 2021, 22:45 GMT | Recurring procurementNo |
ClassificationTechnical inspection services of engineering structures | ||
Delivery area | ||
OCIDocds-h6vhtk-029a96 | ||
What is being bought
The Strategic Asset Management team are responsible for all of the asset information for all of the different asset groupings that exist within the portfolio of the West Midlands Combined Authority (WMCA).
Due to various existing arrangements coming to an end and new services required the WMCA requires a new framework consisting of the following Lots:
• Lot 1 – BIM
• Lot 2 – Inspections
• Lot 3 – Small Works
• Lot 4 - Structures
What changed
From the official release history
- Official notice release published
23 Dec 2021, 22:45 GMT - Submission deadline changed to 28 Jan 2022, 12:00 GMT
23 Dec 2021, 22:45 GMT - Status changed to active
10 Mar 2021, 22:56 GMT - Official notice release published
10 Mar 2021, 22:56 GMT - Submission deadline changed to 12 Apr 2021, 12:00 BST
10 Mar 2021, 22:56 GMT - Buyer information updated
10 Mar 2021, 22:56 GMT
Lots and requirements (4)
Published by the contracting authority
- Lot 1 · #1 - BIMIndividual lot title not publishedactivePublished valueNot publishedThis Framework Agreement will enable WMCA to source independent BIM advice including but not limited to: • Ensuring Paperwork is up to date to meet any new standards such as ISO19650. Including data drops, CDE’s and relevant file formats • Advise on BIM Execution Plans (BEP’s) for both quality and validity ensuring to mitigate any and all risk to the WMCA as far as Practicably possible. • Attend meetings where necessary with external parties to protect the interest of WMCA. • Assist with the promotion of the BIM process through internal meetings with stakeholders and project managers to ensure up take by providing case studies from similar projects or your own experience. • Teaching the necessary skills to the organisation to be self-sufficient and allow for the smooth running of the day to day process. Additional information: The WMCA is looking to establish a six years maximum term Framework Agreement with one supplier for Lot 1 to ensure consistency over that period. A longer-term framework is required due to the extended timescales within Lot 4 to meet the WMCA's cyclical inspection programme.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
- Lot 2 · #2 - InspectionsIndividual lot title not publishedactivePublished valueNot publishedThe Supplier is required to manage relevant inspection programme for vacant sites by a qualified individual for: • Vacant Land • Vacant Buildings These will be delivered on a scheduled programme based on the insurance requirements of our brokers. It is also desirable that the person co-ordinating the surveys provides an on-call service out of hours and act as the primary key holder for the site. The Supplier is required to record results of all inspections (not including Safety Inspections) to include: • Date of the Inspection • Who the inspection was undertaken by • An objective percentage score for the site with clearly set out reasoning • Any issues or risks at the site that need to be highlighted and the pertinent remedial works which are recommended to ensure that our sites are as safe as reasonably practicable. It is also desirable to be able to provide quotes for the suggested works on request. Additional information: The WMCA is looking to establish a six years maximum term Framework Agreement with a minimum of 4 suppliers in total for Lot 2 with a sole supplier for the vacant land and building inspections element and at least three suppliers for the ad-hoc surveys element awarded via mini competitions. A longer- term framework of six years is required due to the extended timescales within Lot 4.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
- Lot 3 · #3 - Small WorksIndividual lot title not publishedactivePublished valueNot publishedThe contractor is required to carry out any works that should be required to monitor or maintain the site, remedy any damage to the site or prevent any further damage to the site up to a value of £50,000. Works will include, but not be limited to: • Removal of fly tipping • Replacement of drain covers, fence panels, roof tiles etc • Maintenance of the boundaries • Purging of gas systems • Drainage of water systems • Landscaping works (incl tree felling, vegetation cutbacks) • Installation and maintenance of security and safety equipment (incl alarms, CCTV) Where applicable, quotes may be requested to align with procurement processes. The contractor is required to produce a report of all works done to include: • Date of works; • Who the work was undertaken by; • Confirmation that the issue is resolved; • Photographic evidence that the work has been completed Additional information: The WMCA is looking to establish a six years maximum term Framework Agreement. In terms of Lot 3, due to the potential variety of works, these will be issued via mini competition to ensure competitiveness across the period. A longer-term framework is required due to the extended timescales within Lot 4 to meet the WMCA's cyclical inspection programme.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
- Lot 4 · #4 - StructuresIndividual lot title not publishedactivePublished valueNot publishedThe Supplier is required to manage relevant inspections programmes by appointing a Supervising Engineer. The Supervising Engineer will supervise the inspection programme and be responsible for the inspections of the North Walsall Cutting bridges, Stourbridge Junction car park footbridge, Four Oaks decked car park and Longbridge decked car park. As well as any other structures which may become part of the WMCA portfolio which can be priced and discussed on a more ad-hoc basis. The Supervising Engineer should be a Chartered Civil or Structural Engineer with a background in design, construction or maintenance of highway structures. The inspection programme is required to commence Summer 2022 unless otherwise stated. Confirmed inspection requirements are: General Inspections; 24 months frequency, commencing July 2022 • North Walsall Cutting bridges - Upper Green Lane, Bloxwich Road, Mill Street and Proffitt Street • Stourbridge Junction car park footbridge Principle Inspections; 6 year intervals, as a replacement of the General Inspection due • North Walsall Cutting bridges - Upper Green Lane, Bloxwich Road, Mill Street and Proffitt Street • Stourbridge Junction car park footbridge General Inspection Plan to be drawn up and agreed for Car Park Structures • Four Oaks Extension • Longbridge The Supplier is required to provide resources for occasional bridge ‘call out visits’ and Special Inspections when a need is identified. Attendance at site is required within 24 hours of the call out request from WMCA Asset Management. The Supplier is required to record results of all inspections (not including Safety Inspections) to include: a) Date of the inspection b) Those responsible for undertaking the inspection c) General information about the structure (e.g. name, reference and location) d) Details of the prevailing weather conditions at the time of the inspection. Additional information: The WMCA is looking to establish a six years maximum term Framework Agreement with one supplier for Lot 4 to ensure consistency over that period. A longer-term framework is required due to the extended timescales within Lot 4 to meet the WMCA's cyclical inspection programme.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
23 Dec 2021, 22:45 GMT - Submission deadline
28 Jan 2022, 12:00 GMT
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
West Midlands Combined Authority
Contracting authority GB-FTS-2655Documents (2)
Official links; attachments are not copied
Related procedures (0)