Find a TenderAwarded without competitionContract details notice
Published 2 Apr 2026, 16:08 BST

Official UK procurement notice

Provision of Artificial Intelligence Schedule Risk Analysis Tool

Official notice

Authority: East West Rail Company Limited (Central government)

Direct awardSME suitable
Sectors: IT Services & Software (72) Delivery: UK
Awarded value£3,014,851published contract · exc. VAT
Awarded 22 Jun 2026no call for competition
Awarded to NPLAN LIMITED2 awards

What is being bought

Published requirement description

Licence of an Artificial Intelligence Schedule Risk Analysis Tool, which uses a proprietary dataset and analysis of previously completed projects to apply learning to current schedules, to better predict the outcome

The lotProcurement structure

single lot · no lot value published
Lot #1AwardedSME
Delivery: UKEligibility: SME eligible

Procedure terms & legal framework

From the official record
Procedure method
Direct award
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
2 Apr 2026, 16:08 BST
Last source update
12 Jul 2026, 13:19 BST
Authority reference
CT4952
FTS notice number
2026/S 000-065391
Latest notice
Contract details notice (UK7)
Delivery area
UK
Official registry OCID
ocds-h6vhtk-067c3d Find a Tender
Why no open competition
Single Suppliers Intellectual Property Exclusive Rights; Single Suppliers Technical Reasons
Published justification

This direct award is proposed under Section 41 and Schedule 5,

paragraphs (5) and (6) of the Procurement Act 2023 on the basis that

the contract may be awarded without competition where, for technical

reasons, only a particular supplier is capable of delivering the

requirement.

EWR Co has determined that the services can only be supplied by

Nplan Ltd for the following technical reasons:

  • A common AI-based schedule risk analysis solution, underpinned

by a proprietary and unique relevant dataset, is required across the

East West Rail programme to ensure consistency of methodology,

outputs and reporting. Nplan's service operates on the basis of a

proprietary dataset comprising over 750,000 schedules across

various industries but critically including historical Crossrail, Network

Rail and HS2 data which is are of particular relevance to EWR given

that these examples also pertain to rail construction; and

  • EWR does not believe any other supplier offers a comparable

service with the same functionality based on real GB rail data.

There are therefore no reasonable alternatives to the Nplan service

offering.

For these reasons, EWR Co considers that Nplan Ltd is the only supplier capable of meeting the specific and complex technical requirements of the project while ensuring value for money and continuity of delivery

Review and risk notes
Risks

n/a

How it was run

Official notice
Submission deadline
—

Timeline

1 Jul 2026 → 12 Jul 2026 · 2 dates
  1. Standstill ends110 days ago
    1 Jul 2026, 23:59 BST
  2. Notice published100 days ago
    12 Jul 2026, 13:19 BST

Notice history

4 events · 3 releases on Find a Tender · since 2 Apr 2026
  1. Transparency notice published
    2 Apr 2026, 16:08 BST
    UK5
  2. Contract award notice published
    22 Jun 2026, 09:38 BST
    UK6
  3. Contract signature expected
    2 Jul 2026, 23:59 BST
    scheduled
  4. Contract details notice published
    12 Jul 2026, 13:19 BST
    UK7

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 2
Awarded value £3,014,8511 contract exc. VAT · 1 repeated publication of the same award counted once
Contracts signed 1latest 6 Jul 2026
Awarded toValueDateStatus
NPLAN LIMITEDSME2 Jul 2026 – 1 Jul 2027 · up to 1 Jul 2037Extensions: Maximum duration of 12 years - with a renewal every year which is to be agreed by the business. · Options: Additional technical support where required£3,014,851same award published again · counted once22 Jun 2026standstill to 1 Jul 2026Standstill
NPLAN LIMITEDSME£3,014,851 †—Awarded

Contracts

  • Contract 2 · NPLAN LIMITEDSME

    Signed
    6 Jul 2026
    Value
    £3,014,851
    Period
    6 Jul 2026 – 5 Jul 2027 · up to 5 Jul 2037 with extensions
    Status
    active
    Extensions
    Maximum duration of 12 years - with a renewal every year which is to be agreed by the business.
    Options
    The right to additional purchases while the contract is valid. Additional technical support where required
    1 agreed KPI: Platform Availability
    • Platform Availability, Commencing at the activation of the Cloud Service, except during maintenance periods and Force Majeure events, Company targets a Cloud Service uptime (“Target Service Uptime”) of 99.5%, calculated as (total time in preceding calendar month - unplanned downtime) ÷ total time in preceding calendar month, expressed as a percentage.

Contracting authority & participating public bodies

East West Rail Company Limited

Contracting authorityPublic authority - central government GB-COH: 11072935 · GB-PPON: PVRL-7849-PXXT The Quadrant, Milton Keynes, MILTON KEYNES, South East, MK9 1ENContact email

Bidders & participating suppliers

1 commercial party on the notice
  • NPLAN LIMITEDAwarded supplierGB-COH: 11043916GB-PPON: PTQY-5439-MMDR 68 Hanbury Street, London, London, E1 5JLContact email

Official documents & specifications (3)

Official links; attachments are not copied

Notices published for this procedure

  • Contract details notice contractContract details noticeUK7Contract details notice on Find a Tender
  • Contract award notice awardContract award noticeUK6Contract award notice on Find a Tender
  • Transparency notice awardTransparency noticeUK5Transparency notice on Find a Tender