Find a TenderAwarded without competitionContract details notice
Published 3 Feb 2026, 16:44 GMT

Official UK procurement notice

Sharnberry MWTS - Power Connection - Phase 2 Non-Contestable Works

Official notice

Authority: Mining Remediation Authority (Central government)

Direct award
Awarded value£435,072published award · exc. VAT
Awarded 17 Feb 2026no call for competition
Awarded to Northern Powergrid (Northeast) PLC2 awards

What is being bought

Published requirement description

The Water and Abandoned Metal Mines Programme (WAMM) is the primary delivery mechanism to achieve the statutory Environment Act target to halve the length of rivers polluted by harmful metals from abandoned metal mines by 2038.

WAMM is being delivered by a partnership between the Mining Remediation Authority, the Environment Agency and Defra.

The former Sharnberry mines are located in County Durham at the far eastern edge of the North Pennines Orefield, in the Pennines Moors.

The mines pollute rivers in the Wear catchment, specifically the Euden Beck and downstream Bedburn Beck.

The Environment Agency carried out a detailed monitoring programme to measure the metal concentrations and river flows at various points across the catchment. This monitoring indicated that the Sharnberry adit is the most significant source of zinc and cadmium pollution and also contributes to lead pollution.

The Environment Agency have advised that a Mine Water Treatment Scheme (MWTS) is required that will require a permanent power connection.

In February 2025, it was agreed to progress with Phase 1 of the grid connection, which is from Eggleston Crest to the boundary of the Eggleston Estate access track.

This contract is for non-contestable works of the phase 2 grid extension, which is for Northern Powergrid to:

  • Upgrade the existing two-conductor system to Three-Phase, which involves rebuilding the line.
  • Carrying out 1x HV closing joint
  • Undertaking all Senior Authorised Person work associated with all connections to the Distribution System

The lotProcurement structure

single lot · no lot value published

Procedure terms & legal framework

From the official record
Procedure method
Direct award
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
3 Feb 2026, 16:44 GMT
Last source update
27 Mar 2026, 10:26 GMT
Authority reference
CA18/2/1/137
FTS notice number
2026/S 000-028354
Latest notice
Contract details notice (UK7)
Delivery area
North East (UKC)
Official registry OCID
ocds-h6vhtk-0615cf Find a Tender
Why no open competition
Single Suppliers Technical Reasons
Published justification

Single supplier - technical reasons

These services fall under the definition of non-contestable works under the auspices of the Electricity Act of 1989

When applying for a new electricity connection to the national grid, non contestable works refer to those elements of the connection process that only the Distribution Network Operator (DNO) can legally carry out. They contrast with contestable works, which independent providers (ICPs or IDNOs) may execute under suitable accreditation.

In this instance the DNO is Northern Powergrid

Notice history

3 events · 2 releases on Find a Tender · since 3 Feb 2026
  1. Transparency notice published
    3 Feb 2026, 16:44 GMT
    UK5
  2. Contract signature expected
    20 Feb 2026, 23:59 GMT
    scheduled
  3. Contract details notice published
    27 Mar 2026, 10:26 GMT
    UK7

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 2
Awarded value £435,0721 award exc. VAT
Contracts signed 2latest 17 Feb 2026
Awarded toValueDateStatus
Northern Powergrid (Northeast) PLC20 Feb 2026 – 31 Dec 2026 · up to 31 Dec 2027Extensions: Extensions will only be required if operational site conditions, weather and other factors delay delivery of services£435,072—Awarded
Northern Powergrid (Northeast) PLC——Awarded

Contracts

  • Sharnberry MWTS - Power Connection - Phase 2 Non-Contestable Works · Northern Powergrid (Northeast) PLC

    Signed
    17 Feb 2026
    Value
    £435,072
    Period
    20 Feb 2026 – 31 Dec 2026 · up to 31 Dec 2027 with extensions
    Status
    active
    Extensions
    Extensions will only be required if operational site conditions, weather and other factors delay delivery of services

    No agreed KPIs: Below threshold and non contestable works

  • Only one contract awarded · Northern Powergrid (Northeast) PLC

    Signed
    17 Feb 2026
    Value
    £0
    Period
    20 Feb 2026 – 31 Dec 2026
    Status
    active

Contracting authority & participating public bodies

Mining Remediation Authority

Contracting authorityPublic authority - central government GB-PPON: PRPD-5825-QDVY 200 Lichfield Lane, Nottinghamshire, East Midlands, NG18 4RGContact name, email

Bidders & participating suppliers

1 commercial party on the notice
  • NORTHERN POWERGRID (NORTHEAST) PLCAwarded supplierGB-COH: 02906593GB-PPON: PDXB-1394-ZPXN Lloyds Court, Newcastle Upon Tyne, North East, NE1 6AFContact email

Official documents & specifications (3)

Official links; attachments are not copied

Notices published for this procedure

  • Contract details notice contractContract details noticeUK7Contract details notice on Find a Tender
  • Contract details notice contractContract details noticeUK7Contract details notice on Find a Tender
  • Transparency notice awardTransparency noticeUK5Transparency notice on Find a Tender