Official UK procurement notice
Northwick Park, One Public Estate Spine / Access Road Construction (CIF -2021-013)
Authority: London Borough of Brent (Local council)
What is being bought
Published requirement descriptionThe council required the provision of highway construction work for the Northwick Park Spine / Access road project.
CPV: Construction work
The lotProcurement structure
single lot · no lot value publishedLot #1Highway construction work for the Northwick Park Spine / Access road projectAwarded
Procedure terms & legal framework
From the official record- Procedure method
- Award procedure without prior publication of a call for competition
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Works
- Notice status
- Awarded without competition
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Direct award (no call for competition)
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 14 Jun 2023, 15:47 BST
- Last source update
- 14 Jun 2023, 15:47 BST
- Authority reference
DN537482- FTS notice number
2023/S 000-016913- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-03d640Find a Tender
- Why no open competition
- The procurement falls outside the scope of application of the directive
- Published justification
Framework
- Review procedure
The Contracting Authority incorporated a 10 day calendar day standstill period at the point information on the award of the contact when communicated to tenderers. The Public Contracts Regulations 2015 (SI 2015 nº 102) (as amended) provide for aggrieved parties who have been harmed or are at risk of harm by a breach of the rules to take action in the High Court (England, Wales and Northern Ireland). Any such action must be started within 30 days beginning with the date when the aggrieved party first knew or ought to have known that grounds for starting the proceedings had arisen. The Court may extend the time limit for starting proceedings where the Court considers that there is a good reason for doing so but not so as to permit proceedings to be started more than 3 months after that date. Where a contract has not been entered into, the Court may order the setting aside of the award decision or order the Contracting Authority to amend any document and may award damages. If the contract has been entered into the Court may only award damages or, where the contract award procedures have not been followed correctly, declare the contract to be “ineffective”.
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| Volkerfitzpatrick Ltd | £6,022,990 † | — | Awarded |
Contracts
Contract 016913-2023-1 · Volkerfitzpatrick Ltd
- Signed
- 14 Jan 2022
- Value
- £6,022,990
- Status
- active
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 3bids · 3 electronic · 3 from abroad | 0 | — | — |
Contracting authority & participating public bodies
Dispute resolution & review bodies
- The High CourtReview body
Bidders & participating suppliers
1 commercial party on the notice- VolkerFitzpatrick LtdAwarded supplier
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.