Find a Tender
complete
Official procurement procedure
Multi-vector waste stream analysis for electrolytic fuel production hubs
Research consultancy services
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Wales & West Utilities Limited: "Multi-vector waste stream analysis for electrolytic fuel production hubs". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Wales & West Utilities Limited | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Wales & West Utilities Limited
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Wales & West Utilities Limited. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
Not availableNo published reports
Supplier ConcentrationModerate Concentration
WARM WALES - CYMRU GYNNESTop vendor: 41% of attributable valuePayment Terms
Check noticePublished terms
Coverage: 13 active published awards; 0 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Historical Awarded Suppliers With This Authority:
| Supplier Name | Historic Awards | Attributable GBP Value |
|---|---|---|
| WARM WALES - CYMRU GYNNES | 1 win | £2,000,000 |
| MIND (THE NATIONAL ASSOCIATION FOR MENTAL HEALTH) | 1 win | £1,150,000 |
| BRITISH KIDNEY PATIENT ASSOCIATION(THE) | 1 win | £1,100,000 |
| SUSTAINABLE COMMUNITY SOLUTIONS LIMITED | 1 win | £626,967 |
Procedure terms
Contracting AuthorityWales & West Utilities Limited | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published31 Jul 2023, 12:55 BST | Last source update31 Jul 2023, 12:55 BST | Recurring procurementNot published |
ClassificationResearch consultancy services | ||
Delivery area | ||
OCIDocds-h6vhtk-03defd | ||
What is being bought
The Alpha phase of the Integrated Hydrogen Transport Hubs project will build on the work undertaken within the Discovery phase by continuing to develop the bespoke site selection
criteria with a view on physical deliverability. This detailed analysis will further enable the down-selection of a preferred site or sites to progress into detailed design. An engineering proposal will then be refined through engagement with statuary undertakers and permitting authorities to understand site specific constraints and risks. OEM's will be consulted to further refine CAPEX and OPEX costs associated with delivery, and propose the commercial
and regulatory operating model in preparation for a legally binding agreement. The Beta phase delivery programme will then be designed in line with proposed delivery partners and the project supply chain, based on the findings of the work completed in Alpha.
What changed
From the official release history
- Official notice release published
31 Jul 2023, 12:55 BST - Status changed to complete
5 Jul 2023, 12:03 BST - Official notice release published
5 Jul 2023, 12:03 BST - Buyer information updated
5 Jul 2023, 12:03 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedWWU REQUIRES a detailed analysis of a bespoke site selection for an Integrated Hydrogen Transport Hub. Including engagement with statuary undertakers and permitting authorities to understand site specific constraints and risks. CAPEX & OPEX costs will also be detailed. WWU SORT TO PROCURE A SOLUTION THAT, TO THE FULLEST EXTENT PRACTICABLE FULFILLED THIS REQUIREMENTContract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
31 Jul 2023, 12:55 BST - Award active
Not published · Not published - Contract active
Signed 31 Jul 2023, 00:00 BST · Not published
Commercial outcome and competition
Awards Awarded supplier not published Not published · Not published · active |
Contracts Contract Not published · signed 31 Jul 2023, 00:00 BST · active |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
Wales & West Utilities Limited
Contracting authority GB-COH-05046791Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleAward due to absence of competition for technical reasons, |