Official UK procurement notice
ICT-20-001 Supply and Maintenance of Multi-Functional Devices and Photocopiers for Schools
Authority: the Education Authority (Central government)
What is being bought
Published requirement descriptionSupply and Maintenance of Multi-Functional Devices and Photocopiers for Schools across Northern Ireland
CPV: Office and computing machinery, equipment and supplies except furniture and software packages
The lotProcurement structure
single lot · no lot value publishedLot #1Supply and Maintenance of Multi-Functional Devices and Photocopiers for Schools
Procedure terms & legal framework
From the official record · publisher note attached- Procedure method
- Award procedure without prior publication of a call for competition
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Goods
- Notice status
- Awarded without competition
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Direct award (no call for competition)
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Unspecified in notice
- First published
- 9 Jul 2025, 12:45 BST
- Last source update
- 23 Jul 2025, 10:54 BST
- FTS notice number
2025/S 000-042284- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-055bf1Find a Tender
- Why no open competition
- The procurement falls outside the scope of application of the directive
- Published justification
It would appear that Regulation 72(1)(b) would apply under the circumstances.
The Regulation states:
(b) for additional works, services or supplies by the original contractor that have become necessary and were not included in the initial procurement, where a change of contractor—
(i) cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement, or
(ii) would cause significant inconvenience or substantial duplication of costs for the contracting authority, provided that any increase in price does not exceed 50% of the value of the original contract;
For this particular modification, (i) EA requires continuity of service from the Contractors until a replacement contract has been procured. EA cannot swap out the technology already installed by the contractors until a new contract is in place.
Plus (ii) the value of the modification is 30% of the original contract value.
Publisher note: This modification is to extend the contract period by 5 months, up to 31st January 2026 and increase the contract award value by 30% (£4,350,000.00) in order to facilitate this.
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast2 suppliers are admitted to this framework without individual award values or dates, see the supplier list below.
Contracts
All 2 of these contracts carry the same published figure, £20,300,000, the framework's maximum for the whole notice, not each contract's own value. They are not eleven separate sums.
Contract 042284-2025-ICT-20-001-1
- Signed
- 22 Jul 2025
- Value
- ceiling above
- Status
- active
- Change Contract previously modified with new end date of 31st August 2025 and value of £15,950,000.00. Contract term now modified to end date of 31st January 2026 and value increased by 30% to £20,300,000.00., Need for modification brought about by circumstances which a diligent contracting authority/entity could not foresee: It would appear that Regulation 72(1)(b) would apply under the circumstances. The Regulation states: (b) for additional works, services or supplies by the original contractor that have become necessary and were not included in the initial procurement, where a change of contractor— (i) cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement, or (ii) would cause significant inconvenience or substantial duplication of costs for the contracting authority, provided that any increase in price does not exceed 50% of the value of the original contract; For this particular modification, (i) EA requires continuity of service from the Contractors until a replacement contract has been procured. EA cannot swap out the technology already installed by the contractors until a new contract is in place. Plus (ii) the value of the modification is 30% of the original contract value. A Pre Market Engagement Notice for the procurement of a new framework has been published and can be accessed via the following link: https://etendersni.gov.uk/epps/cft/prepareViewCfTWS.do?resourceId=6034936
Contract 038569-2025-1
- Signed
- 9 Jul 2025
- Value
- ceiling above
- Status
- active
Contracting authority & participating public bodies
Dispute resolution & review bodies
- The UK does not currently have any such bodies with responsibilities for appeal/mediation proceduresReview body
Framework contractors & participating bidders
5 commercial parties on the notice- CALVERT OFFICE EQUIPMENT LTDFramework contractor
- CALVERT OFFICE EQUIPMENT LTDFramework contractor
- CALVERT OFFICE EQUIPMENT LTDFramework contractor
- QLC SOLUTIONS LTDFramework contractor
- XEROX UK LTDFramework contractor
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.