FWoW Connections Portal - Phase 1 additional costs
IT services: consulting
software development
Internet and support
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: NORTHERN GAS NETWORKS LIMITED: "FWoW Connections Portal - Phase 1 additional costs". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | NORTHERN GAS NETWORKS LIMITED | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: NORTHERN GAS NETWORKS LIMITED
Market Analytics
Derived from OCDS awards & bid statistics
Published history for NORTHERN GAS NETWORKS LIMITED. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
3.5Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 20 active published awards; 8 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityNORTHERN GAS NETWORKS LIMITED | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published28 Sept 2022, 15:54 BST | Last source update28 Sept 2022, 15:54 BST | Recurring procurementNot published |
ClassificationIT services: consulting, software development, Internet and support | ||
Delivery area | ||
OCIDocds-h6vhtk-036c3b | ||
What is being bought
In 2020 during the FWoW Connections project it was identified that an online self-serve portal would benefit both the connections team but also our connections customers by
improving the time it takes to raise and complete a quotation
or job. It would also improve the overall customer experience because customers would have access to real time information about their application status.
TPoint have built the majority of the functionality in the portal. This notice is for for some additional costs to implement Phase 1 of the portal for go live.
What changed
From the official release history
- Official notice release published
28 Sept 2022, 15:54 BST - Status changed to complete
28 Sept 2022, 15:47 BST - Official notice release published
28 Sept 2022, 15:47 BST - Buyer information updated
28 Sept 2022, 15:47 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedIn 2020 during the FWoW Connections project it was identified that an online self-serve portal would benefit both the connections team but also our connections customers by improving the time it takes to raise and complete a quotation or job. It would also improve the overall customer experience because customers would have access to real time information about their application status. TPoint have built the majority of the functionality in the portal. This notice is for for some additional costs to implement Phase 1 of the portal for go live. N.B. This a variation to the Customer Engagement Management System contract. From the last variation the total increase since the original contract was 39%, however NGN was unable to publish a modification notice because the original contract notice could not be found, therefore a VEAT notice was published instead.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
28 Sept 2022, 15:54 BST - Award active
Not published · Not published - Contract active
Signed 28 Sept 2022, 00:00 BST · Not published
Commercial outcome and competition
Awards Awarded supplier not published Not published · Not published · active |
Contracts Contract Not published · signed 28 Sept 2022, 00:00 BST · active |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
NORTHERN GAS NETWORKS LIMITED
Contracting authority GB-COH-NORTHERN GAS NETWORKS LIMITEDDocuments (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleIn 2020 during the FWoW Connections project it was identified that an online self-serve portal would benefit both the connections team but also our connections customers by
improving the time it takes to raise and complete a quotation
or job. It would also improve the overall customer experience because customers would have access to real time information about their application status. TPoint have built the majority
of the functionality in the portal. This notice is for some additional costs to implement Phase 1 of the portal for go live.
N.B. This a variation to the Customer Engagement Management System contract. From the last variation the total overall increase since the original contract was 39%, however NGN was unable to publish a modification notice because the original contract notice cannot be found, therefore a VEAT notice was published instead. |