Find a TenderAwarded without competitionContract award notice
Published 2 Jul 2026, 14:27 BST

Official UK procurement notice

for the completion of the Integrated Control & Safety System (ICSS) for the H3AT Tritium Facility at Culham

Official notice

Authority: UK Atomic Energy Authority (Central government)

Direct award
Awarded value£3,256,918published award · exc. VAT
Award in standstill 8 Sept 2026no call for competition
Award (standstill) to Bilfinger UK Limiited

What is being bought

Published requirement description

Scope of supply is for the continued design development, procurement, manufacture, testing, installation and verification activities for the H3AT Integrated Control and Safety System (ICS).

The lotProcurement structure

single lot · no lot value published

Procedure terms & legal framework

From the official record
Procedure method
Direct award
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
2 Jul 2026, 14:27 BST
Last source update
8 Sept 2026, 08:43 BST
Authority reference
JP-ICS-001
FTS notice number
2026/S 000-084682
Latest notice
Contract award notice (UK6)
Delivery area
UKSouth East (UKJ14)
Official registry OCID
ocds-h6vhtk-06c27d Find a Tender
Why no open competition
Single Suppliers Technical Reasons
Published justification

This notice provides transparency of UKAEA’s intention to award a contract to Bilfinger UK Limited (BUK) for the completion of the Integrated Control & Safety System (ICSS) for the H3AT Tritium Facility at Culham. The ICSS scope forms a critical part of the H3AT facility, covering the design finalisation, manufacture, installation, testing and commissioning of the control, interlock and safety systems required to safely operate the tritium plant. BUK was originally engaged as a specialist subcontractor under a wider contract with a previous main contractor (DBD), with direct responsibility for delivering the ICSS scope. Following the termination of the DBD contract, the ICSS works remain partially complete (approximately 50%) and have been significantly progressed by BUK. UKAEA intends to award a direct contract to BUK to complete the remaining works for the following reasons:

  • Proprietary Know-How & Design Continuity The ICSS design, software configuration, control architecture, and technical associated documentation have been uniquely developed and partially implemented by BUK, and are specific to their proprietary systems, tooling, and engineering approach.
  • Safety & Technical Risk Assumption : A change of supplier would require a third party to assume legal and technical liability to take over, reinterpret, and revalidate partially completed design and safety-critical systems, including Safety Integrity Level (SIL )-rated elements, which would introduce material technical and programme risk that cannot be mitigated by an alternative party
  • System Incompatibility: The ICSS must seamlessly integrate with existing plant systems and previously installed components already delivered by BUK. Substituting the supplier at this stage introduces in incompatibility risks across hardware, software, interfaces and safety validation activities.
  • Disproportionate Duplication & Rework: Replacement of BUK would lead to significant and wasteful rework, duplication of design assurance and testing, and potential invalidation of completed Factory Acceptance Testing (FAT) and statutory safety lifecycle deliverables.
  • Operational Hardship: These impacts would create disproportionate technical and operational difficulties, particularly in relation to safety assurance, system integration, and commissioning of a nuclear-grade system integration and final commissioning of the facility. On this basis, UKAEA considers that:
  • The proposed contract represents a partial continuation and completion of existing works by the original delivery party, and
  • Changing supplier would result in incompatible outcomes void existing warranties/assurances and cause disproportionate technical difficulties in operation and maintenance. The proposed direct award is therefore justified in accordance with the Procurement Act 2023, Schedule 5, Clause 7 (a) and (b). In addition, due to the unique level of system integration, the proprietary nature of the partially completed design, and BUK’s ownership of detailed implementation knowledge, there is an absence of alternatives who can complete the works without significant risk to the facility’s safety case, delay, and substantial duplication of cost, further supporting reliance on Schedule 5 provisions.

How it was run

Official notice
Submission deadline
—

Timeline

8 Sept 2026 → 17 Sept 2026 · 2 dates
  1. Notice published48 days ago
    8 Sept 2026, 08:43 BST
  2. Standstill ends38 days ago
    17 Sept 2026, 23:59 BST

Notice history

3 events · 2 releases on Find a Tender · since 2 Jul 2026
  1. Transparency notice published
    2 Jul 2026, 14:27 BST
    UK5
  2. Contract award notice published
    8 Sept 2026, 08:43 BST
    UK6
  3. Contract signature expected
    30 Sept 2026, 23:59 BST
    scheduled

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £3,256,9181 award exc. VAT
Awarded toValueDateStatus
Bilfinger UK Limiited1 Oct 2026 – 25 Jan 2028£3,256,9188 Sept 2026standstill to 17 Sept 2026Standstill

Contracting authority & participating public bodies

UK Atomic Energy Authority

Contracting authorityPublic authority - central government GB-PPON: PLJV-1169-JTDD Culham Science Centre, Oxfordshire, South East, OX14 3DBContact name, email, phone

Bidders & participating suppliers

1 commercial party on the notice
  • Bilfinger UK LimiitedAwarded supplierGB-PPON: PWRZ-9254-NNBJ Wilson House, Kelburn Court, Birchwood, Warrington, North West, WA3 6UTContact email

Official documents & specifications (2)

Official links; attachments are not copied

Notices published for this procedure

  • Contract award notice awardContract award noticeUK6Contract award notice on Find a Tender
  • Transparency notice awardTransparency noticeUK5Transparency notice on Find a Tender