Extension of Revenue Collection Contract ("RCC") with Cubic

Automatic fare collection
Computer equipment and supplies
Database and operating software package
+9 more
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Transport for London: "Extension of Revenue Collection Contract ("RCC") with Cubic". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
Contracting AuthorityTransport for LondonScope & CategoriesNot publishedSubmission Window
complete
No deadline published
Submission GatewayDirect notice routeLegal Basis & RegimeStandard procurementEstimated Value (exc. VAT)Not published
Bidder Intelligence · Authority Profile: Transport for London
Market Analytics
View Authority Profile →
Derived from OCDS awards & bid statistics
Published history for Transport for London. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Requires at least 5 comparable procedures
Competition Density
3.7Bids / Report
8.6% of reports have one bid
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate available
Payment Terms
Check noticePublished terms
Payment obligations depend on the applicable regime and contract. Consult the official documents.
Coverage: 49 active published awards; 35 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityTransport for London
Procedure methodNot published
Procurement categoryNot published
Statuscomplete
Framework / DPSNot published
CompetitionNot published
Above thresholdNot published
Legal basisNot published
Tender period startsNot published
Clarification deadlineNot published
Electronic submissionNot published
Submission languagesNot published
Published23 Jun 2022, 17:02 BST
Last source update23 Jun 2022, 17:02 BST
Recurring procurementNot published
ClassificationAutomatic fare collection, Computer equipment and supplies, Database and operating software package, IT services: consulting, software development, Internet and support, Information systems, Maintenance and repair of ticket-issuing machinery, Miscellaneous software package and computer systems, Sales, marketing and business intelligence software package, Transaction-processing software package
Delivery area
OCIDocds-h6vhtk-034a00
What is being bought
In 2014, after a competitive tender, TfL entered into the RCC with Cubic Transportation Systems Ltd ("Cubic") for an initial term of 7 years, starting 17 August 2015, with an option to extend for a further 3 years. TfL exercised that option in 2017 and the RCC is now due to expire on 16 August 2025. TfL is in the pre-tender stages of retendering the RCC services. Given the complexity and importance of these services and the time required to complete the competitive tender and handover, and the numerous contingent factors which could delay this process, including anticipated delays in completing the replacement card reader roll-out programme, TfL considers that the RCC needs to be extended by one year, until 16 August 2026 ("Extension") in order to give sufficient flexibility and certainty that these contingent programme risks can be managed appropriately. As explained at IV.1.1 below, TfL considers that the Extension benefits from the exemption in Reg. 88(1)(b) UCR.
What changed
From the official release history
  1. Status changed to complete
    23 Jun 2022, 17:02 BST
  2. Official notice release published
    23 Jun 2022, 17:02 BST
  3. Buyer information updated
    23 Jun 2022, 17:02 BST
Lots and requirements (1)
Published by the contracting authority
  • Lot 1 · #1
    Individual lot title not published
    Status not published
    Published valueNot published
    As noted at II.1.4) above, in August 2015, pursuant to a competitive tender process, TfL entered into the RCC with Cubic. Cubic was awarded the RCC for an initial term of seven years, commencing 17 August 2015, with an option to extend for a further three years. TfL exercised that option in 2017 and the RCC is now due to expire on 16 August 2025. TfL is in the pre-tender stages of its project to retender (via a competitive dialogue) the RCC revenue collection services following expiry of the RCC ("Project Proteus"). Given the complexity and importance to TfL and the travelling public of the revenue collection services and the time required to structure, launch and complete the competitive tender and handover for Project Proteus, and taking into account the numerous contingent factors which could delay Project Proteus, including anticipated delays in completing the replacement card reader roll-out programme (discussed further below), TfL considers that the Extension is needed in order to give sufficient flexibility and certainty that these contingent programme risks can be managed appropriately. The current card readers (which were installed around 2010) are now reaching their end of design life, which creates asset management and revenue risk which would otherwise be unpalatable to TfL and potentially unacceptable to newcomer bidders. It is important for the competitiveness of the Proteus tender to ensure that there is a demonstrably working card reader which the successful bidder can inherit and operate (at least for the bus element of the Proteus procurement, with options available for the installation of the less time-critical rail element). By giving TfL enough time to work with Cubic under the RCC to design, manufacture and complete bus (but not rail) rollout of the new reader, TfL can demonstrate to newcomer bidders that these risks are appropriately mitigated. As explained at sections IV.1.1 [and VI.3] below, TfL considers that the Extension benefits from the exemption for "additional services" in Regulation 88(1)(b) of the UCR. This exemption allows for the non-competitive procurement of additional services that have become necessary, where a change of contractor cannot be made for economic or technical reasons and where such a change would cause significant inconvenience or duplication of costs.
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
Timeline
  1. Procedure published
    23 Jun 2022, 17:02 BST
  2. Award active
    Not published · Not published
  3. Contract active
    Signed 23 Jun 2022, 00:00 BST · Not published
Commercial outcome and competition
Awards
Awarded supplier not published
Not published · Not published · active
Contracts
Contract
Not published · signed 23 Jun 2022, 00:00 BST · active
Bid statistics
highestValidBidValue: 120000000
lowestValidBidValue: 60000000
highestValidBidValue: 120000000 (lot 1)
lowestValidBidValue: 60000000 (lot 1)
Buyer and organisations in this procedure

Transport for London

Contracting authority GB-FTS-14777
View buyer profile
  • Transport for London
    buyer

    5 ENDEAVOUR SQUARE, LONDON, UKI, E201JN
  • High Court (England, Wales and Northern Ireland)
    reviewBody

    London
Documents (0)
Official links; attachments are not copied
No data
No linked documents are published
Related procedures (0)
No data
No related procedures published
Planning and rationale
Planning budgetNot published
No-engagement rationaleNot published
Procedure rationaleTfL considers that the Extension benefits from the exemption in Reg. 88(1)(b) UCR, for the following reasons. The Extension has become necessary in order for TfL to: (i) demonstrate to newcomer bidders that there is a working card reader which the successful bidder can inherit and operate; (ii) deliver an appropriately structured and planned Project Proteus re-procurement programme based on a level playing-field where newcomer bidders are given the necessary information, reading-in time and opportunities to discuss the replacement services with TfL; and (iii) ensure a smooth and risk-mitigated transition from Cubic to any new contractor. It would be very difficult to bring in a different contractor on a short-term basis in a way that safeguarded the continued operation of TfL's revenue collection system and achieved value for money for TfL. Running a competitive tender for a short-term extension ahead of the larger Project Proteus tender process would also involve substantial duplication of costs for TfL and could delay completion of the Proteus tender process. The 12-month duration of the Extension is reasonable and necessary, given the following factors: • due to various factors (including the component supply difficulties arising from the war in Ukraine) TfL has concluded that targeting July 2025 for completing the deployment of the new bus readers is not achievable, and, after taking into account recent input from Cubic, TfL is now working with a revised programme targeting June 2026; • the complexity of the services and the need for newcomer bidders to immerse themselves in information so that they can submit compliant and competitive proposals; • the inherent advantage held by Cubic, which may only be mitigated via the provision of adequate time and information to newcomer bidders during the procurement process; • the complexity of transitioning from Cubic to a new supplier, where the new supplier is likely to require significant handover and early life support from Cubic, and recent market feedback about the likely timeline required for that transition; and • the need to allow for potential delays arising from contingencies such as (i) possible force majeure events resulting from a resurgence of the pandemic, (ii) bidders needing more time during the procurement process due to the factors described above; (iii) transition or handback issues or delays; and (iv) the potential for further delays to the replacement card reader roll-out.