Dunfermline Community Energy Scheme Resilience Upgrade
Construction works for power plants and heating plants
District-heating mains construction work
District-heating plant construction work
+4 more
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Fife Council: "Dunfermline Community Energy Scheme Resilience Upgrade". Published status: planned. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Fife Council | Scope & Categories | Not published | Submission Window | planned No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Fife Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Fife Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Competition Density
9.6Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 183 active published awards; 166 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityFife Council | Procedure methodNot published | Procurement categoryNot published |
Statusplanned | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published5 Mar 2025, 11:46 GMT | Last source update5 Mar 2025, 11:46 GMT | Recurring procurementNot published |
ClassificationConstruction works for power plants and heating plants, District-heating mains construction work, District-heating plant construction work, Electrical installation work of heating and other electrical building-equipment, Heat-transfer station construction work, Heating plant construction work, Heating works | ||
Delivery area | ||
OCIDocds-h6vhtk-04e9bb | ||
What is being bought
Dunfermline Community Energy Scheme (DCES) was constructed between 2006 and 2008.and is located in north Dunfermline. The scheme comprises a primary heat generation station at Lochhead landfill site comprising landfill gas engine CHP, anaerobic gas engine CHP and wood chip biomass boilers. This supplies via Broomhead Energy Centre via a 2.5km DN150 connection.
Broomhead energy centre is located west of the A823 Pilmuir Street off Broomhead Drive. The energy centre comprises a substation receiving heat from Lochhead (providing hydraulic isolation), thermal storage, backup gas boilers and ancillary equipment. The energy centre supplies heat to the DCES heat network comprising public sector, commercial and residential loads in the town.
The heat network supplied from Broomhead has expanded in recent years to onboard 15 new flats from the redeveloped Carnegie Clinic and the Linen Quarter development comprising 157 dwellings.
The aim of the works to be undertaken for this project is to improve the resiliency of the scheme through the replacement of the substation with a twin plate unit, a new pressurisation and expansion unit and other ancillary equipment. In addition, the basis of the water treatment regime of the heat network supplied by the energy centre is to change from being based on an approach using chemical inhibitors to a chemical free approach in with the German VDI 2035 Standard. Note the circuit from Lochhead to the Broomhead centre is to remain unchanged.
What changed
From the official release history
- Status changed to planned
5 Mar 2025, 11:46 GMT - Official notice release published
5 Mar 2025, 11:46 GMT - Buyer information updated
5 Mar 2025, 11:46 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedplannedPublished valueNot publishedFife Council wishes to appoint an experienced district heating contractor to provide the following service: - Review Stage 3 design proposals, develop design to Stage 4 and then construction design, and accept design responsibility. - General scope of work: - Phase 1: - Install pre-fabricated modular building housing a new pressurisation and expansion system and other water quality equipment, and connect to energy centre electrical system and potable water. - Associated builder’s works - Carry out all necessary pipework and controls modifications - Change over from existing open tank based pressurisation system to new sealed pressurisation system and commissioning. - Commissioning of water treatment equipment housed in pre-fabricated modular structure. The DCES is a live network serving commercial premises, residential dwellings and a residential care home. Minimising downtime and avoiding the risk of a sustained outage is a key requirement and evaluation criteria of Fife Council. - Phase 2: - Strip out existing plate heat exchanger and water treatment equipment treatment equipment. - Associated builder’s works. - Install new twin plate substation and new water treatment and water quality monitoring equipment. - Associated electrical works. - Carry out all necessary pipework and controls modifications. - Conditioning of Broomhead district heating network system water to comply with the German VDI 2035 standard. Provision of heat to customers is to be maintained throughout the works - General timescale as follows: - Phase 1 completed by 31/03/26 - Phase 2 completed by 30/06/26Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
5 Mar 2025, 11:46 GMT
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
Fife Council
Contracting authority GB-FTS-2273Documents (0)