DoF Collaborative Arrangement Supply of Unmetered Electricity 2023-2024 (ID 4543436)
Authority: Department of Finance (Central government)
What is being bought
Published requirement descriptionThis contract will be for the supply of 100 percent green Unmetered Electricity for 12 months. The anticipated commencement date shall be 1st April 2023. The Contract will be utilised by the following clients:
- Department for Infrastructure (DfI);
- NI Water (NIW);
- The Police Service of Northern Ireland (PSNI);
- Northern Ireland Housing Executive (NIHE); and
- Translink A bid must be provided for a 12 month term (as detailed within the pricing schedule) for 100 percent green unmetered electricity. Each Client will be wholly responsible for the performance of its obligations under the contract. As CPD and its Clients are committed to the Central Government Energy Management Strategy and Action Plan to 2030 Contractors must provide 100 percent green electricity. This commits all Central Government bodies to reduce costs and consumption consistent with draft Programme for Government (PFG) indicators on greenhouse gas emissions and enhancing security of supply. This is delivered through a target to reduce net energy consumption by 30 percent by 2030 and to spend no more on energy in 2030 as we do today. In addition Department for Economy (DfE) has published an issues paper considering how best to advance proposals for an energy strategy that will enable new and challenging decarbonisation targets to be met. Not least among these is the UK Government legal requirement to achieve “net zero carbon” by 2050. Further details on this initiative can be found at www.economy-ni.gov.uk/energy-strategy-call… ↗ and www.gov.uk/government/news/uk-b… ↗ DfI has embarked on a street lighting LED retrofit programme to replace existing sodium street lighting units with LED ones resulting in reduced consumption as the year progresses. Consequently, the retrofit projects will have an impact on this contract as they will have a direct effect on the consumption of unmetered electricity. The rates submitted must be honoured for the duration of the contract despite the likelihood of a reduction in the annual usage, the supplier should take this into consideration when submitting their response.
- Recurrence: Upon expiry of the contract.
CPV: Electricity
The lotProcurement structure
single lot · value publishedLot #1AwardedRenewalPublished value£30,000,000
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
- Price
Procedure terms & legal framework
From the official record · publisher note attached- Procedure method
- Open procedure
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Goods
- Notice status
- Awarded
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Yes · Upon expiry of the contract.
- First published
- 9 Dec 2022, 10:43 GMT
- Last source update
- 8 Mar 2023, 07:11 GMT
- Award evaluation window
- 30 Jan 2023 – …
- FTS notice number
2023/S 000-006675- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-038c24Find a Tender
- Review procedure
CPD complied with the Public Contracts Regulations 2015 and, where appropriate, incorporated a standstill period (i.e. a minimum of 10 calendar days) at the point information was communicated to tenderers. That notification provided full information on the award decision. This provided time for the unsuccessful tenderers to challenge the award decision before the contract was entered into.
Publisher note: Contract monitoring: the successful contractor’s performance on the contract will be regularly monitored. Contractors not delivering on contract requirements is a serious matter. It means the public purse is not getting what it is paying for. If a contractor fails to reach satisfactory levels of contract performance they will be given a specified time to improve. If, after the specified time, they still fail to reach satisfactory levels of contract performance, the matter will be escalated to senior management in Construction and Procurement Delivery CPD for further action. If this occurs and their performance still does not improve to satisfactory levels within the specified period, it may be regarded as an act of grave professional misconduct and they may be issued with a certificate of unsatisfactory performance and the contract may be terminated. The issue of a certificate of unsatisfactory performance will result in the contractor being excluded from all. procurement competitions being undertaken by centres of procurement expertise on behalf of bodies covered by the Northern Ireland Procurement Policy for a period of 12 months from the date of issue of the certificate.
How it was run
Official notice- Submission deadline
- 30 Jan 2023, 15:00 GMT
- Submission channel
- {"written"}
- Accepted languages
- en
- Bids opened
- 30 Jan 2023, 15:30 GMT
Timeline
30 Jan 2023 → 30 Apr 2023 · 4 dates- Submission deadline30 Jan 2023, 15:00 GMT
- Bids opened30 Jan 2023, 15:30 GMT
- Notice published8 Mar 2023, 07:11 GMT
- Bids must remain valid until30 Apr 2023, 23:59 BST
Notice history
1 event · 2 releases on Find a Tender- Status changed to complete8 Mar 2023, 07:11 GMT
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| POWER NI ENERGY LIMITEDSMEContract | £25,000,000 † | — | Awarded |
Contracts
Contract · POWER NI ENERGY LIMITEDSME
- Signed
- 7 Mar 2023
- Value
- £25,000,000
- Status
- active
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 3bids · 3 electronic · 1 from abroad | 1 | — | — |
Contracting authority & participating public bodies
Dispute resolution & review bodies
- The UK does not have any such bodies with responsibility for review/appeal or mediation proceduresReview body
Bidders & participating suppliers
1 commercial party on the notice- POWER NI ENERGY LIMITEDAwarded supplier
Official documents & specifications (1)
Official links; attachments are not copiedTender pack and attachments
- Economic and financial selection criteria