DLSPME0001 - Principal Contractor or Installation Manager with Support Team
Consultative engineering and construction services
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: DIAMOND LIGHT SOURCE LIMITED: "DLSPME0001 - Principal Contractor or Installation Manager with Support Team". Published status: planning. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | DIAMOND LIGHT SOURCE LIMITED | Scope & Categories | Not published | Submission Window | planning No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: DIAMOND LIGHT SOURCE LIMITED
Market Analytics
Derived from OCDS awards & bid statistics
Published history for DIAMOND LIGHT SOURCE LIMITED. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Competition Density
4.2Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 41 active published awards; 13 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityDIAMOND LIGHT SOURCE LIMITED | Procedure methodNot published | Procurement categoryNot published |
Statusplanning | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published12 May 2025, 10:33 BST | Last source update12 May 2025, 10:33 BST | Recurring procurementNot published |
ClassificationConsultative engineering and construction services | ||
Delivery area | ||
OCIDocds-h6vhtk-051085 | ||
What is being bought
Overview of Diamond and Diamond-II
Diamond Light Source has established the internationally recognised UK Synchrotron facility at Harwell, providing unique and key large scale central national science infrastructure serving academia and industry throughout the UK and attracting visiting scientists worldwide.
The facility comprises a circular building that houses the Synchrotron machine together with the associated beamlines, labs and support facilities. Other long-beamline buildings and a specialist Cryo Electron Microscope centre are located adjacent along with a supporting office facility.
The Diamond-II Project is a £519.4m project to replace the machine with a 4th generation source and includes capital investment in three flagship beamlines to further exploit opportunities offered by the new machine, and investment in modern computing infrastructure and methods, including AI, to boost scientific productivity. Full funding for this project from the UK Government and the Wellcome Trust was confirmed in September 2023.
https://www.diamond.ac.uk/Diamond-II.html
We are still exploring whether the works will be considered as 'construction of a structure' under CDM Regulations and would like to speak to experienced organisations who can share their thoughts, ideas and experiences of other projects to help shape how Diamond moves forward with this particular part of Diamond-II.
Why are we investigating two options for the role of managing Machine upgrade activities within Zone 13 of the Synchrotron
As such, the works may either be carried out utilising the services of a Principal Contractor (PC) together with a Support Team if deemed that the works constitute 'construction of a structure' under CDM or carried out utilising the services of an Installation Manager (IM) together with a Support Team if the works are not deemed to be 'construction of a structure' under CDM.
This appointment will cover the period leading up to the start of the main shutdown (approximately 6 months) and then for Machine upgrading works within the main shutdown (12 months).
Period leading up to the 'main shutdown': it will be necessary for the PC or IM, together with an element of the Support Team, to commence involvement at some period prior to the start of the 'main shutdown' (i.e. a period of approximately 6 months) to familiarise themselves with the site, the scope of works, Diamond procedures and form relationships with key Diamond stakeholders.
Machine upgrade works in main shutdown: the physical installation of the Machine works is scheduled to start Dec'27 and be complete in Dec'28. Further commissioning works will be on-going from this date, but this will be managed separately by Diamond.
The Machine upgrade works will include:
• Strip-out of the original Diamond "Machine" components, installation of new components, connection and initial checking, carried out by Diamond staff
• Pipework upgrade contract, supervised by Diamond staff
• Cabling upgrade contract, supervised by Diamond staff
• Work Effort contract, supervised by Diamond staff
Brief outline of the work
The PC or IM and Support Team will ensure sufficient site supervision to co-ordinate the day-to-day activities within Zone 13 and the three transportation routes in/out of the building. The PC or IM and Support Team will ensure the correct safety related documents are in place, reviewed and approved before works commence.
Whilst the PC or IM will have responsibility for managing and co-ordinating the scope of works, this will be taking place inside the existing facility. Any arrangements proposed by the PC or IM would be expected to be equal to or better than Diamond's rules and procedures.
The PC or IM and Support Team will co-ordinate works in line with the Diamond-II Technical Project plan through chairing regular co-ordination meetings.
The PC or IM and Support Team will ensure that there are no safety conflicts between the various Diamond sub-contractor activities.
The PC or IM and Support Team will control the issue of all safety permits using Diamond's standard procedure.
The PC or IM and Support Team members should be able to demonstrate suitable experience in co-ordinating multi-skilled installation works and hold relevant training certification.
If you feel that your company has relevant experience in managing such works, we would like to hear from you to discuss your views on how the project could be managed in terms of either a Principal Contractor role or an Installation Manager role.
Please send company information detailing similar activities undertaken to Procurement@diamond.ac.uk .
If there are too many responses to deal with, the suppliers with the most relevant experience will be contacted.
Follow this link to download full document: https://dlsltd.sharepoint.com/:u:/s/Procurement-OPN/EYBbPgEwroJLm4X3TGT7csABcBG4s16QooH_kHEdLI9KXg?e=1VHVxi
What changed
From the official release history
- Status changed to planning
12 May 2025, 10:33 BST - Official notice release published
12 May 2025, 10:33 BST - Buyer information updated
12 May 2025, 10:33 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedplanningPublished valueNot publishedThe source published no individual title or description for this lot.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Pipeline notice
12 May 2025, 10:33 BST - Procedure published
12 May 2025, 10:33 BST - engagement
1 Sept 2025, 23:59 BST · scheduledIf you feel that your company has relevant experience in managing such works, we would like to hear from you to discuss your views on how the project could be managed in terms of either a Principal Contractor role or an Installation Manager role. Please visit our website which requires suppliers to complete a one-off simple registration form, which will generate a unique password for your account. You are then able to login to register your interest against the Pre-Market Engagement Notice and download the notice document. Link to the site: https://tenders.diamond.ac.uk/Home.aspx. Please send company information detailing similar activities undertaken to Procurement@diamond.ac.uk . No events are currently scheduled.
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
DIAMOND LIGHT SOURCE LIMITED
Contracting authority GB-COH-04375679Documents (1)
Official links; attachments are not copied
- 12 May 2025, 10:33 BST
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleNot published |