Official UK procurement notice
Destination Farnham Road Civil Works
Authority: Slough Borough Council (Local council)
What is being bought
Published requirement descriptionThis tender opportunity is procure the services to undertake the delivery of the Destination Farnham Road Scheme. The works will include the following
new parking bays including bays with EV charging points
a new off-road, two-way cycle route
upgraded roads and footways
new and upgraded pedestrian and cycle crossing facilities
introduce new street lighting along the route
upgraded bus stops and new parking facilities, along most of Farnham Road
improvements to the small park, and changes to the car park, at the junction of Sheffield Road
widened advisory cycle lanes, and further road improvements, along most of Sheffield Road
a ‘cycle street’ along most of Furnival Avenue
The lotProcurement structure
single lot · no lot value publishedProcedure terms & legal framework
From the official record- Procedure method
- Direct award
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Notice status
- Awarded without competition
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Direct award (no call for competition)
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 21 Apr 2026, 11:04 BST
- Last source update
- 29 Apr 2026, 14:51 BST
- Authority reference
TER25.03.06- FTS notice number
2026/S 000-039277- Latest notice
- Contract details notice (UK7)
- Delivery area
- Official registry OCID
ocds-h6vhtk-068715Find a Tender
- Why no open competition
- Additional Repeat Extension Partial Replacement
- Published justification
A direct award was identified as the preferred route to market due to the technical nature of the works. The award was made through the CCS Framework Agreement RM6088, Lot 2.2 – Construction and Associated Works (South of England, £3m–£10m).
How it was run
Official notice- Submission deadline
- —
Timeline
29 Apr 2026 → 11 May 2026 · 2 dates- Notice published180 days ago29 Apr 2026, 14:51 BST
- Standstill ends167 days ago11 May 2026, 23:59 BST
Notice history
4 events · 3 releases on Find a Tender · since 21 Apr 2026- Transparency notice published21 Apr 2026, 11:04 BSTUK5
- Contract award notice published29 Apr 2026, 09:04 BSTUK6
- Contract details notice published29 Apr 2026, 14:51 BSTUK7
- Contract signature expected13 May 2026, 23:59 BSTscheduled
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| Volkerfitzpatrick LtdCivil Works for the Destination Farnham Road Scheme13 May 2026 – 2 Mar 2028 | £7,506,141 | 1 Oct 2025 | Awarded |
Contracts
Civil Works for the Destination Farnham Road Scheme · Volkerfitzpatrick Ltd
- Signed
- 29 Apr 2026
- Value
- £7,506,141
- Period
- 13 May 2026 – 2 Mar 2028
- Status
- active
6 agreed KPIs: Time Predictability · Quality – Target of zero defects at completion · Cost Predictability CEs …
- Time Predictability, Meeting Programme – This measure will assess the number of calendar days between the Contract Completion Date and actual Completion as Cl 30.2:
- Quality – Target of zero defects at completion, This measure will compare total number of Defects raised compared to number of Defects not completed before Completion Date. It will be based on the formula: A x100 / B, A – Number of Defects not completed within time, B – Total number of Defects raised.
- Cost Predictability CEs, Change in costs This measure will compare the submitted cost of the compensation events to the actual cost. All costs associated with the compensation are to be included. It will be based on the formula: A x100 / B, A – Actual total cost of CEs, B – Submitted total cost of CEs.
- Compensation events, This will measure number of CEs raised by Contractor compared to number of CEs accepted by Project Manager. A x100 B, A – Number of CEs accepted by project manager, B – Total number of CEs. submitted by Contractor
- Agreement of Final Account, This will measure the time taken for the Project Manager and Contractor to agree the Final Account from the point of contract completion
- Time taken to submit the Health and Safety File and as-built drawings to the Employer, This will measure the time taken for submission of the above documents
Contracting authority & participating public bodies
Bidders & participating suppliers
1 commercial party on the notice- VolkerFitzptrick LimitedAwarded supplier
Official documents & specifications (3)
Official links; attachments are not copiedNotices published for this procedure
- Contract details notice Contract details notice on Find a Tender
- Contract award notice Contract award notice on Find a Tender
- Transparency notice Transparency notice on Find a Tender