Find a TenderClosedTender notice
Published 8 May 2025, 16:34 BST

Official UK procurement notice

Design, Build, Install and Maintenance Contract for Halton Microgrid

Official notice

Authority: Halton Borough Council (Local council)

WorksCompetitive flexible procedureAbove thresholdSME suitable
Published estimate£15,600,000≈ £5.1m / year · £15,600,000 inc. VAT · 1 value update
Submissions closed 16 Mar 2026
Contract term 3 yrs 1 moends 31 Jul 2029 · up to 1 Jun 2057 with extensions · starts 1 Jul 2026

What is being bought

Published requirement description

BACKGROUND INFORMATION

Halton Borough Council (HBC) is a Unitary Authority based in Cheshire, North West England, comprising the main towns of Runcorn and Widnes. The Council declared a Climate Emergency on the 16th October 2019. Following the declaration, the Council developed an Action Plan which is predominantly focused on reducing the Council's own carbon production.

The Council has developed a number of rooftop solar PV schemes and a 1.2MWp solar farm. Whilst these projects have been invaluable, it became apparent to the Council that larger interventions would also be required in order to meet the Council's 2040 net zero target. With this in mind, the Council commissioned a feasibility study in early 2020 to evaluate the potential to construct a solar farm on Council owned wasteland. The study concluded that the potential existed to construct a 3.62MWp solar farm on a closed landfill site located immediately north of Ditton Rd in Widnes (postcode WA8 0PG - Coordinates E: 350056, N: 385004).

The site was historically used as a chemical waste landfill site, before being converted to a municipal golf course (St Michael's Golf Course). The course was subsequently closed, and the site has been unused since.

The Council are now planning to construct a 3.62MWp solar farm at the closed landfill site, which will be connected to the existing 1.2MWp solar farm via a new 11kV link. The resulting 5.2MWp of solar PV generation will provide power to a number of council owned facilities in Widnes town via an extensive 11kV ring main which is to be installed as part of the project. The scheme will also incorporate a 2MW/4MWh battery storage scheme and a high-power electric vehicle charging hub at the Council's Lower House Lane transport depot.

On 1st June 2021 the Council secured a 6.1MVA export and 5.0MVA import grid connection offer from the local DNO (SP Energy Networks).

On 27th June 2024, the Council submitted a planning application for the project, and the application was approved on 23rd January 2025.

During 2024, the Council has negotiated the necessary agreements to obtain construction access to the site. The Council own the land on which the scheme is to be built, all of the buildings, and will own the Microgrid once it is commissioned and handed over.

The Council are now seeking EPC (Engineer Procure and Construct) proposals for the turn-key detailed design, installation and commissioning of the Smart Microgrid Project, which will encompass the following key components;

(a) A 3.62MWp solar farm, including all associated building and civil engineering works.

(b) An 11kV link between the existing 1.2MWp solar farm and the new 3.62MWp solar farm.

(c) A 2MW/4MWh battery storage system at the new solar farm site.

(d) An 11kV link from the new solar farm substation to a new Intake Substation located at the

Council's Lower House Lane depot, including an associated horizontal drill under a major A

Road.

(e) A new 33kV / 11kV Intake Substation (ISS) at the Council's Lower House Lane Depot.

(f) New 11kV distribution substation infrastructure at four Council sites (Halton Stadium, Halton Leisure Centre, Municipal Offices and Lower House Lane Transport Depot)

(g) A buried HV ring connecting the new Intake Substation (ISS) with the four distribution

substations.

(h) High power EV and eRCV charging infrastructure at the Lower House Lane transport depot.

(i) A SCADA control system to enable the efficient and optimal management of the completed microgrid system and the associated generation and storage assets.

The Tenderer's scope will include all works required to deliver a fully compliant, safe, efficient and working installation.

Following completion of the construction works. The EPC Tenderer shall be responsible for providing EPC warranty and O&M (Operations and Maintenance) services for a minimum period of two years, with options for multiple contract extensions.

  • How the procedure runs: This tender notice relates to the award of a public contract through a Competitive Flexible Procedure in accordance with section 20(1) and 20(2)(b) of the Procurement Act 2023. For a description of the process including conditions of participation , the process for submitting initial and final tenders (including the negotiation stage) and the award criteria and assessment methodology, please refer to the documents available on the procurement web portal The Chest which can be accessed from the following link https://www.the-chest.org.uk/ . The project reference for the opportunity is DN797010. The contracting authority reserves the right to rely on section 31 PA 2023 to modify the terms of the procurement.

CPV: Electrical installation work · Electricity · Solar energy

The lotProcurement structure

single lot · value published
Lot #1Renewal 3 yrs 1 moSMEPublished value£15,600,000
Contract period: 1 Jul 2026 – 31 Jul 2029 (3 yrs 1 mo) · up to 1 Jun 2057 with extensionsValue: £15,600,000 exc. VAT · £15,600,000 inc. VAT
Delivery: North WestEligibility: SME eligible
Extensions: Contract extensions for the operation and maintenance and related services. The extension options available are for 3 years and 5 x 5 years. A total of 6 available extensions. Extensions are subject to a review of performance, requirements and agreement on pricing.

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
How bids were scored
Quality: 70%Price: 30%
Published award criteria (2)
  • Quality
  • Price
What this means for your bid
  • Price carries 30 of 100 points: a 10% discount moves about 3 points. The method statement decides this lot, not the discount.

Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.

Procedure terms & legal framework

From the official record
Procedure method
Competitive flexible procedure
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Procurement category
Works
Notice status
Closed
Procurement threshold
Above threshold (FTS publication)
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
8 May 2025, 16:34 BST
Last source update
12 Feb 2026, 15:33 GMT
Award evaluation window
Submission end – 30 Apr 2026
Authority reference
DN797010
FTS notice number
2025/S 000-073277
Latest notice
Tender notice (UK4)
Classification (CPV)
Electrical installation workElectricitySolar energy
Delivery area
North West (UKD71)
Official registry OCID
ocds-h6vhtk-050f2b Find a Tender
How it runs

This tender notice relates to the award of a public contract through a Competitive Flexible Procedure in accordance with section 20(1) and 20(2)(b) of the Procurement Act 2023.

For a description of the process including conditions of participation , the process for submitting initial and final tenders (including the negotiation stage) and the award criteria and assessment methodology, please refer to the documents available on the procurement web portal The Chest which can be accessed from the following link www.the-chest.org.uk ↗ . The project reference for the opportunity is DN797010.

The contracting authority reserves the right to rely on section 31 PA 2023 to modify the terms of the procurement.

How it was run

Official notice
Run through: ProContract (Due North) · Who buys & how to bid on ProContract
Supplier login requiredElectronic submission allowedLanguage: EN
Access & registration note: Free · short registration with manual review; public opportunity list
Submission deadline
16 Mar 2026, 15:00 GMT
Clarification deadline
27 Jan 2026, 15:00 GMT
Submission channel
Official e-sourcing portal
Electronic submission
Allowed
Accepted languages
en
Detailed submission instructions & authority contactsFrom official release

The full tender pack can be accessed free of charge via The Chest procurement web portal at www.the-chest.org.uk ↗

Timeline

8 May 2025 → 1 Jul 2026 · 8 dates
  1. Planning notice published
    8 May 2025, 16:34 BST
  2. Market engagement
    28 May 2025, 23:59 BST

    There are two parts to this preliminary market engagement process, a Microsoft Teams presentation and a questionnaire to complete and return. All details and documents are made available via The Chest which can be accessed by the following link www.the-chest.org.uk ↗ The Chest reference for this PME is DN773969

    The Council will only be issuing and receiving documents for this PME via The Chest. Should you have any queries about this preliminary market engagement process, please send these via The Chest's Question and Answer section for a response.

  3. Tender notice published348 days ago
    12 Nov 2025, 15:46 GMT
  4. Clarification questions by273 days ago
    27 Jan 2026, 15:00 GMT
  5. Latest notice published256 days ago
    12 Feb 2026, 15:33 GMT
  6. Submission deadline225 days ago
    16 Mar 2026, 15:00 GMT
  7. Award decision expected by179 days ago
    30 Apr 2026, 23:59 BST
  8. Contract starts118 days ago
    1 Jul 2026, 00:00 BST

Notice history

12 events · 5 releases on Find a Tender · since 8 May 2025
  1. Preliminary market engagement notice published
    8 May 2025, 16:34 BST
    UK2
  2. Tender notice published
    12 Nov 2025, 15:46 GMT
    UK4
  3. Published value updated
    12 Nov 2025, 15:46 GMT
  4. Status changed to active
    12 Nov 2025, 15:46 GMT
  5. Procurement method changed
    12 Nov 2025, 15:46 GMT
  6. Deadline published: 9 Jan 2026, 20:00 GMT
    12 Nov 2025, 15:46 GMT
  7. Tender notice published
    20 Nov 2025, 18:03 GMT
    UK4
  8. Deadline moved to 20 Jan 2026, 22:00 GMT
    20 Nov 2025, 18:03 GMT
    +11 days · was 9 Jan 2026, 20:00 GMT
  9. Tender notice published
    22 Dec 2025, 16:25 GMT
    UK4
  10. Deadline moved to 20 Feb 2026, 22:00 GMT
    22 Dec 2025, 16:25 GMT
    +31 days · was 20 Jan 2026, 22:00 GMT
  11. Tender notice published
    12 Feb 2026, 15:33 GMT
    UK4
  12. Deadline moved to 16 Mar 2026, 15:00 GMT
    12 Feb 2026, 15:33 GMT
    +24 days · was 20 Feb 2026, 22:00 GMT
Published amendments (1)

The deadline date for submission of initial tenders has been extended from 9th January 2026 at 20:00 to 20th January 2026 22:00.

Routine re-releases (5)
  • 2025-11: 1 release · 12 Nov 2025
  • 2025-05: 1 release · 8 May 2025

Contracting authority & participating public bodies

Halton Borough Council

Contracting authorityPublic authority - sub-central government GB-PPON: PLTJ-1788-CBLR Municipal Building, Widnes, North West, WA8 7QFContact email

Official documents & specifications (6)

Official links; attachments are not copied

Tender pack and attachments

  • Bidding documents and specificationstenderBidding documents and specificationsThe full access of the tender pack is available free of charge on The Chest procurement web portal at www.the-chest.org.uk Reference number DN797010.

Notices published for this procedure

  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender
  • Preliminary market engagement notice planningPreliminary market engagement noticeUK2Preliminary market engagement notice on Find a Tender