Derby Etches Park Depot Enhancement Works Project

Official notice

Authority: ABELLIO EAST MIDLANDS LIMITED

WorksNegotiated procedure with prior call for competition
Budget not disclosedValue not published
Submissions closed 30 Apr 2021awarded 12 Jan 2022
Contract term Ends 31 Oct 2022
Notice summaryFrom the published notice

This Notice has been produced to confirm the Contract Award for the design and build (GRIP5 to GRIP8) of various operational enhancements at East Midlands Railways (EMR) Derby Etches Park Depot North Shed. The Depot enhancement works required result from the introduction of EMR's new Hitachi BMU fleet of trains, due to enter service in January 2023, which underpin EMR's commitment to delivering improved services to its customers. The Depot enhancement works required result from the introduction of East Midlands Railway's (EMR) new Hitachi BMU fleet of trains, due to enter service in January 2023, which underpin EMR's commitment to delivering improved services to its customers. Reception Roads Enhancements to four fuel roads to include CET, AdBlue, potable water, flushing water and fuelling to decrease the servicing time of the fleet to a maximum of 20 minutes per train set, and including a service gantry and weather apron.

What is being bought

Published requirement description

This Notice has been produced to confirm the Contract Award for the design and build (GRIP5 to GRIP8) of various operational enhancements at East Midlands Railways (EMR) Derby Etches Park Depot North Shed.

The Depot enhancement works required result from the introduction of EMR's new Hitachi BMU fleet of trains, due to enter service in January 2023, which underpin EMR's commitment to delivering improved services to its customers.

CPV: Railway depot construction work

The lotProcurement structure

single lot · no lot value published
Lot #1The Depot enhancement works required result from the introduction of East Midlands…Awarded

The Depot enhancement works required result from the introduction of East Midlands Railway's (EMR) new Hitachi BMU fleet of trains, due to enter service in January 2023, which underpin EMR's commitment to delivering improved services to its customers.

This Project requires the Design and Build (GRIP5 to GRIP8) of various operational enhancements at EMR's Derby Etches Park Depot North Shed and are summarised below;

Stabling Roads

Construction of two new buffer stopped stabling roads (with associated walking routes and lighting) and one OLE traction test through road.

Reception Roads Enhancements to four fuel roads to include CET, AdBlue, potable water, flushing water and fuelling to decrease the servicing time of the fleet to a maximum of 20 minutes per train set, and including a service gantry and weather apron.

Depot Protection

Design and installation of a new depot protection and signalling system to provide safe entry and exit to and from the Fuel Roads.

North Shed

Extension to the existing maintenance shed to accommodate one 5-car Hitachi BMU train with associated M&E, civils, exhaust extraction system, overhead crane, pitted road and loading bay. Additional enhancements to existing maintenance shed including two inspection gantries, exhaust extraction system and upgrades to shore

supplies.

Shore Supplies

Installation of five electrical shore supplies - one in the North Shed extension and four externally within the depot, including new substation and associated supplies.

Power Supply to OLE

Design and construction of new electrical substation and associated

supply to feed new OLE traction test track (new incoming DNO supply to be provided by East Midlands Railway)

Loading Bay Access Road

Construction of a new access road into North Shed extension, passing over three operational railroads.

During the Design and Build phases of all work to be undertaken, the entire Depot will and must remain fully operational at all times.

Contract period: … – 31 Oct 2022
Delivery: East Midlands
Variant bids: allowed

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
Conditions of participation1
  • Suitability

    All interested parties responding to this Notice must have the following to be considered further:-

    RISQS accredited (Railway Industry Supplier Qualification Scheme)

    Valid Railway Safety Case

    Alcumus SafeContractor accredited

Procedure terms & legal framework

From the official record · publisher note attached
Procedure method
Negotiated procedure with prior call for competition
Legal basis
CELEX · 32014L0025 Utilities Contracts Regulations 2016 (Directive 2014/25/EU)
Procurement category
Works
Notice status
Awarded
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
No (one-off requirement)
First published
19 Mar 2021, 10:52 GMT
Last source update
28 Mar 2022, 14:36 BST
FTS notice number
2022/S 000-008299
Classification (CPV)
Railway depot construction work
Delivery area
East Midlands (UKF1)
Official registry OCID
ocds-h6vhtk-029d54 Find a Tender

Publisher note: To register your interest in this Notice you should submit an expression of interest to the contact details shown within this Notice and request a copy of the Prequalification Questionnaire to be submitted by the date shown at IV.2.2 The Utilities Contracts Regulations 2016 ("Regulations") do not in accordance with their terms apply to this procurement. Neither the issue of this Invitation to Negotiate (as amended by East Midlands Railway and notified to Bidders from time to time) (the ITN) nor the selection of any Bidder, nor any other document, contact or conduct in connection with this ITN constitutes any acceptance by East Midlands Railway that the Regulations apply to the Project covered by this ITN or an agreement by East Midlands Railway to abide by those Regulations. The procurement process as described in this document (the ITN Process) and any subsequent contract awarded will be subject to English law and the exclusive jurisdiction of the English courts. By participating in the ITN Process a Bidder agrees to be bound by the above conditions and limitations. This Important Notice must be read in conjunction with all instructions to Bidders contained within this document. Bidder means each legal entity issued with an ITN and invited to participate in this ITN Process.

How it was run

Official notice
Submission deadline
30 Apr 2021, 16:00 BST
Submission channel
{"written"}
Accepted languages
en
Participation fee
document
Bid validity
180 days from the deadline

Timeline

30 Apr 2021 → 28 Mar 2022 · 2 dates
  1. Submission deadline
    30 Apr 2021, 16:00 BST
  2. Notice published
    28 Mar 2022, 14:36 BST

Notice history

2 events · 2 releases on Find a Tender · since 28 Mar 2022
  1. Status changed to complete
    28 Mar 2022, 14:36 BST
  2. Buyer details updated
    28 Mar 2022, 14:36 BST

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Contracts signed 1latest 12 Jan 2022

1 further award records carry no date or value.

Contracts

  • Contract 008299-2022-1 · supplier not published

    Signed
    12 Jan 2022
    Value
    —
    Period
    … – 31 Oct 2022
    Status
    active

Contracting authority & participating public bodies

ABELLIO EAST MIDLANDS LIMITED

Contracting authorityRailway services 2nd Floor St Andrew's House, 18-20 St Andrew Street, LONDON, East Midlands, EC4A 3AGContact email
Process and specification contact points (1)
  • FPA Consulting LimitedProcess contact point Derby, East MidlandsContact name, email, phone

Official documents & specifications

Official links; attachments are not copied

No document links were published on the notice.