Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Torbay Council: "Deed of Variation to Lease for Riviera International Conference Centre". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Torbay Council | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Torbay Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Torbay Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Average Price Reduction
Not availableInsufficient comparable data
Competition Density
3.8Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 41 active published awards; 32 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Price reduction compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityTorbay Council | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published12 Jan 2021, 12:44 GMT | Last source update12 Jan 2021, 12:44 GMT | Recurring procurementNot published |
ClassificationArchitectural, construction, engineering and inspection services, Hotel, restaurant and retail trade services, Recreational, cultural and sporting services | ||
Delivery area | ||
OCIDocds-h6vhtk-028991 | ||
What is being bought
On 25 July 2019 Torbay Council awarded a lease for the operation of the Riviera International Conference Centre (RICC) to Parkwood Leisure Ltd, with the intention that Parkwood Leisure Ltd would take over operation of the RICC on 01 April 2020. This notice relates to changes in the lease arrangements which were not included in the original procurement and that have been brought about as a direct result of the impact of the COVID-19 pandemic.
What changed
From the official release history
- Status changed to complete
12 Jan 2021, 12:44 GMT - Official notice release published
12 Jan 2021, 12:44 GMT - Buyer information updated
12 Jan 2021, 12:44 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedStatus not publishedPublished valueNot publishedOn 25 July 2019 Torbay Council awarded a lease for the operation of the Riviera International Conference Centre (RICC) to Parkwood Leisure Ltd, with the intention that Parkwood Leisure Ltd would take over operation of the RICC on 01 April 2020. In March 2020, the Council and Parkwood Leisure Ltd had a completed lease in readiness for signing ahead of the 1st April 2020; setting out all the commercial terms along with the capital investment to be delivered in 2020 and 2021. Due to restrictions imposed in response to the pandemic the RICC was closed and signing of the lease was deferred until such time as it could be agreed by both parties that Parkwood Leisure Ltd could take over its operation. The Council and Parkwood Leisure Limited have agreed that the originally proposed twenty five year lease will go ahead from 01 April 2021 and this will remain the basis for the medium to long term future of this partnership. However, in order to capture and address the impact of Covid-19 the Council intends to enter into a short term deed of variation with Parkwood Leisure Ltd, subject to approval through the Council budget setting process. This deed of variation will cover a financial support package that will be in place for the first twenty four months of the lease, which will be capped at approximately £830,000. This funding is being provided to enable Parkwood Leisure Ltd to move the RICC from the deficit position that has been created during the pandemic, in order to ensure the long term sustainability and viability of the business. It is expected that the support package will be made through the payment of a fixed fee quarterly in advance.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
12 Jan 2021, 12:44 GMT - Award active
Not published · Not published - Contract active
Signed 3 Dec 2020, 00:00 GMT · £830,000
Commercial outcome and competition
Awards Parkwood Leisure Ltd Not published · Not published · active |
Contracts Deed of Variation to Lease for Riviera International Conference Centre £830,000 · signed 3 Dec 2020, 00:00 GMT · active |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
Torbay Council
Contracting authority GB-FTS-398Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleThe Council and Parkwood Leisure Ltd were in the process of finalising the lease when the first national COVID-19 lockdown commenced. In accordance with government guidance the RICC ceased operation whilst restrictions were in place. Due to uncertainty of the date for re-opening and the cancellation of booked conferences/events signing of the lease was stalled. In June 2020 the Council assumed responsibility for the RICC management company to provide some surety for staff, whilst options for the RICC’s future were explored:
1) Parkwood Leisure Ltd take over the lease and commence operating the RICC with the addition of a short term agreement to provide funding to support recovery. Parkwood Leisure Ltd.'s tender submission provided a sound basis for negotiation, offering an expedient solution and reducing risk to staff and the business.
2) Retender for an operator. Market uncertainty in relation to post COVID-19 recovery and timescales for putting new arrangements in place would increase the risk to staff, extend the time for the RICC to recover and impact on the local economy.
3) Council continue to manage the RICC. The Council’s lack of experience and expertise in this specific area would increase the risk to staff, extend the time for the RICC to recover and impact on the local economy
4) Close the RICC. This would put all of the staff at RICC at risk and have a significant/long term impact on the local economy.
Options 2 and 3 would be further considered should agreement with Parkwood Leisure Ltd not be reached.
The Council entered into negotiation with Parkwood Leisure Ltd on the basis set out in II.2.4 above. Subject to the outcome of the negotiations and approval through Council governance processes, the Council intends to enter into a short term agreement with Parkwood Leisure Ltd, with a view to moving to a lease only arrangement once recovery has been established. The Council would enter into agreement under clauses 2(b)(ii) and 2(c) of Article 32 Use of the negotiated procedure without prior publication of Directive 2014/24/EU. The justification under clause 2(b)(ii) is that Parkwood Leisure Ltd was the successful economic operator under a Competitive Dialogue Procedure as outlined within Article 30 of the Directive (2014/24/EU) and implemented in the UK by The Public Contracts Regulations 2015 (SI 2015/102). The Council received two bids through this tender process, the second bid being rejected as non-compliant. This meant Parkwood Leisure Ltd was the only credible option in terms of enabling the re-opening of the RICC in a timely manner, minimising the risk of job losses or complete closure of the site. They have a sound track record in operating similar facilities and demonstrated through the procurement process and subsequent renegotiation that they are in a position to take on operation of the site within a reasonable timescale. The justification under clause 2(c) is that neither the Council nor Parkwood Leisure Ltd could have foreseen the outbreak of Coronavirus or the impact it would have on all aspects of everyday life. The Council had undertaken a compliant procurement process to appoint Parkwood Leisure Ltd, but the requirement to close the RICC and uncertainty around timescales for re-opening have impacted on their business plan for the site. The closure will result in a significant reduction in income including future conference bookings, putting at risk the ability for any organisation to effectively operate the RICC, resulting in its closure and loss of jobs for all staff. This risk would increase with any delay in reaching an agreement with an economic operator to take on the lease. The RICC plays a significant role in the visitor/tourism economy of Torbay and its effective operation is vital to rebuilding that economy. To safeguard as many jobs as possible and support the local economy through operating the RICC, the Council considers there is an urgent need to commence rebuilding the business. |