Find a Tender
complete
Official procurement procedure
Contract for the development of an Intermediate Care Centre
Construction work
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: GATESHEAD COUNCIL: "Contract for the development of an Intermediate Care Centre". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | GATESHEAD COUNCIL | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: GATESHEAD COUNCIL
Market Analytics
Derived from OCDS awards & bid statistics
Published history for GATESHEAD COUNCIL. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
6.6Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 66 active published awards; 64 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityGATESHEAD COUNCIL | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published10 Aug 2021, 15:16 BST | Last source update10 Aug 2021, 15:16 BST | Recurring procurementNot published |
ClassificationConstruction work | ||
Delivery area | ||
OCIDocds-h6vhtk-02986f | ||
What is being bought
Award of a Public Works contract under Regulation 32(2) (b) (iii) of the Public Contract Regulations 2015 for the development of a single site, purpose built intermediate care centre in Gateshead at Gretna Terrace, Gateshead NE10 0BS. The public works
contract will be delivered on a turn-key basis (including fixtures and fittings) to enable the Council to transfer its intermediate care provision from its existing 3 centres to a single
purpose-built site. The Negotiated Procedure without Prior Publication was followed and is justified under Regulation 32 (2) (b) (iii)
What changed
From the official release history
- Official notice release published
10 Aug 2021, 15:16 BST - Status changed to complete
4 Mar 2021, 16:46 GMT - Official notice release published
4 Mar 2021, 16:46 GMT - Buyer information updated
4 Mar 2021, 16:46 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedThe Council currently operates its intermediary care provision across 3 centres but there is a need to move the provision to a fit for purpose, single site care provision to ensure that the needs of the population are met now and for future years to come. The fundamental considerations for the location of a single site centre were both its proximity to the Queen Elizabeth Hospital, Gateshead and having good transport links for family and carers to get to, to visit loved ones. Therefore, the location requirement was for the new intermediary care centre to be located within a 1-mile radius of the Queen Elizabeth Hospital. The delivery of a timely development is required to enable the existing intermediate care provision to transfer to a fit for purpose development, which will deliver essential savings. It was a requirement for the new centre to be within very close proximity to a primary school to enable an essential intergenerational activity programme that is currently ran within an existing intermediate care centre to continue at the new centre. The Negotiated Procedure without Prior Publication has been followed and was justified under Regulation 32 (2) (b) (iii) for the award of a public works contracts for development of an intermediate care centre at Gretna Terrace, Gateshead NE10 0BS. The development site meets the Council's fundamental location requirements being within the 1-mile radius of the Queen Elizabeth Hospital, Gateshead with good transport links. The Works could only be supplied by a particular economic operator due to their exclusive rights as landowner of the development site. A timely delivery of the development can be met because the site is cleared, has planning permission in place and will be delivered on a turn-key basis. There were no reasonable alternative or substitute development sites within the desired location that could meet the delivery timescales.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
10 Aug 2021, 15:16 BST - Award active
Not published · Not published - Contract active
Signed 19 Jul 2021, 00:00 BST · £8,259,300
Commercial outcome and competition
Awards Leamside Estates Limited Not published · Not published · active |
Contracts Contract £8,259,300 · signed 19 Jul 2021, 00:00 BST · active |
Bid statistics bids: 1 (lot 1) |
Buyer and organisations in this procedure
GATESHEAD COUNCIL
Contracting authority GB-FTS-7372Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleThe Works could only be supplied by a particular economic operator due to their exclusive rights as landowner of the
development site which meets the Councils fundamental requirements of location being within the 1-mile radius of the Queen Elizabeth Hospital, Gateshead. The requirement of a
timely delivery can be met because the site is cleared and has planning permission in place. The development site is also adjacent to Falla Primary School to enable the intergenerational
activity programme to be delivered within the new centre. There were no reasonable alternative or substitute development sites, with planning permission within the desired location which would be suitable for the development of an intermediate care centre. |