Official UK procurement notice
Constructability Advice · UK public procurement notice
Authority: Anglian Water Services (Public body)
What is being bought3 lots · detail below
Published requirement descriptionThis notice is for the provision of constructability consultancy services.
Anglian Water is looking to put in place a framework of up to 15 suppliers who can provide constructability advice for various projects within the Anglian Water business, including the Strategic Resource Options (SRO) Reservoir programme.
The framework will be made up of three lots:
- Civil engineering and earthworks
- Pipelines
- Water Treatment
The full scoping document can be found within the Scanmarket link.
CPV: Civil engineering consultancy services
How this framework works
From the published notice- Places
- up to 15 suppliers
Lots and requirements (3)Procurement structure
3 lots · no lot values published · win at most 3 of themLot #1Civil Engineering and Earthworks
We are looking to put in place a framework agreement with a maximum of 5 contractors per lot, who can provide constructability advice on a number of our projects, including the Strategic Resource Option (SRO) Reservoir programme.
We have split the framework into three specialist lots. Lot 1 is for suppliers who can provide advice on civil engineering and earthworks.
What we mean by civils engineering and earthworks is described below:
All civils structures associated with the construction and operation of storage and service reservoirs for water supply, including dams, inlets, draw off facilities/outlet towers, pumping stations and emergency drawdowns and the construction of supporting infrastructure to enable the reservoir and wider development, including road construction, road improvements, rail heads, small ports and docks, aggregate/rock processing and handling facilities, quarrying, new service provision, existing service diversion and all construction logistics associated with the above. This will include for the excavation, transport, placement, and compaction of fill materials to construct earth structures, associated earthworks to optimise cut and fill balances, cutting of new waterways, dredging of existing waterways and raising or construction of flood embankments within the reservoir site area and along open channel transfers (existing waterways).
While the scope of services may vary from project to project, some anticipated services include the following:
- Critical review of design and assurance of constructability through to commissioning turnovers and to operations, including providing advice on buildability and construction sequence/ methodology and identification of temporary construction requirements.
- Input into the selection of the preferred options for the key construction and building systems - structures, Mechanical, Electrical and Plumbing (MEP), facades, etc to suit the supply chain, including materials, plant and equipment and bulk material storage, movement/transfer, and disposal.
- Market-based estimating, construction planning and scheduling.
- Provide advice on opportunities for Modern Methods of Construction (MMC)/ off-site fabrication/ modular building, etc. and quality control, assurance, and oversight methods.
- Value management - provide advice on potential value engineering opportunities in the developing design.
- Provide market intelligence on UK construction supply-chain pipelines and advise on construction and supply-chain risks relating to the proposals, including inflation and material shortages / long-lead items and impacts of early procure vs warrantees. This information can then be captured and shared within the wider AW business to be able to understand the supply chain landscape in terms of potential issues that could affect Anglian Water and opportunities.
- Support with the identification of products, materials, methods, and initiatives to enable sustainability ambitions and targets to be realised, including zero carbon opportunities.
- Environmental mitigation validation and optioneering.
- Provide market intelligence and feedback on preferable contract types to adopt/use that will provide AW certainty and control over project constraints and outcomes.
- Provide critical friend support (industry peer review) to major projects throughout the life span of the project.
- Contributions to, and validation of, any planning-related documentation under the Town and Country Planning Act or the Development Consent Order process that requires construction input and critique, including but not limited to:
a) Code of Construction Practice
b) Construction Management Plan
c) Construction Environmental Management Plan
d) Traffic Management Plan
e) Social impact strategy
f) Sustainability Strategy
Lot #2Pipelines (Infrastructure)
We are looking to put in place a framework agreement with a maximum of 5 contractors per lot, who can provide constructability advice on a number of our projects, including the Strategic Resource Option (SRO) Reservoir programme.
We have split the framework into three specialist lots. Lot 2 is for suppliers who can provide advice on pipelines.
What we mean by pipelines (infrastructure) is described below:
All infrastructure for large diameter pipelines and long interconnectors, including the design, construction, commissioning, and operations of; open cut techniques, trenchless, drainage, welding, materials selection, production management, temporary commissioning infrastructure, water quality and process science including chlorine dosing, pumping stations and break tanks.
While the scope of services may vary from project to project, some anticipated services include the following:
- Critical review of design and assurance of constructability through to commissioning turnovers and to operations, including providing advice on buildability and construction sequence/ methodology and identification of temporary construction requirements.
- Input into the selection of the preferred options for the key construction and building systems - structures, Mechanical, Electrical and Plumbing (MEP), facades, etc to suit the supply chain, including materials, plant and equipment and bulk material storage, movement/transfer, and disposal.
- Market-based estimating, construction planning and scheduling.
- Provide advice on opportunities for Modern Methods of Construction (MMC)/ off-site fabrication/ modular building, etc. and quality control, assurance, and oversight methods.
- Value management - provide advice on potential value engineering opportunities in the developing design.
- Provide market intelligence on UK construction supply-chain pipelines and advise on construction and supply-chain risks relating to the proposals, including inflation and material shortages / long-lead items and impacts of early procure vs warrantees. This information can then be captured and shared within the wider AW business to be able to understand the supply chain landscape in terms of potential issues that could affect Anglian Water and opportunities.
- Support with the identification of products, materials, methods, and initiatives to enable sustainability ambitions and targets to be realised, including zero carbon opportunities.
- Environmental mitigation validation and optioneering.
- Provide market intelligence and feedback on preferable contract types to adopt/use that will provide AW certainty and control over project constraints and outcomes.
- Provide critical friend support (industry peer review) to major projects throughout the life span of the project.
- Contributions to, and validation of, any planning-related documentation under the Town and Country Planning Act or the Development Consent Order process that requires construction input and critique, including but not limited to:
a) Code of Construction Practice
b) Construction Management Plan
c) Construction Environmental Management Plan
d) Traffic Management Plan
e) Social impact strategy
f) Sustainability Strategy
Lot #3Water Treatment (Non-infrastructure)
We are looking to put in place a framework agreement with a maximum of 5 contractors per lot, who can provide constructability advice on a number of our projects, including the Strategic Resource Option (SRO) Reservoir programme.
We have split the framework into three specialist lots. Lot 3 is for suppliers who can provide advice on water treatment (non-infrastructure).
What we mean by water treament (non-infrastructure) is described below:
All operations associated with the design, construction, commissioning, handover, and operation of 150-300 MLD water treatment facilities, including water treatment works, wastewater treatment, INNS treatment and conditioning.
While the scope of services may vary from project to project, some anticipated services include the following:
- Critical review of design and assurance of constructability through to commissioning turnovers and to operations, including providing advice on buildability and construction sequence/ methodology and identification of temporary construction requirements.
- Input into the selection of the preferred options for the key construction and building systems - structures, Mechanical, Electrical and Plumbing (MEP), facades, etc to suit the supply chain, including materials, plant and equipment and bulk material storage, movement/transfer, and disposal.
- Market-based estimating, construction planning and scheduling.
- Provide advice on opportunities for Modern Methods of Construction (MMC)/ off-site fabrication/ modular building, etc. and quality control, assurance, and oversight methods.
- Value management - provide advice on potential value engineering opportunities in the developing design.
- Provide market intelligence on UK construction supply-chain pipelines and advise on construction and supply-chain risks relating to the proposals, including inflation and material shortages / long-lead items and impacts of early procure vs warrantees. This information can then be captured and shared within the wider AW business to be able to understand the supply chain landscape in terms of potential issues that could affect Anglian Water and opportunities.
- Support with the identification of products, materials, methods, and initiatives to enable sustainability ambitions and targets to be realised, including zero carbon opportunities.
- Environmental mitigation validation and optioneering.
- Provide market intelligence and feedback on preferable contract types to adopt/use that will provide AW certainty and control over project constraints and outcomes.
- Provide critical friend support (industry peer review) to major projects throughout the life span of the project.
- Contributions to, and validation of, any planning-related documentation under the Town and Country Planning Act or the Development Consent Order process that requires construction input and critique, including but not limited to:
a) Code of Construction Practice
b) Construction Management Plan
c) Construction Environmental Management Plan
d) Traffic Management Plan
e) Social impact strategy
f) Sustainability Strategy
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
- “Constructability Advice” is a framework: the contest is a place on its panel, up to 15 suppliers, not a single contract.
Procedure terms & legal framework
From the official record- Procedure method
- Negotiated procedure with prior call for competition
- Legal basis
- CELEX · 32014L0025 Utilities Contracts Regulations 2016 (Directive 2014/25/EU)
- Procurement category
- Services
- Notice status
- Closed
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- No (one-off requirement)
- First published
- 21 Feb 2024, 16:39 GMT
- Last source update
- 21 Feb 2024, 16:39 GMT
- Authority reference
2024-0946- FTS notice number
2024/S 000-005712- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-043beeFind a Tender
How it was run
Official notice- Appointment period ends
- 22 Mar 2024, 23:00 GMT
- Submission channel
- {"electronicSubmission"}
- Accepted languages
- en
Timeline
21 Feb 2024 → 22 Mar 2024 · 2 dates- Notice published21 Feb 2024, 16:39 GMT
- Admission / appointment period endsperiod end, not a bid countdown22 Mar 2024, 23:00 GMT
Contracting authority & participating public bodies
Dispute resolution & review bodies
- High CourtReview body
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.