Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Guy's and St Thomas' NHS Foundation Trust: "Condensate Water Pipework System - Quantity Surveyor". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
Contracting AuthorityGuy's and St Thomas' NHS Foundation TrustScope & CategoriesNot publishedSubmission Window
complete
No deadline published
Submission GatewayDirect notice routeLegal Basis & RegimeStandard procurementEstimated Value (exc. VAT)Not published
Bidder Intelligence · Authority Profile: Guy's and St Thomas' NHS Foundation Trust
Market Analytics
View Authority Profile →
Derived from OCDS awards & bid statistics
Published history for Guy's and St Thomas' NHS Foundation Trust. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Requires at least 5 comparable procedures
Competition Density
6.6Bids / Report
10% of reports have one bid
Supplier ConcentrationModerate Concentration
T-Safe UK LtdTop vendor: 35.4% of attributable value
Payment Terms
Check noticePublished terms
Payment obligations depend on the applicable regime and contract. Consult the official documents.
Coverage: 43 active published awards; 10 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Historical Awarded Suppliers With This Authority:
Supplier NameHistoric AwardsAttributable GBP Value
T-Safe UK Ltd1 win£290,513
CFES-Ltd1 win£160,296
Loates-Taylor Shannon (LTS) Architects1 win£160,000
ILLUMINA CAMBRIDGE LIMITED1 win£156,201
Oander1 win£37,000
Procedure terms
Procedure methodNot published
Procurement categoryNot published
Statuscomplete
Framework / DPSNot published
CompetitionNot published
Above thresholdNot published
Legal basisNot published
Tender period startsNot published
Clarification deadlineNot published
Electronic submissionNot published
Submission languagesNot published
Published25 Sept 2025, 15:39 BST
Last source update25 Sept 2025, 15:39 BST
Recurring procurementNot published
ClassificationNot published
Delivery areaLocation not published
OCIDocds-h6vhtk-05a25b
What is being bought
The project entails the replacement of existing Condenser Water pipework system with new. This pipework runs from the Ground to the 30th floor of Guy’s Tower. The project will need to be undertaken in two phases to ensure that cooling is available to the site at all times to the Hospital. The existing Condenser Water pipework provides the heat rejection for the existing Daikin Applied centrifugal chillers consisting of two 1.7 MW packaged centrifugal chillers reference 1A/1B (System 1) and one 3.4 MW packaged centrifugal chiller reference 2 (System 2) located within the Ground floor plantroom adjacent the main hospital entrance. The existing system is designed to allow for one system to operate at any one time, not two systems. Therefore, only one system can be worked on at any one time. A Condenser Water bypass is to be installed within the Ground Floor plantroom. This is to allow for example system 1 chiller to operate with system 2 system, and vice versa. The project is currently at stage 4 and estimates a 52-week construction phase.
What changed
From the official release history
  1. Status changed to complete
    25 Sept 2025, 15:39 BST
  2. Official notice release published
    25 Sept 2025, 15:39 BST
  3. Buyer information updated
    25 Sept 2025, 15:39 BST
Lots and requirements (1)
Published by the contracting authority
  • Lot 1 · #1
    Individual lot title not published
    complete
    Published valueNot published
    The source published no individual title or description for this lot.
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
Timeline
  1. Procedure published
    25 Sept 2025, 15:39 BST
  2. Award active
    8 Sept 2025, 00:00 BST · £37,000
Commercial outcome and competition
Awards
Oander
£37,000 · 8 Sept 2025, 00:00 BST · active
ContractsNo contract published
Bid statistics
bids: 5 (lot 1)
finalStageBids: 5 (lot 1)
smeFinalStageBids: 0 (lot 1)
vcseFinalStageBids: 0 (lot 1)
Buyer and organisations in this procedure

Guy's and St Thomas' NHS Foundation Trust

Contracting authority GB-PPON-PDZC-6438-DGPX
View buyer profile
  • Guy's and St Thomas' NHS Foundation Trust
    buyer

    GB-PPON: PDZC-6438-DGPX
    Great Maze Pond, London, UKI44, SE1 9RT, GB
  • Oander
    supplier

    2 Park Court, Pyrford Road, , Surrey,, West Byfleet, UKJ25, KT14 6SD, GB
Award and contract changes
Documents (0)
Official links; attachments are not copied
No data
No linked documents are published
Related procedures (0)
No data
No related procedures published