Official UK procurement notice
Britannia Phase 2b - Design & Build Contractor CPN
Authority: London Borough of Hackney (Local council)·Consortium: 2 public authorities
What is being bought
Published requirement descriptionMain contractor to deliver Phase 2b of the Britannia Masterplan on the site of the old Britannia Leisure Centre, Northport Street/Grange Street, London, N1 5FT.
CPV: Construction work
The lotProcurement structure
single lot · value publishedLot #1AwardedPublished value£120,000,000
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published award criteria (2)
- Quality: 60
- Price: 40
- Price carries 40 of 100 points: a 10% discount moves about 4 points. The method statement decides this lot, not the discount.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record · publisher note attached- Procedure method
- Competitive procedure with negotiation
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Works
- Notice status
- Awarded
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- No (one-off requirement)
- First published
- 21 Jun 2022, 10:57 BST
- Last source update
- 20 Nov 2023, 15:21 GMT
- Authority reference
DN609781- FTS notice number
2023/S 000-034296- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-03489fFind a Tender
- Review procedure
Tenderers who are unsuccessful shall be informed by the authority as soon as possible after the decision has been made as to the reasons why the tenderer was unsuccessful. A 10 day standstill period shall be observed prior to the entry into a contract by the relevant authority.
If an appeal regarding the award of the contract has not been successfully resolved, the Public Contracts Regulations 2015 (SI 2015 No 102) provide for aggrieved parties who have been harmed or are at risk of harm by breach of the rules to take legal action. Any such action must be brought within the applicable limitation period. Where a contract has not been entered into, the Court may order the setting aside of the award decision or order the authorities to amend any document and may award damages.
If the contract has been entered into, the Court may, depending on the circumstances, award damages, make a declaration of ineffectiveness, order the relevant authority to pay a fine and/or order that the duration of the contract be shortened.
The purpose of the standstill period referred to above is to allow the parties to apply to the Courts to set aside the award decision before the contract is entered into.
Publisher note: Britannia Phase 2b - Design & Build Contractor CPN
How it was run
Official notice- Submission deadline
- 21 Jul 2022, 12:00 BST
- Submission channel
- {"electronicSubmission"}
- Accepted languages
- en
Timeline
21 Jul 2022 → 20 Nov 2023 · 3 dates- Submission deadline21 Jul 2022, 12:00 BST
- Invitations to tender expected9 Aug 2022, 00:00 BST
- Notice published20 Nov 2023, 15:21 GMT
Notice history
2 events · 2 releases on Find a Tender · since 20 Nov 2023- Status changed to complete20 Nov 2023, 15:21 GMT
- Buyer details updated20 Nov 2023, 15:21 GMT
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| ARDMORE CONSTRUCTION GROUP LIMITED | £155,685,124 † | — | Awarded |
Contracts
Contract 034296-2023-1 · ARDMORE CONSTRUCTION GROUP LIMITED
- Signed
- 21 Jul 2023
- Value
- £155,685,124
- Period
- … – 23 Dec 2026
- Status
- active
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 2bids | — | — | — |
Contracting authority & participating public bodies
2 public bodies on the noticeDispute resolution & review bodies
- Public Procurement Review ServiceReview body
- The Public Procurement Review Service of the Cabinet OfficeReview contact point
- The Royal Courts of JusticeReview body
Bidders & participating suppliers
1 commercial party on the notice- ARDMORE CONSTRUCTION GROUP LIMITEDAwarded supplier