← Back to search results

ClosedFind a Tender · UK4

ABP Civils Framework

Buyer: ASSOCIATED BRITISH PORTS →

Participate on in-tendhost.co.uk ↗External submission platform

BuyerASSOCIATED BRITISH PORTS
StatusClosed
Deadline12 Dec 2025
Value£102,000,000
Published17 Nov 2025

What is being bought

ABP is looking to appoint suitably qualified contractors to our new Civils Framework. The ABP Civils Framework is designed to provide access to pre-qualified civil engineering contractors across the Humber, Southampton, South Wales and East Anglia. Its scope encompasses a wide range of low to mid value construction and maintenance works, structured to support both operational efficiency and Small to Medium size Enterprise (SME) participation. This Framework was shaped through extensive Applicant engagement, including Q&A sessions, face-to-face meetings, and questionnaires to refine the Lotting structure and address barriers to participation.

Categories

Construction work 45000000Site preparation work 45100000Works for complete or part construction and civil engineering work 45200000Resurfacing works 45233251Building installation work 45300000Building completion work 45400000Hire of construction and civil engineering machinery and equipment with operator 45500000

Lot details

Lot 1A - Humber - Minor Works

Lot 1A Humber - Minor Works (Estimated Individual Project Values £0 up to £250k)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 1B - Humber - Small Works

Lot 1B Humber - Small Works (Estimated Individual Project Values £250k up to £1.5M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 1C - Humber - Surfacing Works

Lot 1C Humber – Surfacing Works (Estimated Contract Value up to £1M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 2A - Southampton - Minor Works

Lot 2A Southampton - Minor Works (Estimated Individual Project Values £50k up to £500k)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 2B - Southampton - Small Works

Lot 2B Southampton - Small Works (Estimated Individual Project Values £500k up to £1.5M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 3A - South Wales - Minor Works

Lot 3A South Wales - Minor Works (Estimated Individual Project Values £0 up to £250k)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 3B - South Wales -Small Works

Lot 3B South Wales - Small Works (Estimated Individual Project Values £250k up to £1.5M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 3C - South Wales - Surfacing Works

Lot 3C South Wales – Surfacing Works (Estimated Contract Value up to £1M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 4A - East Anglia - Minor Works

Lot 4A East Anglia - Minor Works (Estimated Individual Project Values £0 up to £250k)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 4B - East Anglia - Small Works

Lot 4B East Anglia - Small Works (Estimated Contract Value £250k up to £1.5M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 4C - East Anglia – Surfacing Works

Lot 4C East Anglia – Surfacing Works (Estimated Contract Value up to £1M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 5 - National Intermediate Works

Lot 5 National Intermediate Works (Estimated Individual Project Values £1.5M up to £4M)

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

Lot 6 - General Inclusion

Lot 6 - General Inclusion Lot

Statusactive
Value£0
Contract periodFrom 20 Apr 2026 to 19 Apr 2031
SME suitabilitySuitable for SMEs

Award criteria
Simple description — The following information summarises the approach to evaluating and scoring the Applicants PSQ response. Initial Compliance Check ABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected. Provided for information only and not scored A number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided. Mandatory Pass / Fail sections A number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage. The sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document Scored and weighted sections Only those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. The sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document.

What is included

ItemCategoryQuantity
1Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
2Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
3Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
4Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
5Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
6Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
7Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
8Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
9Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
10Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
11Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
12Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published
13Construction work, Site preparation work, Works for complete or part construction and civil engineering work, Resurfacing works, Building installation work, Building completion work, Hire of construction and civil engineering machinery and equipment with operatorNot published

Comparable-procurement analytics

Benchmarked against retained Find a Tender procedures with CPV division 45. The category anchor is Construction work (45000000); this is a deliberately broad market comparator. The comparison is shown at several levels rather than pretending one company or region is always the best benchmark.

Comparison setProceduresReported bids per procedureNamed award suppliersPrice evidence
Market: CPV division 4517,1314 median · 30.2 average (5,652 of 17,131 with a bid count)3.8 average (6,249 of 17,131 with named award suppliers)Not published
Same buyer6Not publishedNot publishedNot published
Similar published value (0.5×–2×)5293 median · 75.8 average (8 of 529 with a bid count)7.6 average (8 of 529 with named award suppliers)Not published

“Reported bids” is an official aggregate, sometimes reported per lot; it is the closest available competition measure. “Named award suppliers” are winners, not all applicants.

Price-outcome signal

Not enough comparable procedures currently publish both a GBP tender value and a usable lowest-valid-bid value to calculate a responsible price-reduction benchmark. Tenderline deliberately does not infer a saving from named award suppliers or from missing award values.

Procurement strategy & market signals

Framework agreementYes
Dynamic purchasing systemNot published
Competitive procurementNot published
Recurring requirementNot published
Procurement method rationaleNot published
Rationale classificationsNot published
Special regimeutilities
Covered byNot published
Submission policyallowed
Selection criteriaNot published
Risk detailsNot published

Planning & early market engagement

BudgetNot published
No-engagement rationaleNot published
Planning documents0
Planning milestones0

No planning milestones published.

Related procurements

No linked framework, prior procurement or reprocurement published.

Documents & submission route

Source data inventory

Diagnostic view. “Not published” means this current release does not provide a value.

OCIDocds-h6vhtk-05e2a2
Latest release ID074463-2025
Latest release timestampMon Nov 17 2025 15:17:08 GMT+0000 (Coordinated Universal Time)
Sourcefind-a-tender
Official notice URLhttps://www.find-tender.service.gov.uk/Notice/074463-2025
Tender statusactive
Procurement methodselective
Procurement method detailsCompetitive flexible procedure
Main procurement categoryworks
Above thresholdYes
Legal basis2023/54
Tender period: startNot published
Tender period: endNot published
Expression of interest deadline2025-12-12T12:00:00+00:00
Enquiry deadline2025-11-28T17:00:00+00:00
Award period: startNot published
Award period: end2026-03-31T23:59:59+01:00
Submission method detailshttps://in-tendhost.co.uk/abp/aspx/Tenders/Current
Submission languagesen
Electronic catalogue policyNot published
Total tender value£102,000,000
Tender lots in source13
Tender items in source13
Tender documents in source2
Awards in latest release0
Contracts in latest release0
Parties in latest release1

Notice history

DateEventReference
17 Nov 2025tender074463-2025

All source data

Unmodified official OCDS data retained by Tenderline for this procurement process.

Complete current OCDS release JSON
{
  "id": "074463-2025",
  "tag": [
    "tender"
  ],
  "date": "2025-11-17T15:17:08Z",
  "ocid": "ocds-h6vhtk-05e2a2",
  "buyer": {
    "id": "GB-COH-ZC000195",
    "name": "ASSOCIATED BRITISH PORTS"
  },
  "tender": {
    "id": "INF-GRP-25/1170",
    "lots": [
      {
        "id": "1",
        "title": "Lot 1A - Humber - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 1A\tHumber - Minor Works (Estimated Individual Project Values £0 up to £250k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "2",
        "title": "Lot 1B - Humber - Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 1B\tHumber - Small Works (Estimated Individual Project Values £250k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "3",
        "title": "Lot 1C - Humber - Surfacing Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 1C\tHumber – Surfacing Works (Estimated Contract Value up to £1M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "4",
        "title": "Lot 2A - Southampton - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 2A\tSouthampton - Minor Works (Estimated Individual Project Values £50k up to £500k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "5",
        "title": "Lot 2B - Southampton - Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 2B\tSouthampton - Small Works (Estimated Individual Project Values £500k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "6",
        "title": "Lot 3A -\tSouth Wales - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 3A\tSouth Wales - Minor Works (Estimated Individual Project Values £0 up to £250k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "7",
        "title": "Lot 3B - South Wales -Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 3B\tSouth Wales - Small Works (Estimated Individual Project Values £250k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "8",
        "title": "Lot 3C - South Wales - Surfacing Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 3C\tSouth Wales – Surfacing Works (Estimated Contract Value up to £1M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "9",
        "title": "Lot 4A - East Anglia - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 4A\tEast Anglia - Minor Works (Estimated Individual Project Values £0 up to £250k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "10",
        "title": "Lot 4B - East Anglia - Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 4B\tEast Anglia - Small Works (Estimated Contract Value £250k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "11",
        "title": "Lot 4C - East Anglia – Surfacing Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 4C\tEast Anglia – Surfacing Works (Estimated Contract Value up to £1M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "12",
        "title": "Lot 5  - National Intermediate Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 5 \tNational Intermediate Works (Estimated Individual Project Values £1.5M up to £4M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "13",
        "title": "Lot 6 - General Inclusion",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 6 - General Inclusion Lot",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      }
    ],
    "items": [
      {
        "id": "1",
        "relatedLot": "1",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "2",
        "relatedLot": "2",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "3",
        "relatedLot": "3",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "4",
        "relatedLot": "4",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "5",
        "relatedLot": "5",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "6",
        "relatedLot": "6",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "7",
        "relatedLot": "7",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "8",
        "relatedLot": "8",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "9",
        "relatedLot": "9",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "10",
        "relatedLot": "10",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "11",
        "relatedLot": "11",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "12",
        "relatedLot": "12",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "13",
        "relatedLot": "13",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      }
    ],
    "title": "ABP Civils Framework",
    "value": {
      "currency": "GBP",
      "amountGross": 102000000
    },
    "status": "active",
    "documents": [
      {
        "id": "conflictOfInterest",
        "description": "Not published",
        "documentType": "conflictOfInterest"
      },
      {
        "id": "074463-2025",
        "url": "https://www.find-tender.service.gov.uk/Notice/074463-2025",
        "format": "text/html",
        "noticeType": "UK4",
        "description": "Tender notice on Find a Tender",
        "documentType": "tenderNotice",
        "datePublished": "2025-11-17T15:17:08Z"
      }
    ],
    "procedure": {
      "features": "The two-stage process is as described below:\nStage 1 PSQ\nThe Applicant is issued with a PSQ including instructions to Applicants, Requirements and a set of qualitative questions which are to demonstrate the Applicant’s:\n•\tCompliance\n•\tFinancial Capability\n•\tLegal Capability\n•\tHealth & Safety Approach\n•\tQuality Approach\n•\tSupply Chain Approach\n•\tQuality Approach\n•\tTechnical Capability and Experience\nCompleted PSQ should be submitted strictly in accordance with the instructions to Applicants described within the PSQ document and received by ABP no later than 12/12/2025 at 12:00 GMT.\nFor the avoidance of doubt, the Applicants are required to submit all documents requested to be included in all sections of the PSQ Response Document attached in Appendix 04 – PSQ Response Document to enable their PSQ submissions to be fully evaluated against the evaluation criteria. The evaluation criteria are also provided within the PSQ Response Document.\nStage 2 – Invitation to Tender (ITT)\nFollowing the conclusion of Stage 1 PSQ, down – selected Applicants will be invited to participate in the second stage of the process.\nStage 2 will comprise the issuing of the ITT to the successful down-selected applicants for each geographical Lot and sub Lot.\nClear objectives and evaluation criteria aligned to strategic goals will be included in the tender documents, inviting Applicants to demonstrate how their proposals will deliver broader organisational benefits.\nFollowing this stage, ABP will award Contract/s based on the Most Advantageous Tender, based on the evaluation criteria."
    },
    "legalBasis": {
      "id": "2023/54",
      "uri": "https://www.legislation.gov.uk/ukpga/2023/54/contents",
      "scheme": "UKPGA"
    },
    "techniques": {
      "frameworkAgreement": {
        "type": "closed",
        "method": "withAndWithoutReopeningCompetition",
        "description": "ABP will have the option to call-off contracts or engage in mini-competitions under the Framework Agreement with individual Applicants as and when services are required.  Please note however that there is no obligation for ABP to call off from the Framework Agreement (i.e. ABP may appoint work to parties outside of the Framework Agreement if necessary). \nLots 1A, 3A, 4A & 1C, 3C & 4C \nFor Lots 1A, 3A, 4A & 1C, 3C & 4C, any work awarded will use the NEC4 Term Service Contract and individual Task Orders will be issued accordingly by the Service Manager to instruct specific items of work within the scope of the contract. The schedule of rates submitted at tender stage will be used as the basis for pricing all Task Orders. \nLots 1B, 2B, 3B, 4B & Lot 5\nFor Lots 1B, 2B, 3B, 4B & Lot 5, work will be awarded in two ways; firstly, the results of a mini-competition with either price or price/quality being the assessment criteria. This will be defined during the publication of each individual request for quotation (Call off contract); or secondly, through a direct award. ABP reserves the right to make an award to any Contractor it feels will provide the required works most effectively.\nWork will be awarded through the framework using Work Orders (in line with the NEC4 Framework Contract). Each Work Order will be accompanied by an NEC4 Engineering & Construction Contract signed as a deed for Lots 1B, 2B, 3B, 4B & Lot 5.\nLot 2A \nFor Lot 2A, the work awarded will use the JCT Measured Term Contract. Each call-off will be instructed by the Employer under the agreed schedule of rates, ensuring transparency and consistency in pricing. This approach provides flexibility for recurring tasks while maintaining contractual certainty and compliance with JCT terms. \nCall of Procedures\nABP ultimately reserves the right, at its sole discretion, to utilise any of the following call-off procedures under the framework agreement, this applies to all Lots:\nMini-Competition\nA competitive process where all eligible Applicants on the Lot are invited to submit bids for a specific requirement. Evaluation is based on the criteria set out in the mini-competition documentation.\nDirect Award Procedure\nABP may award a contract directly to a Applicant without further competition. This is typically used where there is an urgent requirement or a clear best-fit Applicant."
      },
      "hasFrameworkAgreement": true
    },
    "awardPeriod": {
      "endDate": "2026-03-31T23:59:59+01:00"
    },
    "description": "ABP is looking to appoint suitably qualified contractors to our new Civils Framework.\nThe ABP Civils Framework is designed to provide access to pre-qualified civil engineering contractors across the Humber, Southampton, South Wales and East Anglia. Its scope encompasses a wide range of low to mid value construction and maintenance works, structured to support both operational efficiency and Small to Medium size Enterprise (SME) participation.\nThis Framework was shaped through extensive Applicant engagement, including Q&A sessions, face-to-face meetings, and questionnaires to refine the Lotting structure and address barriers to participation.",
    "enquiryPeriod": {
      "endDate": "2025-11-28T17:00:00+00:00"
    },
    "specialRegime": [
      "utilities"
    ],
    "aboveThreshold": true,
    "submissionTerms": {
      "languages": [
        "en"
      ],
      "electronicSubmissionPolicy": "allowed"
    },
    "procurementMethod": "selective",
    "mainProcurementCategory": "works",
    "submissionMethodDetails": "https://in-tendhost.co.uk/abp/aspx/Tenders/Current",
    "procurementMethodDetails": "Competitive flexible procedure",
    "expressionOfInterestDeadline": "2025-12-12T12:00:00+00:00"
  },
  "parties": [
    {
      "id": "GB-COH-ZC000195",
      "name": "ASSOCIATED BRITISH PORTS",
      "roles": [
        "buyer"
      ],
      "address": {
        "region": "UKI32",
        "country": "GB",
        "locality": "London",
        "postalCode": "WC2E 9ES",
        "countryName": "United Kingdom",
        "streetAddress": "25 Bedford Street"
      },
      "details": {
        "url": "https://in-tendhost.co.uk/abp/aspx/Tenders/Current",
        "classifications": [
          {
            "id": "privateUtility",
            "scheme": "UK_CA_TYPE",
            "description": "Private utility"
          }
        ]
      },
      "identifier": {
        "id": "ZC000195",
        "scheme": "GB-COH"
      },
      "contactPoint": {
        "name": "Daniel Murray",
        "email": "procurement@abports.co.uk"
      }
    }
  ],
  "language": "en",
  "initiationType": "tender"
}
Complete JSON history (1 releases)
17 Nov 2025 · 074463-2025 · tender
{
  "id": "074463-2025",
  "tag": [
    "tender"
  ],
  "date": "2025-11-17T15:17:08Z",
  "ocid": "ocds-h6vhtk-05e2a2",
  "buyer": {
    "id": "GB-COH-ZC000195",
    "name": "ASSOCIATED BRITISH PORTS"
  },
  "tender": {
    "id": "INF-GRP-25/1170",
    "lots": [
      {
        "id": "1",
        "title": "Lot 1A - Humber - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 1A\tHumber - Minor Works (Estimated Individual Project Values £0 up to £250k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "2",
        "title": "Lot 1B - Humber - Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 1B\tHumber - Small Works (Estimated Individual Project Values £250k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "3",
        "title": "Lot 1C - Humber - Surfacing Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 1C\tHumber – Surfacing Works (Estimated Contract Value up to £1M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "4",
        "title": "Lot 2A - Southampton - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 2A\tSouthampton - Minor Works (Estimated Individual Project Values £50k up to £500k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "5",
        "title": "Lot 2B - Southampton - Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 2B\tSouthampton - Small Works (Estimated Individual Project Values £500k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "6",
        "title": "Lot 3A -\tSouth Wales - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 3A\tSouth Wales - Minor Works (Estimated Individual Project Values £0 up to £250k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "7",
        "title": "Lot 3B - South Wales -Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 3B\tSouth Wales - Small Works (Estimated Individual Project Values £250k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "8",
        "title": "Lot 3C - South Wales - Surfacing Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 3C\tSouth Wales – Surfacing Works (Estimated Contract Value up to £1M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "9",
        "title": "Lot 4A - East Anglia - Minor Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 4A\tEast Anglia - Minor Works (Estimated Individual Project Values £0 up to £250k)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "10",
        "title": "Lot 4B - East Anglia - Small Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 4B\tEast Anglia - Small Works (Estimated Contract Value £250k up to £1.5M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "11",
        "title": "Lot 4C - East Anglia – Surfacing Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 4C\tEast Anglia – Surfacing Works (Estimated Contract Value up to £1M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "12",
        "title": "Lot 5  - National Intermediate Works",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 5 \tNational Intermediate Works (Estimated Individual Project Values £1.5M up to £4M)",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      },
      {
        "id": "13",
        "title": "Lot 6 - General Inclusion",
        "value": {
          "amount": 0,
          "currency": "GBP",
          "amountGross": 0
        },
        "status": "active",
        "renewal": {
          "description": "The proposed Framework Agreement will be in place for 5 years with a possible extension provision of 3 years, with the maximum duration to be 8 years. The framework will be extended at the discretion of the Authority at the end of year 5."
        },
        "hasRenewal": true,
        "description": "Lot 6 - General Inclusion Lot",
        "suitability": {
          "sme": true
        },
        "awardCriteria": {
          "criteria": [
            {
              "name": "Simple description",
              "type": "price",
              "description": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
            }
          ],
          "weightingDescription": "The following information summarises the approach to evaluating and scoring the Applicants PSQ response.\nInitial Compliance Check\nABP will undertake a compliance check of the information submitted (including checks on ABP’s compliance screening software). Failure to complete all relevant questions, failure to enclose supporting documentation or compliance concerns being flagged by ABP’s compliance screening software may result in the Applicant’s PSQ response being rejected.\nProvided for information only and not scored\nA number of sections of this PSQ which are to be returned with your submission are not scored and are supplied for ABP’s information only. However, these sections must be fully completed & all information required and requested must be provided.\nMandatory Pass / Fail sections\nA number of sections are PASS/FAIL criteria with either a mandatory PASS or discretionary PASS requirements. If you score a FAIL in any one of the sub-sections of the PSQ, the Applicant will not progress to the next stage. If you score a PASS in all of the sub-sections, your submission will progress to the full PSQ evaluation stage.\nThe sections that are evaluated using the mandatory PASS/FAIL criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document\nScored and weighted sections\nOnly those Applicants that have passed the “PASS/FAIL” criteria and provided the information in the “For Information only” sections will go on to be fully scored by the ABP Evaluation Team. \nThe sections that are to be evaluated using the below Scoring Criteria are clearly detailed in the PSQ Response Document contained within Appendix 04 - PSQ Response Document."
        },
        "contractPeriod": {
          "endDate": "2031-04-19T23:59:59+01:00",
          "startDate": "2026-04-20T00:00:00+01:00",
          "maxExtentDate": "2034-04-19T23:59:59+00:00"
        }
      }
    ],
    "items": [
      {
        "id": "1",
        "relatedLot": "1",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "2",
        "relatedLot": "2",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "3",
        "relatedLot": "3",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "4",
        "relatedLot": "4",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "5",
        "relatedLot": "5",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "6",
        "relatedLot": "6",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "7",
        "relatedLot": "7",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "8",
        "relatedLot": "8",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "9",
        "relatedLot": "9",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "10",
        "relatedLot": "10",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "11",
        "relatedLot": "11",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "12",
        "relatedLot": "12",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      },
      {
        "id": "13",
        "relatedLot": "13",
        "additionalClassifications": [
          {
            "id": "45000000",
            "scheme": "CPV",
            "description": "Construction work"
          },
          {
            "id": "45100000",
            "scheme": "CPV",
            "description": "Site preparation work"
          },
          {
            "id": "45200000",
            "scheme": "CPV",
            "description": "Works for complete or part construction and civil engineering work"
          },
          {
            "id": "45233251",
            "scheme": "CPV",
            "description": "Resurfacing works"
          },
          {
            "id": "45300000",
            "scheme": "CPV",
            "description": "Building installation work"
          },
          {
            "id": "45400000",
            "scheme": "CPV",
            "description": "Building completion work"
          },
          {
            "id": "45500000",
            "scheme": "CPV",
            "description": "Hire of construction and civil engineering machinery and equipment with operator"
          }
        ]
      }
    ],
    "title": "ABP Civils Framework",
    "value": {
      "currency": "GBP",
      "amountGross": 102000000
    },
    "status": "active",
    "documents": [
      {
        "id": "conflictOfInterest",
        "description": "Not published",
        "documentType": "conflictOfInterest"
      },
      {
        "id": "074463-2025",
        "url": "https://www.find-tender.service.gov.uk/Notice/074463-2025",
        "format": "text/html",
        "noticeType": "UK4",
        "description": "Tender notice on Find a Tender",
        "documentType": "tenderNotice",
        "datePublished": "2025-11-17T15:17:08Z"
      }
    ],
    "procedure": {
      "features": "The two-stage process is as described below:\nStage 1 PSQ\nThe Applicant is issued with a PSQ including instructions to Applicants, Requirements and a set of qualitative questions which are to demonstrate the Applicant’s:\n•\tCompliance\n•\tFinancial Capability\n•\tLegal Capability\n•\tHealth & Safety Approach\n•\tQuality Approach\n•\tSupply Chain Approach\n•\tQuality Approach\n•\tTechnical Capability and Experience\nCompleted PSQ should be submitted strictly in accordance with the instructions to Applicants described within the PSQ document and received by ABP no later than 12/12/2025 at 12:00 GMT.\nFor the avoidance of doubt, the Applicants are required to submit all documents requested to be included in all sections of the PSQ Response Document attached in Appendix 04 – PSQ Response Document to enable their PSQ submissions to be fully evaluated against the evaluation criteria. The evaluation criteria are also provided within the PSQ Response Document.\nStage 2 – Invitation to Tender (ITT)\nFollowing the conclusion of Stage 1 PSQ, down – selected Applicants will be invited to participate in the second stage of the process.\nStage 2 will comprise the issuing of the ITT to the successful down-selected applicants for each geographical Lot and sub Lot.\nClear objectives and evaluation criteria aligned to strategic goals will be included in the tender documents, inviting Applicants to demonstrate how their proposals will deliver broader organisational benefits.\nFollowing this stage, ABP will award Contract/s based on the Most Advantageous Tender, based on the evaluation criteria."
    },
    "legalBasis": {
      "id": "2023/54",
      "uri": "https://www.legislation.gov.uk/ukpga/2023/54/contents",
      "scheme": "UKPGA"
    },
    "techniques": {
      "frameworkAgreement": {
        "type": "closed",
        "method": "withAndWithoutReopeningCompetition",
        "description": "ABP will have the option to call-off contracts or engage in mini-competitions under the Framework Agreement with individual Applicants as and when services are required.  Please note however that there is no obligation for ABP to call off from the Framework Agreement (i.e. ABP may appoint work to parties outside of the Framework Agreement if necessary). \nLots 1A, 3A, 4A & 1C, 3C & 4C \nFor Lots 1A, 3A, 4A & 1C, 3C & 4C, any work awarded will use the NEC4 Term Service Contract and individual Task Orders will be issued accordingly by the Service Manager to instruct specific items of work within the scope of the contract. The schedule of rates submitted at tender stage will be used as the basis for pricing all Task Orders. \nLots 1B, 2B, 3B, 4B & Lot 5\nFor Lots 1B, 2B, 3B, 4B & Lot 5, work will be awarded in two ways; firstly, the results of a mini-competition with either price or price/quality being the assessment criteria. This will be defined during the publication of each individual request for quotation (Call off contract); or secondly, through a direct award. ABP reserves the right to make an award to any Contractor it feels will provide the required works most effectively.\nWork will be awarded through the framework using Work Orders (in line with the NEC4 Framework Contract). Each Work Order will be accompanied by an NEC4 Engineering & Construction Contract signed as a deed for Lots 1B, 2B, 3B, 4B & Lot 5.\nLot 2A \nFor Lot 2A, the work awarded will use the JCT Measured Term Contract. Each call-off will be instructed by the Employer under the agreed schedule of rates, ensuring transparency and consistency in pricing. This approach provides flexibility for recurring tasks while maintaining contractual certainty and compliance with JCT terms. \nCall of Procedures\nABP ultimately reserves the right, at its sole discretion, to utilise any of the following call-off procedures under the framework agreement, this applies to all Lots:\nMini-Competition\nA competitive process where all eligible Applicants on the Lot are invited to submit bids for a specific requirement. Evaluation is based on the criteria set out in the mini-competition documentation.\nDirect Award Procedure\nABP may award a contract directly to a Applicant without further competition. This is typically used where there is an urgent requirement or a clear best-fit Applicant."
      },
      "hasFrameworkAgreement": true
    },
    "awardPeriod": {
      "endDate": "2026-03-31T23:59:59+01:00"
    },
    "description": "ABP is looking to appoint suitably qualified contractors to our new Civils Framework.\nThe ABP Civils Framework is designed to provide access to pre-qualified civil engineering contractors across the Humber, Southampton, South Wales and East Anglia. Its scope encompasses a wide range of low to mid value construction and maintenance works, structured to support both operational efficiency and Small to Medium size Enterprise (SME) participation.\nThis Framework was shaped through extensive Applicant engagement, including Q&A sessions, face-to-face meetings, and questionnaires to refine the Lotting structure and address barriers to participation.",
    "enquiryPeriod": {
      "endDate": "2025-11-28T17:00:00+00:00"
    },
    "specialRegime": [
      "utilities"
    ],
    "aboveThreshold": true,
    "submissionTerms": {
      "languages": [
        "en"
      ],
      "electronicSubmissionPolicy": "allowed"
    },
    "procurementMethod": "selective",
    "mainProcurementCategory": "works",
    "submissionMethodDetails": "https://in-tendhost.co.uk/abp/aspx/Tenders/Current",
    "procurementMethodDetails": "Competitive flexible procedure",
    "expressionOfInterestDeadline": "2025-12-12T12:00:00+00:00"
  },
  "parties": [
    {
      "id": "GB-COH-ZC000195",
      "name": "ASSOCIATED BRITISH PORTS",
      "roles": [
        "buyer"
      ],
      "address": {
        "region": "UKI32",
        "country": "GB",
        "locality": "London",
        "postalCode": "WC2E 9ES",
        "countryName": "United Kingdom",
        "streetAddress": "25 Bedford Street"
      },
      "details": {
        "url": "https://in-tendhost.co.uk/abp/aspx/Tenders/Current",
        "classifications": [
          {
            "id": "privateUtility",
            "scheme": "UK_CA_TYPE",
            "description": "Private utility"
          }
        ]
      },
      "identifier": {
        "id": "ZC000195",
        "scheme": "GB-COH"
      },
      "contactPoint": {
        "name": "Daniel Murray",
        "email": "procurement@abports.co.uk"
      }
    }
  ],
  "language": "en",
  "initiationType": "tender"
}