Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Cyngor Gwynedd Council: "A55 UK Highways Ltd - Menai Suspension Bridge - Major Maintenance Painting 2023". Published status: active. Published value: Value not published. 1 published lot. Recorded submission deadline: 29 Oct 2021, 13:00 BST. See the official notice for participation instructions.
| Contracting Authority | Cyngor Gwynedd Council | Scope & Categories | Not published | Submission Window | Closed 29 Oct 2021, 13:00 BST |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Cyngor Gwynedd Council
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Cyngor Gwynedd Council. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
5.1Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 104 active published awards; 104 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityCyngor Gwynedd Council | Procedure methodNot published | Procurement categoryNot published |
Statusactive | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published29 Sept 2021, 12:35 BST | Last source update29 Sept 2021, 12:35 BST | Recurring procurementNo |
ClassificationConstruction work, Painting and protective-coating work of structures | ||
Delivery area | ||
OCIDocds-h6vhtk-02e5ea | ||
What is being bought
The project is to remove the existing corrosion protection system and apply a new system on the soffit of the Menai Suspension Bridge Deck and cantilevered steel footways, which also extend around the towers.
What changed
From the official release history
- Status changed to active
29 Sept 2021, 12:35 BST - Official notice release published
29 Sept 2021, 12:35 BST - Submission deadline changed to 29 Oct 2021, 13:00 BST
29 Sept 2021, 12:35 BST - Buyer information updated
29 Sept 2021, 12:35 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedactivePublished valueNot publishedThe project is to remove the existing corrosion protection system and apply a new system on the soffit of the Menai Suspension Bridge Deck and cantilevered steel footways, which also extend around the towers.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
29 Sept 2021, 12:35 BST - Submission deadline
29 Oct 2021, 13:00 BST
Commercial outcome and competition
AwardsNo award published |
ContractsNo contract published |
Bid statisticsNo aggregate bid statistics published |
Buyer and organisations in this procedure
Cyngor Gwynedd Council
Contracting authority GB-FTS-1561Documents (2)
Official links; attachments are not copied
Related procedures (0)
No related procedures published