VT3 Phase 3 A & B - Civil Engineering Works Contract
Harbour construction works
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: BELFAST HARBOUR COMMISSIONERS: "VT3 Phase 3 A & B - Civil Engineering Works Contract". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | BELFAST HARBOUR COMMISSIONERS | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: BELFAST HARBOUR COMMISSIONERS
Market Analytics
Derived from OCDS awards & bid statistics
Published history for BELFAST HARBOUR COMMISSIONERS. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
3Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 5 active published awards; 1 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityBELFAST HARBOUR COMMISSIONERS | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published21 Jun 2023, 14:22 BST | Last source update21 Jun 2023, 14:22 BST | Recurring procurementNot published |
ClassificationHarbour construction works | ||
Delivery area | ||
OCIDocds-h6vhtk-038440 | ||
What is being bought
The successful bidder shall supply, construct, and install all permanent works and all associated temporary works within an operational container terminal ("Works").
Please note that these works will be sequenced in 7 Phases and shall take place within an operational container terminal
The Works will include the following;
• Liaising, coordinating and co-operating with Irish Continental Group to ensure the Works are carried out in a safe manner within the operational terminal and cause as little disruption as possible to the ongoing operations.
• Laying of approximately 9,200m2 of pavement quality concrete
• Laying of approximately 7,928 m2 of hot rolled asphalt
• Laying of approximately 10,600m2 of gravel surfacing
• Installation of 450m of heavy-duty storm slot drains
• Installation of all other associated storm drainage
• Construction of 4nr reefer towers with piled foundations
• ISPS boundary and internal paladin fencing and gates
• Estimated programme for the works is 80 weeks
• M&E Services including HV and LV power networks, lighting, data connections and all associated civil engineering works including, ducting and chambers.
• Approximate length of HV cabling: 1350m
• Number of reefer towers to be connected: 4
What changed
From the official release history
- tender value changed
21 Jun 2023, 14:22 BST - Status changed to complete
21 Jun 2023, 14:22 BST - Official notice release published
21 Jun 2023, 14:22 BST - Submission deadline changed to published date
21 Jun 2023, 14:22 BST - Published value updated to £6,500,000
14 Nov 2022, 16:05 GMT - Status changed to active
14 Nov 2022, 16:05 GMT - Official notice release published
14 Nov 2022, 16:05 GMT - Submission deadline changed to 2 Dec 2022, 12:00 GMT
14 Nov 2022, 16:05 GMT - Buyer information updated
14 Nov 2022, 16:05 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedThe Works will include the following; • Liaising, coordinating and co-operating with Irish Continental Group to ensure the Works are carried out in a safe manner within the operational terminal and cause as little disruption as possible to the ongoing operations. • Laying of approximately 9,200m2 of pavement quality concrete • Laying of approximately 7,928 m2 of hot rolled asphalt • Laying of approximately 10,600m2 of gravel surfacing • Installation of 450m of heavy-duty storm slot drains • Installation of all other associated storm drainage • Construction of 4nr reefer towers with piled foundations • ISPS boundary and internal paladin fencing and gates • Estimated programme for the works is 80 weeks • M&E Services including HV and LV power networks, lighting, data connections and all associated civil engineering works including, ducting and chambers. • Approximate length of HV cabling: 1350m • Number of reefer towers to be connected: 4Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
21 Jun 2023, 14:22 BST - Award active
Not published · Not published - Contract active
Signed 12 Jun 2023, 00:00 BST · Not published
Commercial outcome and competition
Awards McGaffin Contracts Not published · Not published · active |
Contracts Contract Not published · signed 12 Jun 2023, 00:00 BST · active |
Bid statistics bids: 3 (lot 1) |
Buyer and organisations in this procedure
BELFAST HARBOUR COMMISSIONERS
Contracting authority GB-FTS-10198Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published