UK Manufacturing Technology for Next Generation Wind Turbines: Composites Phase 2B

Energy and related services
UK
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Department for Energy Security and Net Zero: "UK Manufacturing Technology for Next Generation Wind Turbines: Composites Phase 2B". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
Contracting AuthorityDepartment for Energy Security and Net ZeroScope & CategoriesNot publishedSubmission Window
complete
No deadline published
Submission GatewayDirect notice routeLegal Basis & RegimeStandard procurementEstimated Value (exc. VAT)Not published
Bidder Intelligence · Authority Profile: Department for Energy Security and Net Zero
Market Analytics
View Authority Profile →
Derived from OCDS awards & bid statistics
Published history for Department for Energy Security and Net Zero. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Requires at least 5 comparable procedures
Competition Density
3.7Bids / Report
44.4% of reports have one bid
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate available
Payment Terms
Check noticePublished terms
Payment obligations depend on the applicable regime and contract. Consult the official documents.
Coverage: 11 active published awards; 9 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Procedure methodNot published
Procurement categoryNot published
Statuscomplete
Framework / DPSNot published
CompetitionNot published
Above thresholdNot published
Legal basisNot published
Tender period startsNot published
Clarification deadlineNot published
Electronic submissionNot published
Submission languagesNot published
Published23 Oct 2023, 11:52 BST
Last source update23 Oct 2023, 11:52 BST
Recurring procurementNot published
ClassificationEnergy and related services
Delivery area
UK
OCIDocds-h6vhtk-03df67
What is being bought
Department for Energy Security and Net Zero has appointed the Offshore Renewable Energy Catapult (OREC) to carry out the work described in Section II.2.4 of this notice. OREC will work in close collaboration with the National Composites Centre (NCC) to deliver the scope of the project. OREC and NCC are members of the UK Catapult Network and are centres of excellence responsible for offshore wind and composite materials respectively. This collaboration is therefore a unique offering of all of the skills and capabilities needed to deliver this project.
What changed
From the official release history
  1. Official notice release published
    23 Oct 2023, 11:52 BST
  2. Buyer information updated
    23 Oct 2023, 11:52 BST
  3. Status changed to complete
    6 Jul 2023, 14:22 BST
  4. Official notice release published
    6 Jul 2023, 14:22 BST
  5. Buyer information updated
    6 Jul 2023, 14:22 BST
Lots and requirements (1)
Published by the contracting authority
  • Lot 1 · #1
    Individual lot title not published
    cancelled
    Published valueNot published
    Department for Energy Security and Net Zero has procured work under Phase 2B of the 'UK Manufacturing Technology for Next Generation Wind Turbines'. This is a continuation of Joule Phase 1, which investigated the potential for incorporating radically new composite-based components and lightweight designs in 20MW+ offshore wind turbines and Joule Phase 2, which developed more detailed design concepts for a range of composite components within an offshore wind turbine. Engagement with the industry during Phase 2 has highlighted a number of risks with progressing to openly tendered Phase 3, and this Phase 2B has been designed to address those risks and will further progress the technical design and verification of a composite tower product and establish the basis and strategy for the tower's potential commercial exploitation to best benefit the UK supply chain in the potential Phase 3.
    Contract periodNot published
    EligibilityNot published
    Options / renewalNot published
Timeline
  1. Procedure published
    23 Oct 2023, 11:52 BST
  2. Award active
    Not published · Not published
  3. Contract active
    Signed 23 Oct 2023, 00:00 BST · £4,700,000
Commercial outcome and competition
Awards
Offshore Renewable Energy Catapult Development Limited
Not published · Not published · active
Contracts
UK Manufacturing Technology for Next Generation Wind Turbines: Composites Phase 2B
£4,700,000 · signed 23 Oct 2023, 00:00 BST · active
Bid statistics
bids: 1 (lot 1)
Buyer and organisations in this procedure

Department for Energy Security and Net Zero

Contracting authority GB-FTS-94110
View buyer profile
  • Department for Energy Security and Net Zero
    buyer
    centralPurchasingBody
    reviewBody

    3-8 Whitehall Place, London, UK, SW1A 2EG
  • Offshore Renewable Energy Catapult Development Limited
    supplier

    Offshore House, Albert Street, Blyth, Northumberland, UK, NE24 1LZ
Documents (0)
Official links; attachments are not copied
No data
No linked documents are published
Related procedures (0)
No data
No related procedures published
Planning and rationale
Planning budgetNot published
No-engagement rationaleNot published
Procedure rationaleDepartment for Energy Security and Net Zero (DESNZ) was looking for a Delivery Partner (DP) with a number of characteristics, which would enable effective delivery of the scope of the programme. The DP is required to have deep technical expertise and operational knowledge in offshore wind and composite industries; ability to engage with the market and the supply chain in a neutral way. The Catapult network was set up to be neutral and in the benefit of UK PLC therefore OREC/NCC’s participation in a potential Phase 3 will remain neutral, fair and supports the applicants/successful suppliers in a non-competitive way. While developing the business case for this programme, DESNZ has considered various procurement route options. DESNZ market analysis was informed by holding a market engagement event to seek market input. The technical challenge of this programme is to apply the innovation in both the design and manufacturing of composite components in areas of the wind turbine systems, which have historically not utilised composites. The DESNZ market analysis has indicated that there is no single organisation able to deliver the niche yet demanding technical scope of Phase 2B, it also showed evidence that a consortium of OREC/NCC has the technical capability to deliver Phase 2B and that a different DP would likely have to subcontract OREC/NCC services to deliver the programme. NCC is the UK’s leading authority on the design and manufacture of composite structures, OREC is the UK’s leading authority on offshore wind, including the component design, validation and supply chain growth of the industry. The combination of the NCC and OREC represents the key technology areas required to deliver the programme, combining composite and offshore wind design, manufacturing and supply chain knowledge. The partnership is actively working on other composites / offshore wind programmes and previously delivered Phase 1 and Phase 2 of this programme. As defined by UK Government, the role of Catapults is to engage with industry to drive and support adoption of new technologies. OREC/NCC are technology and solution agnostic, they work with full supply chain without ties to particular suppliers or manufacturers and they are not-for-profit. The justification for the Single Tender Action (STA) is therefore that competition is absent due to technical reasons, and to provide the combination of skills, integration and neutrality a STA to OREC/NCC, is the most suitable procurement route to achieve the objectives and outcomes of Phase 2B of the programme.