Find a TenderAwarded
Published 22 Aug 2022, 17:42 BST

Official UK procurement notice

STEP Construction Partner (CP)

Official notice

Authority: United Kingdom Fusion Energy·Consortium: 3 public authorities

2 lotsWorksCompetitive dialogueMax 1 lot to bid
Published estimate£20,000,000,000total for 2 lots · 1 value update
Submissions closed 12 Jul 2024awarded 2 Apr 2026
Awarded to ILIOS

What is being bought2 lots · detail below

Published requirement description

UKIFS (now UKFE) has conducted this Procurement for a Construction Partner, who, together with a Fusion Partner (determined to be United Kingdom Atomic Energy Authority (UKAEA)), will bring together and develop extensive industrial capabilities to design and build a UK prototype fusion energy plant capable of delivering net-energy to the grid, and build a world-leading fusion delivery industry.

The Procurement was originally divided into two lots:

  • Lot 1: Engineering Partner (EP)
  • Lot 2: Construction Partner (CP)

However, Lot 1 – EP has since been cancelled. Lot 2 – CP is now the only Lot included in this Procurement exercise.

The contract term for Lot 2 will expire 31 March 2029, followed by three (3) optional extension periods of four (4), six (6) and seven (7) years.

UKFE will have the right to exercise an extension option at six (6) months’ notice. The maximum contract duration will be twenty (20) years with an estimated value of £10,000,000,000 across this period.

CPV: Advisory and consultative engineering services · Architectural, construction, engineering and inspection services · Architectural, engineering and planning services · Architectural, engineering and surveying services · Civil engineering consultancy services · Construction consultancy services · Construction management services · Construction project management services · Construction supervision services · Construction work for engineering works except bridges, tunnels, shafts and subways · Construction work for industrial buildings · Construction work for manufacturing plant · +27 more

Lots and requirements (2)Procurement structure

2 lots · all with a published value (£20,000,000,000 together) · a supplier may bid for at most 1 of them
Lot #1Engineering Partner (EP)RenewalPublished value£10,000,000,000

The Engineering Partner’s (EP) primary responsibility will be to provide the capability to drive the integrated design of the STEP Prototype Plant (SPP), and to then manufacture that plant through a developing supply chain. This includes (but not be limited to) providing capabilities for management of all engineering data, responsibility for the detailed design of SPP systems, equipment, and components, and contracting through the engineering supply chain. The EP will be responsible for leading a supply chain which delivers the manufacture and assembly of the SPP components. See the procurement documents for further details.

Delivery: UK
Extensions: The EP contract term will be an initial 3 year period, followed by 3 optional extension periods of 4, 6 and 7 years (these durations are subject to change as the Programme develops). UKIFS will have the right to exercise an extension option on 6 months’ notice. The maximum contract length duration for the EP contract will be 20 years with an estimated value of £10,000,000,000.Variant bids: not allowed
Lot #2Construction PartnerAwardedRenewalPublished value£10,000,000,000

The Construction Partner’s (CP) primary responsibility will be to collaboratively provide the capability to drive the integrated design of the overall layout, buildings, infrastructure, onsite and offsite facilities of the STEP Prototype Plant (SPP) to fulfil the support, enclosure and environmental requirements of the operational plant. The CP will then purchase, fabricate, deliver and install all elements of the designed facilities utilising existing and new supply chains, directly sourced or contracted resources. The CP’s responsibilities will include (but not be limited to) managing the overall health, safety, environment and security systems applicable to all parties engaged at the site. Additional information: Lot 1 for the Engineering Partner (EP) was cancelled and will not be awarded. Only Lot 2 for the Construction Partner (CP) forms part of this notice.

Delivery: UK
Extensions: The CP contract term will be an initial 3 year period, followed by 3 optional extension periods of 4, 6 and 7 years (these durations are subject to change as the Programme develops). UKIFS will have the right to exercise an extension option on 6 months’ notice. The maximum contract length duration for the CP contract will be 20 years with an estimated value of £10,000,000,000.Variant bids: not allowed

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
How bids were scored
Quality: 65%Price: 25%Social value: 10%
Published sub-criteria (6)
  • Corporate: Economic Value: 15%
  • Programme: 17%
  • Technical: 18%
  • Cultural: Behavioural and Collaborative Assessment: 15%
  • price: 25%
  • Corporate: Social Value: 10%
Lot distribution rule: UKAEA will apply bid restrictions. Please see the SSP for further details.
Conditions of participation1
  • Suitability

    Refer to Procurement Documents for information.

Successive reduction
Candidates will be reduced successively across stages
What this means for your bid
  • Price carries 25 of 100 points: a 10% discount moves about 2.5 points. The method statement decides this lot, not the discount.

Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.

Procedure terms & legal framework

From the official record · publisher note attached
Procedure method
Competitive dialogue
Legal basis
CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
Procurement category
Works
Notice status
Awarded
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Yes (GPA)
Recurring procurement
No (one-off requirement)
First published
22 Aug 2022, 17:42 BST
Last source update
22 Apr 2026, 12:28 BST
Authority reference
T-SP050-22
FTS notice number
2026/S 000-036554
Classification (CPV)
Advisory and consultative engineering servicesArchitectural, construction, engineering and inspection servicesArchitectural, engineering and planning servicesArchitectural, engineering and surveying servicesCivil engineering consultancy servicesConstruction consultancy servicesConstruction management servicesConstruction project management servicesConstruction supervision servicesConstruction work for engineering works except bridges, tunnels, shafts and subways
+29 moreConstruction work for industrial buildingsConstruction work for manufacturing plant
Delivery area
UK
Official registry OCID
ocds-h6vhtk-0361bf Find a Tender
Contract terms
Performance terms

Refer to Procurement Documents for information.

Review and risk notes
Review procedure

In accordance with the Public Contracts Regulations (PCR) 2015, the authority will observe a minimum ten (10) calendar day standstill period at the point that information regarding the award of the contract is communicated to tenderers.

If an appeal regarding the award of a contract has not been successfully resolved by the authority, the Public Contracts Regulations (PCR) 2015 provide for aggrieved parties who have been harmed or are at risk of harm by a breach of the Regulations to take action in the High Court (England, Wales and Northern Ireland).

Publisher note: UKAEA is launching this procurement on behalf of UK Industrial Fusion Solutions Limited (UKIFS). UKIFS will take over responsibility for running the procurement when it is established part way through the procurement process and will be the client entity that will enter into the contracts at the conclusion of the procurement.

How it was run

Official notice
Run through: EU-Supply (CTM) · Who buys & how to bid on EU-Supply
Public notice page · account needed to bidLanguage: EN
Access & registration note: Free · 5–10 minutes
Submission deadline
12 Jul 2024, 13:00 BST
Submission channel
{"electronicSubmission","written"}
Accepted languages
en
Detailed submission instructions & authority contactsFrom official release

Timeline

30 Apr 2023 → 22 Apr 2026 · 3 dates
  1. Next notice expected
    30 Apr 2023, 00:00 BST
  2. Submission deadline
    12 Jul 2024, 13:00 BST
  3. Notice published187 days ago
    22 Apr 2026, 12:28 BST

Notice history

7 events · 9 releases on Find a Tender · since 10 Nov 2022
  1. Published value updated to £20,000,000,000
    10 Nov 2022, 17:07 GMT
    was £10,000,000,000
  2. Status changed to active
    22 May 2024, 14:19 BST
  3. Procurement method changed
    22 May 2024, 14:19 BST
  4. Deadline published: 12 Jul 2024, 13:00 BST
    22 May 2024, 14:19 BST
  5. Buyer details updated
    22 May 2024, 14:19 BST
  6. Status changed to complete
    22 Apr 2026, 12:28 BST
  7. Buyer details updated
    22 Apr 2026, 12:28 BST
Published amendments (5 · 1 deadline change)
WhenWhatBeforeAfterShift
—TextShort Description · II.14—We will shortly be commencing pre-market engagement for this opportunity. If you would like to express an interest in participating, please refer to the details within the attached document located in EU Supply via the link in this notice.
—Text1.AEmail address updated[email protected]
—DeadlineExpression of Interest Date · Final26 Sept 202230 Sept 2023+369 d

Date extended to September 2023 for Pre - Market Engagement.

Revised Clarification Deadline now 2nd August 2024 at 1:00pm Revised SQ Deadline now 16th August 2024 at 1:00pm

SQ Response Deadline changed from 16/08/2024 at 1300hrs to 30/08/2024 at 1300hrs.

2 amendments published without a description.

Routine re-releases (9)
  • 2024-05: 1 release · 22 May 2024
  • 2023-04: 1 release · 18 Apr 2023
  • 2022-11: 1 release · 10 Nov 2022
  • 2022-08: 3 releases · 22 Aug 2022, 25 Aug 2022

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value Not summedvery large published value (£1bn+), not counted until verified; check the notice
Bids received 3
Contracts signed 1latest 2 Apr 2026
Awarded toValueDateStatus
Lot 2 · Construction Partner1 award
ILIOSSTEP Engineering Partner and Construction Partner£10,000,000,000 †very large published value · not counted until verified, check the notice—Awarded

Contracts

  • STEP Engineering Partner and Construction Partner · ILIOS

    Signed
    2 Apr 2026
    Value
    £10,000,000,000
    Status
    active

Bid statistics published by the authority

LotBidsSMEVCSEValid bid range
2 · Construction Partner3bids · 3 electronic0——

Contracting authority & participating public bodies

2 public bodies on the notice

United Kingdom Fusion Energy

Contracting authorityBody governed by public lawGeneral public services N/A Culham Campus, Abingdon, UK, OX14 3DBContact email

Consortium members and other public bodies

Dispute resolution & review bodies

  • The High CourtMediation bodyReview bodyReview contact point London

Bidders & participating suppliers

1 commercial party on the notice
  • ILIOSAwarded supplier1157281 2nd Floor, Optimum House, Clippers Quay, Salford, UK, M50 3XP

Official documents & specifications (2)

Official links; attachments are not copied

Tender pack and attachments

  • Economic and financial selection criteriatenderEconomic and financial selection criteria
  • Technical selection criteriatenderTechnical selection criteria