Find a Tender
complete
Official procurement procedure
SCAH Power Upgrades – PR27 Woodham Lane
Construction work for pipelines
communication and power lines
for highways
+3 more
UK
Published value
Not published
Submission deadline Not published
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: Defra Network eTendering Portal: "SCAH Power Upgrades – PR27 Woodham Lane". Published status: complete. Published value: Value not published. 1 published lot. Submission deadline not published. See the official notice for participation instructions.
| Contracting Authority | Defra Network eTendering Portal | Scope & Categories | Not published | Submission Window | complete No deadline published |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | Not published |
Bidder Intelligence · Authority Profile: Defra Network eTendering Portal
Market Analytics
Derived from OCDS awards & bid statistics
Published history for Defra Network eTendering Portal. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
Not availableInsufficient comparable data
Competition Density
4.1Bids / Report
Supplier ConcentrationNo estimate
Insufficient attributable awardsNo concentration estimate availablePayment Terms
Check noticePublished terms
Coverage: 280 active published awards; 270 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Procedure terms
Contracting AuthorityDefra Network eTendering Portal | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published5 Sept 2023, 14:19 BST | Last source update5 Sept 2023, 14:19 BST | Recurring procurementNot published |
ClassificationConstruction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork, Public utilities | ||
Delivery area UK | ||
OCIDocds-h6vhtk-03fa25 | ||
What is being bought
The Contract is for the connection of 43000kVA with a high level of resilience via dual feed 132/11kV substations from West Weybridge GSP and Laleham GSP. The connection provides Defra with its future electrical requirements at its site at Weybridge. The works are majority Non-Contestable works and comprise the elements set out under II.2.4.
What changed
From the official release history
- Status changed to complete
5 Sept 2023, 14:19 BST - Official notice release published
5 Sept 2023, 14:19 BST - Buyer information updated
5 Sept 2023, 14:19 BST
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcancelledPublished valueNot publishedThe Contract is for the connection of 43000kVA with a high level of resilience via dual feed 132/11kV substations from West Weybridge GSP and Laleham GSP. The works comprise the following:<br/>Works at GSP<br/>• Complete modification application (Mod App) with NG for increased load/new feeder at Laleham 132kV Grid. <br/>• Install 132kV sealing end installation and commissioning of the new 132kV feeder CB at Laleham GSP <br/>• Complete modification application (Mod App) with NG for increased load West Weybridge GSP with a 276MVA Transformer likely to require upgrade of SGT1 180MVA to a 240MVA <br/>• Install 1 x 132kV CB at West Weybridge GSP <br/>• Installation and commissioning of an Auto-Switching Scheme at West Weybridge GSP<br/>• Shutdowns<br/>• Wayleaves <br/>• Install and commission 4 x RTUs at the newly constructed Substations<br/>Upgrading SGT1 at West Weybridge<br/>• Install and commission SGT1 180MVA to a 240MVA<br/>Other Charges <br/>• Operation & Maintenance Charges<br/>• ECCR Charges <br/>Cable Route Works<br/>• Cable route feasibility Study <br/>• Excavation, installation of 132kV cable (single circuit) and reinstatement, (between Laleham GSP and Sub 1 on customer site), approximately 11km<br/>• Excavation, installation of 132kV cable (single circuit) and reinstatement, (between West Weybridge GSP and Sub 2 on customer site), approximately 2km<br/>Substation works<br/>• Install and commission a 60MVA dual wound 132/11kV transformer completed with ancillary plant, AVC, HV/LV protection panels, impedance earthing and Auxiliary transformers for both sub-stations. <br/>• Install and commission a 9 panel 11kV switchboard complete with ancillary plant including 48V DC/110V DC battery charger & RTU etc for the sub-stations.<br/>• Civil works including relating to the sub-stations.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
5 Sept 2023, 14:19 BST - Award active
Not published · Not published - Contract active
Signed 24 Oct 2022, 00:00 BST · £40,911,987
Commercial outcome and competition
Awards UK Power Networks Ltd Not published · Not published · active |
Contracts Contract £40,911,987 · signed 24 Oct 2022, 00:00 BST · active |
Bid statistics bids: 1 (lot 1) |
Buyer and organisations in this procedure
Defra Network eTendering Portal
Contracting authority GB-FTS-1944Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published
Planning and rationale
Planning budgetNot published |
No-engagement rationaleNot published |
Procedure rationaleThe Department for Environment, Food and Rural Affairs (Defra) has entered into an agreement with UKPN as Distribution Network Operator for the area, to reserve capacity for future electrical requirements at its site at Weybridge. This agreement includes the carrying out of necessary works for the provision of the electricity. <br/>The works are made up of majority Non-Contestable works, as such UKPN (as Distribution Network Operator for the area) are the only provider permitted to deliver these works. <br/>Further, given the high level of resilience, full 132 kV accreditation, security requirements, commercial agreement obligations, complex interface and programming criticality issues that exist for the project, UKPN are the sole provider that possess the technical ability to provide the works. |