Refurbishment and Upgrade of Calf of Eday Lighthouse
No classification published
Location not published
Published value
£330,000
Submission deadline 24 Feb 2026, 00:00 GMT
Lots published1
Procurement Executive Summary
AI & Search Synopsis
Generated from official OCDS record
Tenderline Synopsis: The Northern Lighthouse Board: "Refurbishment and Upgrade of Calf of Eday Lighthouse". Published status: complete. Published value: £330,000. 1 published lot. Recorded submission deadline: 24 Feb 2026, 00:00 GMT. See the official notice for participation instructions.
| Contracting Authority | The Northern Lighthouse Board | Scope & Categories | Not published | Submission Window | Closed 24 Feb 2026, 00:00 GMT |
|---|---|---|---|---|---|
| Submission Gateway | Direct notice route | Legal Basis & Regime | Standard procurement | Estimated Value (exc. VAT) | £330,000 |
Bidder Intelligence · Authority Profile: The Northern Lighthouse Board
Market Analytics
Derived from OCDS awards & bid statistics
Published history for The Northern Lighthouse Board. These figures describe retained records, not a forecast of bids or a measure of buyer bias.
Published-to-award variance
20.9%Historical Average
Competition Density
3.5Bids / Report
Supplier ConcentrationLow Concentration
Accted EngineeringTop vendor: 19.2% of attributable valuePayment Terms
Check noticePublished terms
Coverage: 36 active published awards; 25 bid reports (which may be per lot). Supplier values exclude multi-supplier awards, frameworks and DPS, and use GBP only. They are published award values, not payments. Published-to-award variance compares single-lot, single-award, single-supplier GBP procedures with explicitly non-framework/non-DPS status; increases remain in the average. Unpublished data stays unknown. Awarded suppliers are winners, not all bidders.
Historical Awarded Suppliers With This Authority:
| Supplier Name | Historic Awards | Attributable GBP Value |
|---|---|---|
| Accted Engineering | 2 wins | £600,000 |
| TRAC HLM Ltd | 2 wins | £362,764 |
| Accted Limited | 1 win | £303,640 |
| RS Merriman Limited | 1 win | £295,707 |
| George Leslie Ltd | 1 win | £247,122 |
Procedure terms
Contracting AuthorityThe Northern Lighthouse Board | Procedure methodNot published | Procurement categoryNot published |
Statuscomplete | Framework / DPSNot published | CompetitionNot published |
Above thresholdNot published | Legal basisNot published | Tender period startsNot published |
Clarification deadlineNot published | Electronic submissionNot published | Submission languagesNot published |
Published13 Mar 2026, 19:33 GMT | Last source update13 Mar 2026, 19:33 GMT | Recurring procurementNot published |
ClassificationNot published | ||
Delivery areaLocation not published | ||
OCIDocds-h6vhtk-060715 | ||
What is being bought
Description of Works
The Site
Location: Calf of Eday Minor Light is situated on the small island of Eday, to the Northeast of mainland Orkney (Latitude 59o 14.2’ N, Longitude 2o 45.7’ W).
Lighthouse Site: Access to the site is through an agreed right of access with the owner of Carrick Farm, Eday. This consists of a rough footpath through grazing fields (pasture and rough grazing), approx. 870m in length. The topography is relatively flat, with some sections of steeper ground across small burns. There are steep cliffs immediately to the seaward side of the access track.
On the landward side of the site, there is a small solar array bounded by a post and wire fence, and a set of concrete steps with galvanised steel handrail down to the lighthouse access walkway. This walkway itself is formed of galvanised steel which sits on stone piers.
The lighthouse itself is built on a concrete base within the intertidal zone and sits approximately 18.0m out from high tide level.
This project is to refurbish the lighthouse structure including replacement of the existing access ladder, balcony and lightroom with GRP equivalent, and full electrical re-work. There are minor repairs required to the existing access walkway and solar array.
Site Access
Due to the location of this site, the majority of materials and equipment will be transported to and from site via NLB Ship and Helicopter. See sections of NLB Helicopter manual for details of working with the helicopter included as an Appendix to the tender documents. There will additionally be a requirement to bring some sections of the new lightroom to site using a ‘multicat’ style low draught vessel with crane attachment.
The site can be accessed by boat, subject to local weather conditions, and on foot, as above. An agreement may be reached with the landowner regarding access through their fields using small ATVs, but this is not currently in place.
The Principal Contractor must also ensure that the condition of any access routes are monitored and any areas identified as hazardous are noted with details passed to their own employees, appointed sub-contractors, and all visiting NLB personnel. If necessary, suitable remedial and protective measures should be put in place to protect anyone on the site and the environment for the duration of the contract.
All materials for site establishment to be delivered to NLB Oban no later than 17 April 2026.
NLV Pharos and NLB Helicopter to deliver materials to site starting 28 April 2026, with block ending 3 May 2026, latest.
A mid-visit by NLV Pharos and NLB Helicopter is scheduled for 28-30 June 2026, inclusive.
Project works to be completed ahead of scheduled clearance by NLV Pharos and NLB Helicopter 29 August to 1 September 2026, inclusive.
Main elements of project as follows:
•Carry out full asbestos survey of buildings where work will take place
•Delivery of all plant/materials to site, and establish site
•Establishment of site camp, to include welfare and accommodation for site staff for duration of the project
•Erection of scaffolding or other suitable access to allow for works to existing lightroom
•Demolition and removal from site of existing lightroom, balcony and access ladder
•Template made of existing fixing holes in top of octagonal tower section
•Fabrication, delivery to site (using multicat vessel or other suitable means) and install of new GRP lightroom, aluminium balcony and access ladder
•Full electrical strip, including optic and solar panels, and install of new system
•Full internal and external redecoration of the tower, including removal of lightning conductor system
•Works to upgrade access bridge, including replacement of cross beams where corroded, infill of voids on masonry piers and replacement of some handrail elements
•Rewire of solar array boundary fence
•Demobilisation
Programme
All contractors must submit a detailed works programme, at tender stage, with a proposed work commencement date on site of 28 April 2026. We require flexibility on the programme to be able to cope with many variables including tides, weather etc. On award we agree a final programme of works.
It is important that Tenderers or their representative(s) attend the site visit, any Tenderers submitting a tender that have not attended the site visit, will not be considered. Site visits will be conducted on Wednesday 11 February 2026. Please request a site visit via Delta eSourcing attendance and names, mobile numbers of representatives attending site.
What changed
From the official release history
- tender value changed
13 Mar 2026, 19:33 GMT - Status changed to complete
13 Mar 2026, 19:33 GMT - Official notice release published
13 Mar 2026, 19:33 GMT - Submission deadline changed to published date
13 Mar 2026, 19:33 GMT - Published value updated to £330,000
15 Jan 2026, 19:06 GMT - Status changed to active
15 Jan 2026, 19:06 GMT - Official notice release published
15 Jan 2026, 19:06 GMT - Submission deadline changed to 24 Feb 2026, 00:00 GMT
15 Jan 2026, 19:06 GMT - Buyer information updated
15 Jan 2026, 19:06 GMT
Lots and requirements (1)
Published by the contracting authority
- Lot 1 · #1Individual lot title not publishedcompletePublished valueNot publishedThe source published no individual title or description for this lot.Contract periodNot publishedEligibilityNot publishedOptions / renewalNot published
Timeline
- Procedure published
13 Mar 2026, 19:33 GMT - Submission deadline
24 Feb 2026, 00:00 GMT - Award active
11 Mar 2026, 00:00 GMT · £303,640
Commercial outcome and competition
Awards Accted Limited £303,640 · 11 Mar 2026, 00:00 GMT · active |
ContractsNo contract published |
Bid statistics bids: 2 (lot 1) finalStageBids: 2 (lot 1) smeFinalStageBids: 2 (lot 1) vcseFinalStageBids: 0 (lot 1) |
Buyer and organisations in this procedure
The Northern Lighthouse Board
Contracting authority GB-PPON-PMGV-7529-QWXGAward and contract changes
Documents (0)
Official links; attachments are not copied
No linked documents are published
Related procedures (0)
No related procedures published