What is being bought
Published requirement descriptionThe award of a contract by Education Authority Northern Ireland (EANI) without prior publication of a call for competition in the Official Journal of the European Union, in respect of the continued provision of a Term Service Contract for Electrical Maintenance and Minor Works (Belfast Region) Lot 1 as further described in OJEU Contract Notice and as outlined in the previous VEATs issued on 28 May 2021, 15 April 2022, 13 December 2022, September 2023 and 8 February 2024.
CPV: Building construction work
The lotProcurement structure
single lot · no lot value publishedLot #1Provision of planned and responsive electrical maintenance and minor works to be…
Provision of planned and responsive electrical maintenance and minor works to be carried out in schools and associated facilities located in the Education Authority (Belfast Region) Area Lot 1.
Procedure terms & legal framework
From the official record · publisher note attached- Procedure method
- Award procedure without prior publication of a call for competition
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Works
- Notice status
- Awarded without competition
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Direct award (no call for competition)
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Unspecified in notice
- First published
- 8 Feb 2024, 19:09 GMT
- Last source update
- 28 Mar 2024, 19:09 GMT
- Authority reference
Belfast Electrical Lot 1- FTS notice number
2024/S 000-010446- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-043898Find a Tender
- Why no open competition
- The procurement falls outside the scope of application of the directive
- Published justification
To secure continuity, Task Orders issued on/after 1 July 2021 as per VEAT (2022/S 000-010138) are adjusted for inflation, calculated with the BCIS Measured Term Contract Updating Percentages. Inflation from mid-point of original contract to 31 March 2021 is: PSA SOR ELEC11 Rate A, Rate B/D/E, Rate C 7.6 pct, 14.1 pct and 13.9 pct respectively, applies to Sections 1, 2, 3 and 4 of Price List; Rate B/D/E applies to Section 3; PSA SOR MECH11 Rate A, Rate B/D/ E, Rate C 20.7 pct, 12.2 pct and 13.9 pct respectively, applies to Sections 1, 2 and 3; Rate B/D/E applies to Section 3; PSA SOR BCE09 14.3 pct applies to Section 4 Item OT010.370 to 460. Inflation after 1 April 2021 is changed in BCIS MTC Updating Percentages from 31 March 2021 indices based on TO issue date/latest published index. For travel expenses for Response Task Orders issued outside of Lot received on or after 1 June 2022, an additional amount for travel has been included.
It is the EA’s intention, upon receipt of compelling evidence, to consider the review of certain prices in the price lists for specific elements of which the impact of inflation is higher than what could have reasonably and diligently anticipated. This includes:
Copper cabling comprising HV/LV cables: standard power cables 600/1000V, armoured and armoured: fire resistant, sizes exceeding 500mm² one core, 185mm² two core, 120mm² three core and 95mm² four core (Rate A only), Copper cabling comprising HV/LV cables: standard power cables 1900/3300V, armoured, sizes exceeding 150mm² one core and 120mm² two core (Rate A only), Surface trunking: steel; standard; one / two compartment; size 50 x 50 / 75 x 75 / 100 x 50 / 100 x 100; including lids and extra over items, i.e. accessories (Rate A only), 600 / 1000 V: armoured insulated cable to BS 7846: fire resistant to BS 6387 category CWZ, BS EN 50200 PH60, BS 8434-1 30 minutes, BS EN 60332-1-2, BS EN 60332-3-24: low emission of smoke and corrosive gases when affected by fire to BS EN 61034-2,BS EN 60754-1 and 2; four core; size 10mm2 / 16mm2 / 25mm2 (Rate A only), Insulation; aluminium foil; joints sealed with tape and banded around pipe and fittings; all sizes / thickness (Rate A only), Flexible conduit; metallic; steel; size 20mm (Rate A only), Cable tray; perforated galvanised steel; plain flange edge; light / medium / heavy duty; width 50mm / 100mm / 150mm including ventilated cover and extra over items, i.e. accessories (Rate A only), Cable tray; wire basket; zinc plated steel; not exceeding 30mm deep / 30 to 60mm deep / 60 to 110mm deep; width 50mm / 100mm / 150mm; including extra over items, i.e. accessories (Rate A only), 450 / 750 V: wiring cable: insulated and sheathed flame retardant to BS EN 60332-1-2: low emission of smoke and corrosive gases when affected by fire to BS EN 61034-2 and BS EN 60754-1 and 2; single core to BS 7211: flame retardant to BS EN 60332-1-2; two / three / four core screened: flame retardant to BS EN 60332-1-2 and BS EN 60332-3-4: size 1.5mm2 or greater (Rate A only), 600 / 1000 V: armoured insulated cable to BS 7846: fire resistant to BS 6387 category CWZ, BS EN 50200 PH60, BS 8434-1 30 minutes, BS EN 60332-1-2, BS EN 60332-3-24: low emission of smoke and corrosive gases when affected by fire to BS EN 61034-2,BS EN 60754-1 and 2; 3 / 4 core; 1.5mm2 or greater (Rate A only), 600 / 1000 V: mains power cable: thermosetting insulated: steel wire armoured; three / four core; 6.0mm2 or greater (Rate A only) and Radiators: panel: steel; single and double convector; all sizes (Rate A only)
Publisher note: In applying for a price uplift in respect of these Exceptional items, the Contractor will have the choice to either claim the rates in the Price List applying the appropriate indexation percentage or claim under the Defined Costs. If the price of an Exceptional Item has been previously agreed, the Contractor may continue to claim at this rate. The Contractor is not required to produce evidence if they do not wish to avail of the Defined Costs. . . Regulation 72(1)(c) permits this extension due to unforeseen circumstances which a diligent contracting authority could not have foreseen and the overall nature of the contract is not altered. In particular, due to the inherent complexity of the procurement process, it is taking much longer than could have reasonably been anticipated and despite the best efforts of EANI, the process remains ongoing. . . In order to provide continued access to schools and the scale, complexity and nature of the construction works and possible duplication of costs it is not possible to change the current provider. Regulation 72(1)(b) further permits this as a change of provider: . (i) cannot be made for economic and technical reasons as requirements of interchangeability or interoperability of services procured under the original procurement and given the need to ensure continued access to EANI schools and facilities and could result in partial/total closure of schools; and . . (ii) will cause significant inconvenience and duplication of costs.
Notice history
1 event · 2 releases on Find a Tender- Buyer details updated28 Mar 2024, 19:09 GMT
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| Irwin ME LtdSME | £4,000,000 † | — | Awarded |
| Irwin ME LtdSME | £1 † | — | Awarded |
Contracts
Contract 010446-2024-1 · Irwin ME LtdSME
- Signed
- 28 Mar 2024
- Value
- £1
- Status
- active
Contract 004324-2024-1 · Irwin ME LtdSME
- Signed
- 8 Feb 2024
- Value
- £4,000,000
- Status
- active
Contracting authority & participating public bodies
2 public bodies on the noticeConsortium members and other public bodies
- Education AuthorityContracting authorityBody governed by public lawEducation
Dispute resolution & review bodies
- Official name: The UK does not have any special review body with responsibility for appeal/mediation procedures in public procurement competitionsReview body
- The UK does not have any special review body with responsibility for appeal/mediation procedures in public procurement competitionsReview body
Bidders & participating suppliers
1 commercial party on the notice- Irwin ME LtdAwarded supplier
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.